HomeMy WebLinkAbout1517 Howard Avenue - Approval LetterCITY OF BURLINGAME
BURLIN A,ME
City Hall — 501 Primrose Road.
Burlingame, California 94010-3997
January 26, 2009
Mark Robertson
918 E. Grant Place
San Mateo, CA
Re: 1517 Howard Avenue
Dear Mr. Robertson,
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Division
PH: (650) 558-7250
FAX: (650) 696-3790
Since there was no appeal to or suspension by the City Council, the January 12, 2009, Planning
Commission approval of your application for Design Review, Special Permit, and Conditional Use
Permit became effective January 23, 2009. This application was for a new, two story single family
dwelling at 1517 Howard Avenue, zoned R-1.
The January 12, 2009 minutes of the Planning Commission state your application was approved with
the following conditions:
that the project shall be built as shown on the plans submitted to the Planning Division date
stamped December 11, 2008, Sheets 1 through 8;
2. that any changes to building materials, exterior finishes, windows, architectural features,
roof height or pitch, and amount or type of hardscape materials shall be subject to Planning
Division or Planning Commission review (FYI or amendment to be determined by Planning
staff);
3. that if the structure is demolished or the envelope changed at a later date the Conditional
Use Permit, as well as any other exceptions to the code granted here, will become void;
4. that any changes to the size or envelope of the basement, first or second floors, or garage,
which would include adding or enlarging a dormer(s), shall require an amendment to this
permit;
5. that the conditions of the Chief Building Official's October 10, 2008 memo, the City
Engineer's October 16, 2008 memo, the Fire Marshal's October 13, 2008 memo, the City
Arborist's October 29, 2008 memo, and the NPDES Coordinator's October 17, 2008 memo
shall be met;
6. that demolition for removal of the existing structures and any grading or earth moving on
the site shall not occur until a building permit has been issued and such site work shall be
required to comply with all the regulations of the Bay Area Air Quality Management District;
®I Register online to receive City of Burlingame e-mail updates at www.burlingame.org IN
January 26, 2009
1517 Howard Avenue
Page 2
7. that prior to issuance of a building permit for construction of the project, the project
construction plans shall be modified to include a cover sheet listing all conditions of
approval adopted by the Planning Commission, or City Council on appeal; which shall
remain a part of all sets of approved plans throughout the construction process.
Compliance with all conditions of approval is required; the conditions of approval shall not
be modified or changed without the approval of the Planning Commission, or City Council
on appeal;
8. that all air ducts, plumbing vents, and flues shall be combined, where possible, to a single
termination and installed on the portions of the roof not visible from the street; and that
these venting details shall be included and approved in the construction plans before a
Building permit is issued;
9. that the project shall comply with the Construction and Demolition Debris Recycling
Ordinance which requires affected demolition, new construction and alteration projects to
submit a Waste Reduction plan and meet recycling requirements; any partial or full
demolition of a structure, interior or exterior, shall require a demolition permit;
10. that during demolition of the existing residence, site preparation and construction of the new
residence, the applicant shall use all applicable "best management practices" as identified
in Burlingame's Storm Water Ordinance, to prevent erosion and off -site sedimentation of
storm water runoff;
11. that the project shall meet all the requirements of the California Building and Uniform Fire
Codes, 2007 Edition, as amended by the City of Burlingame;
THE FOLLOWING CONDITIONS SHALL BE MET DURING THE BUILDING INSPECTION
PROCESS PRIOR TO THE INSPECTIONS NOTED IN EACH CONDITION:
12. that prior to scheduling the foundation inspection, a licensed surveyor shall locate the
property corners, set the building footprint and certify the first floor elevation of the new
structure(s) based on the elevation at the top of the form boards per the approved plans;
this survey shall be accepted by the City Engineer;
13. that prior to scheduling the framing inspection the project architect or residential designer,
or another architect or residential design professional, shall provide an architectural
certification that the architectural details shown in the approved design which should be
evident at framing, such as window locations and bays, are built as shown on the approved
plans; architectural certification documenting framing compliance with approved design
shall be submitted to the Building Division before the final framing inspection shall be
scheduled;
14. that prior to scheduling the roof deck inspection, a licensed surveyor shall shoot the height
of the roof ridge and provide certification of that height to the Building Department; and
15. that prior to final inspection, Planning Department staff will inspect and note compliance of
the architectural details (trim materials, window type, etc.) to verify that the project has been
built according to the approved Planning and Building plans.
o1 Register online to receive City of Burlingame e-mail updates at www.burlingame.org 111
January 26, 2009
1517 Howard Avenue
Page 3
Reimbursement of the Design Review deposit will be processed and will be mailed to the property
owner under separate cover.
