HomeMy WebLinkAbout1928 Devereux Drive - Approval LetterDocuSign Envelope ID: E7FE91C7-7249-49A7-99DD-70EEEDF2ABFE
�
CITY OF BURLINGAME
City Hall — 501 Primrose Road
Burlingame, California 94010-3997
June 3, 2022
Qing Gan
4973 Rio Vista Avenue
San Jose, CA 95129
Re: 1928 Devereux Drive
Dear Mr. Gan,
E, Cisv
r• +
,�. ; r .
- � ;;_°
�Y
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Division
PH:(650)558-7250
FAX: (650) 696-3790
Since there was no appeal to or suspension by the City Council, the May 23, 2022, Planning
Commission approval of your application for Design Review became effective June 2, 2022. This
application was for a first and second story addition to an existing single-unit dwelling at 1928 Devereux
Drive, zoned R-1.
The May 23, 2022, minutes of the Planning Commission state your application was approved with the
following conditions:
that the project shall be built as shown on the plans submitted to the Planning Division date
stamped May 12, 2022, sheets GO, A1.0 through A4.0, and site survey sheet;
2. that the existing nonconforming wall and foundation, located within the left side setback at 3'-3"
where 5'-0" is required per code and measuring 21'-0" in length, shall not be removed during
construction; if any wall studs or foundation, or both, along the existing nonconforming length are
removed during construction, either an application for a Side Setback Variance will be required to
replace the wall at the same location or an application for a Design Review Amendment will be
required showing compliance with current setback requirements;
3. that the existing nonconforming wall and foundation, located within the front setback (garage
wall) at 15'-3" where 35'-0" is required per code for a two-car attached garage and measuring
18'-0" in length, shall not be removed during construction; if any wall studs or foundation, or both,
along the existing nonconforming length are removed during construction, either an application
for a Front Setback Variance will be required to replace the wall at the same location or an
application for a Design Review Amendment will be required showing compliance with current
setback requirements;
4.
�
that any changes to building materials, exterior finishes, windows, architectural features, roof
height or pitch, and amount or type of hardscape materials shall be subject to Planning Division
or Planning Commission review (FYI or amendment to be determined by Planning staf�;
that prior to issuance of a building permit for construction of the project, the project construction
plans shall be modified to include a cover sheet listing all conditions of approval adopted by the
Planning Commission, or City Council on appeal; which shall remain a part of all sets of
CC Register online to receive City of Burlingame e-mail updates at www.burlingame.org ::
DocuSign Envelope ID: E7FE91 C7-7249-49A7-99DD-70EEEDF2ABFE
June 3, 2022
1928 Devereux Drive
Page 2
approved plans throughout the construction process. Compliance with all conditions of approval
is required; the conditions of approval shall not be modified or changed without the approval of
the Planning Commission, or City Council on appeal;
6. that any changes to the size or envelope of the first or second floors, or garage, which would
include adding or enlarging a dormer(s), shall require an amendment to this permit;
7. that any recycling containers, debris boxes or dumpsters for the construction project shall be
placed upon the private property, if feasible, as determined by the Community Development
Director;
8. that demolition for removal of the existing structures and any grading or earth moving on the site
shall not occur until a building permit has been issued and such site work shall be required to
comply with all the regulations of the Bay Area Air Quality Management District;
9. that prior to issuance of a building permit for construction of the project, the project construction
plans shall be modified to include a cover sheet listing all conditions of approval adopted by the
Planning Commission, or City Council on appeal; which shall remain a part of all sets of
approved plans throughout the construction process. Compliance with all conditions of approval
is required; the conditions of approval shall not be modified or changed without the approval of
the Planning Commission, or City Council on appeal;
10. that all air ducts, plumbing vents, and flues shall be combined, where possible, to a single
termination and installed on the portions of the roof not visible from the street; and that these
venting details shall be included and approved in the construction plans before a Building permit
is issued;
11. that the project shall comply with the Construction and Demolition Debris Recycling Ordinance
which requires affected demolition, new construction and alteration projects to submit a Waste
Reduction plan and meet recycling requirements; any partial or full demolition of a structure,
interior or exterior, shall require a demolition permit;
12. that the project shall meet all the requirements of the California Building and Uniform Fire Codes,
in effect at time of building permit submittal, as amended by the City of Burlingame;
THE FOLLOWING CONDITIONS SHALL BE MET DURING THE BUILDING INSPECTION
PROCESS PRIOR TO THE INSPECTIONS NOTED IN EACH CONDITION:
13. that prior to scheduling the framing inspection the applicant shall provide a certification by the
project architect or residential designer, or another architect or residential design professional,
that demonstrates that the project falls at or below the maximum approved floor area ratio for the
property;
14. that prior to scheduling the framing inspection the project architect or residential designer, or
another architect or residential design professional, shall provide an architectural certification that
the architectural details shown in the approved design which should be evident at framing, such
as window locations and bays, are built as shown on the approved plans; architectural
certification documenting framing compliance with approved design shall be submitted to the
Building Division before the final framing inspection shall be scheduled;
�� Register online to receive City of Burlingame e-mail updates at www.burlingame.org a�
DocuSign Envelope ID: E7FE91C7-7249-49A7-99DD-70EEEDF2ABFE
. �
June 3, 2022
1928 Devereux Drive
Page 3
15. that prior to scheduling the roof deck inspection, a licensed surveyor shall shoot the height of the
roof ridge and provide certification of that height to the Building Division; and
16. that prior to final inspection, Planning Division staff will inspect and note compliance of the
architectural details (trim materials, window type, etc.) to verify that the project has been built
according to the approved Planning and Building plans.
All site improvements and construction work will require a separate application to the Building Division.
This approval is valid for two years during which time a building permit must be issued (building
permit must be issued by June 2, 2024). One extension of up to one year may be considered by the
Community Development Director if a written application and filing fee is submitted to the Planning
Division at least 30 days prior to the expiration date of the initial Planning approval.
The decision of the Council is a final administrative decision pursuant to Code of Civil Procedure Section
1094.6. If you wish to challenge the decision in a court of competent jurisdiction, you must do so within
90 days of the date of the decision unless a shorter time is required pursuant to state or federal law.
Sincerely,
�.ui�n, �ar�i�n.t,V'
Kevin Gardiner, AICP
Community Development Director
c. Michael and Jing Liu, property owners
1928 Devereux Drive
Burlingame, CA 94010-464
Chief Deputy Valuation, Assessor's Office
(LOT 26 BLOCK 10 RAY PARK RSM 23/45 46 47 48; APN: 025-212-170)
File