HomeMy WebLinkAbout100 California Drive - Approval LetterCITY OF BURLINGAME
City Hall — 501 Primrose Road
Burlingame, California 94010-3997
June 3, 2011
Cheryl Putnam
3 California Drive
Burlingame, Ca 94010
� COMMUNITY DEVELOPMENT DEPARTMENT
r'�����
BURLINGAME Planning Division
PH: (650) 558-7250
���� FAX: (650) 696-3790
Re: Commercial Design Review — 100 California Drive
Dear Ms. Putnam,
Since there was no appeal to or suspension by the City Council, the May 23, 2011, Planning
Commission approval of your application for Commercial Design Review became effective June 2,
2011. This application was for changes to the faCade of an existing commercial building at 100
California Drive, zoned C-2, Subarea D, Burlingame Avenue Commercial Area.
The May 23, 2011 minutes of the Planning Commission state your application was approved with the
following conditions:
that the project shall be built as shown on the plans submitted to the Planning Division date
stamped April 15, 2011, sheets A.001 through A.004, A.101, A.201 through A.203, A.301
and D.201 and D.301; any changes to the exterior materials shall require review by the
Planning Commission;
2. that the conditions of the Chief Building Official's April 15, 2011 and September 28, 2010
memos, the City Engineer's April 25, 2011 and October 6, 2010 memos, the Fire Marshal's
and NPDES Coordinator's September 28, 2010 memos shall be met;
3. that any changes to the size or envelope of building, which would include changing or
adding exterior walls or parapet walls, shall require an amendment to this permit;
4. that any changes to building materials, exterior finishes, windows, architectural features,
roof height or pitch, and amount or type of hardscape materials shall be subject to Planning
Division or Planning Commission review (FYI or amendment to be determined by Planning
staf fl;
5. that demolition or removal of the existing structures and any grading or earth moving on the
site shall not occur until a building permit has been issued and such site work shall be
required to comply with all the regulations of the Bay Area Air Quality Management District;
C� Register online to receive City of Burlingame e-mail updates at www.burlingame.org �:
June 3, 2011
100 California Drive
Page 2
6. that prior to issuance of a building permit for construction of the project, the project
construction plans shall be modified to include a cover sheet listing all conditions of
approval adopted by the Planning Commission, or City Council on appeal; which shall
remain a part of all sets of approved plans throughout the construction process.
Compliance with all conditions of approval is required; the conditions of approval shall not
be modified or changed without the approval of the Planning Commission, or City Council
on appeal;
7. that the project shall comply with the Construction and Demolition Debris Recycling
Ordinance which requires affected demolition, new construction and alteration projects to
submit a Waste Reduction plan and meet recycling requirements; any partial or full
demolition of a structure, interior or exterior, shall require a demolition permit;
8. that the applicant shall comply with Ordinance 1503, the City of Burlingame Storm Water
Management and Discharge Control Ordinance;
9. that the project shall meet all the requirements of the California Building and Uniform Fire
Codes, 2010 Edition, as amended by the City of Burlingame;
THE FOLLOWING CONDITIONS SHALL BE MET DURING THE BUILDING INSPECTION
PROCESS PRIOR TO THE INSPECTIONS NOTED IN EACH CONDITION:
10. that prior to scheduling the framing inspection, the project architect, engineer or other
licensed professional shall provide architectural certification that the architectural details
such as window locations and bays are built as shown on the approved plans; if there is no
licensed professional involved in the project, the property owner or contractor shall provide
the certification under penalty of perjury. Certifications shall be submitted to the Building
Division; and
11. that prior to final inspection, Planning Division staff will inspect and note compliance of the
architectural details (trim materials, window type, etc.) to verify that the project has been
built according to the approved Planning and Building plans.
All site improvements and construction work will require separate application to the Building
Department. This approval is valid for three years during which time a building permit must be
issued. One extension of up to two years may be considered by the Planning Commission if
application is made before the end of the first year.
The decision of the Council is a final administrative decision pursuant to Code of Civil Procedure
Section 1094.6. If you wish to challenge the decision in a court of competent jurisdiction, you must
do so within 90 days of the date of the decision unless a shorter time is required pursuant to state or
�: Register online to receive City of Burlingame e-mail updates at www.burlingame.org �:
June 3, 2011
100 California Drive
Page 3
federal law.
Sincerely,
� j;i %
��/�
William Meeker
Community Development Director
c. Hugh Hynes, architect
Proto Architecture LLP
118 A Tiffany Avenue
San Francisco, CA 94110
100-198 California Drive LLC, property owner
3 California Drive
Burlingame, CA 94010
Chief Deputy Valuation, Assessor's Office
(PARCEL A 2.202 AC MOL PARCEL MAP VOL 60/52-53; APN: 029-233-080)
Chief Building Official, Community Development Dept./Building Div.
:v Register online to receive City of Burlingame e-mail updates at www.burlingame.org em