All site improvements and construction work will require separate application to the Building
Department. This approval is valid for one year during which time a building permit must be issued.
One extension of up to one year may be considered by the Planning Commission if application is
made before the end of the first year.
The decision of the Council is a final administrative decision pursuant to Code of Civil Procedure
Section 1094.6. If you wish to challenge the decision in a court of competent jurisdiction, you must
do so within 90 days of the date of the decision unless a shorter time is required pursuant to state or
federal law.
Sincerely,
William Meeker
Community Development Director
c. Chief Deputy Valuation, Assessor's Office
(LOT 5 BLOCK 5 BURLINGAME PARK NO 2 RSM B/17; APN: 028-292-240)
Gerry and Orla Gallagher
1517 Howard Avenue
Burlingame, CA 94010
Chief Building Official, Community Development Dept./Building Div.
File
®: Register online to receive City of Burlingame e-mail updates at www.burlingame.org c�
Project Comments
Date: October 9, 2008
To: Y City Engineer
(650) 558- 7230
❑ Chief Building Official
(650) 558-7260
❑ City Arborist
(650) 558-7254
From: Planning Staff
❑ Recycling Specialist
(650) 558-7271
❑ Fire Marshal
(650) 558-7600
❑ NPDES Coordinator
(650) 342-3727
❑ City Attorney
Subject: Request for Design Review, Special Permit for garage length and
Conditional Use Permits for an accessory structure for a new two-
story single family dwelling and detached garage at 1517 Howard
Avenue, zoned R-1, APN: 028-292-240
Staff Review: Tuesday, October 14, 2008
1. See attached.
2. Sewer backwater protection certification is required. Contact Public Works —
Engineering Division at (650) 558-7230 for additional information.
3. This project is subject to the City policy to maximize the planter strip. The new
sidewalk is required to be constructed to the property line and transition to the
existing sidewalks on both adjacent properties. Both the site and landscape
plans need to be revised to meet this requirement.
Reviewed by: V V
Date: 10/16/2008
PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION
PLANNING REVIEW COMMENTS
Project Name: 2!f Li -I cr
Project Address: ts� I l�
The following requirements apply to the project
1 !J A property boundary survey shall be preformed by a licensed land
surveyor. The survey shall show all property lines, property corners,
easements, topographical features and utilities. (Required prior to the
building permit issuance.) 51-" L �
2 The site and roof drainage shall be shown on plans and should be made to
drain towards the Frontage Street. (Required prior to the building permit
issuance.) Ct f 5 px
3. The applicant shall submit project grading and drainage plans for
approval prior to the issuance of a Building permit.
4 The project site is in a flood zone, the project shall comply with the City's
flood zone requirements.
5 �_ AA-anitary sewer lateral Wt is required for the project in accordance with
the City's standards. ( )
6. The project plans shall show the required Bayfront Bike/Pedestrian trail
and necessary public access improvements as required by San Francisco
Bay Conservation and Development Commission.
7. Sanitary sewer analysis is required for the project. The sewer analysis
shall identify the project's impact to the City's sewer system and any
sewer pump stations and identify mitigation measures.
8 .. Submit traffic trip generation analysis for the project.
9. Submit a traffic impact study for the project. The traffic study should
identify the project generated impacts and recommend mitigation
measures to be adopted by the project to be approved by the City
Engineer.
10. The project shall file a parcel map with the Public Works Engineering
Division. The parcel map shall show all existing property lines, easements,
monuments, and new property and lot lines proposed by the map.
Pagel of 3
U:\private development\PLANNING REVIEW COMMEENTS.doc
PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION
11. A latest preliminary title report of the subject parcel of land shall be
submitted to the Public Works Engineering Division with the parcel map
for reviews.
12 Map closure/lot closure calculations shall be submitted with the parcel
map.
13 The project shall submit a condominium map to the Engineering Divisions
in accordance with the requirements of the Subdivision Map Act.
14 D The project shall, at its own cost, design and construct frontage public
improvements including curb, gutter, sidewalk and other necessary
appurtenant work.
15 The project shall, at its own cost, design and construct frontage streetscape
improvements including sidewalk, curb, gutters, parking meters and poles,
trees, and streetlights in accordance with streetscape master plan.
16 By the preliminary review of plans, it appears that the project may cause
adverse impacts during construction to vehicular traffic, pedestrian traffic
and public on street parking. The project shall identify these impacts and
provide mitigation measure acceptable to the City.
17 The project shall submit hydrologic calculations from a registered civil
engineer for the proposed creek enclosure. The hydraulic calculations
must show that the proposed creek enclosure doesn't cause any adverse
impact to both upstream and downstream properties. The hydrologic
calculations shall accompany a site map showing the area of the 100-year
flood and existing improvements with proposed improvements.
18 Any work within the drainage area, creek, or creek banks requires a State
Department of Fish and Game Permit and Army Corps of Engineers
Permits.
19 No construction debris shall be allowed into the creek.
20 'b The project shall comply with the City's NPDES permit requirement to
prevent storm water pollution.
21 The project does not show the dimensions of existing driveways, re-
submit plans with driveway dimensions. Also clarify if the project is
proposing to widen the driveway. Any widening of the driveway is subject
to City Engineer's approval.
22 The plans do not indicate the slope of the driveway, re -submit plans
showing the driveway profile with elevations
Page 2 of 3
UAprivate development\PLANNING REVIEW CON%1ENTS.doc
PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION
23 The back of the driveway/sidewalk approach shall be at least 12" above
the flow line of the frontage curb in the street to prevent overflow of storm
water from the street into private property.
24. For the takeout service, a garbage receptacle shall be placed in front. The
sidewalk fronting the store shall be kept clean 20' from each side of the
property.
25. For commercial projects a designated garbage bin space and cleaning area
shall be located inside the building. A drain connecting the garbage area to
the Sanitary Sewer System is required.
Page 3 of 3
Wprivate development\PLANNING REVIEW COMNMNTS.doe
Project Comments
Date: October 9, 2008
To: ❑ City Engineer
(650) 558-7230
X Chief Building Official
(650) 558-7260
❑ City Arborist
(650) 558-7254
From: Planning Staff
❑ Recycling Specialist
(650) 558-7271
❑ Fire Marshal
(650) 558-7600
❑ NPDES Coordinator
(650) 342-3727
❑ City Attorney
Subject: Request for Design Review, Special Permit for garage length and
Conditional Use Permits for an accessory structure for a new two-
story single family dwelling and detached garage at 1517 Howard
Avenue, zoned R-1, APN: 028-292-240
Staff Review: Tuesday, October 14, 2008
1) On the plans specify that this project will comply with the 2007 California Building Codes (CBC).
2) Anyone who is doing business in the City must have a current City of Burlingame business
license.
3) Provide fully dimensioned plans.
4) Show the distances from all exterior walls to property lines or to assumed property lines
5) When you submit your plans to the Building Division for plan review provide a completed
Supplemental Demolition Permit Application. NOTE: The Demolition Permit will not be issued
until a Building Permit is issued for the project.
6) Comply with the 2005 California Energy Efficiency Standards for low-rise residential / non-
residential buildings. Go to http://www.energy.ca.gov/title24 for publications and details.
7) Obtain a survey of the property lines for any structure within one foot of the property line.
8) On the plans specify that the roof eaves will not project within two feet of the property line.
9) Provide details on the plans which show that all roof projections which project beyond the point
where fire -resistive construction would be required will be constructed of one -hour fire -resistance -
rated construction per CBC 704.2.
10) Indicate on the plans that exterior bearing walls less than five feet from the property line will be
built of one -hour fire -rated construction. (Table 602)
11) Rooms that can be used for sleeping purposes must have at least one window or door that
complies with the egress requirements. Specify the size and location of all required egress
windows on the elevation drawings.
12) Provide guardrails at all landings. NOTE: All landings more than 30" in height at any point are
considered in calculating the allowable lot coverage. Consult the Planning Department for details
if your project entails landings more than 30" in height.
13) Provide handrails at all stairs where there are four or more risers.
14) Provide lighting at all exterior landings
Reviewe --- I Date: I o,L(o Lo p
Project Comments
Date: October 9, 2008
To: ❑ City Engineer
(650) 558-7230
❑ Chief Building Official
(650) 558-7260
eCity Arborist
(650) 558-7254
❑ Recycling Specialist
(650) 558-7271
❑ Fire Marshal
(650) 558-7600
❑ NPDES Coordinator
(650) 342-3727
❑ City Attorney
From: Planning Staff
Subject: Request for Design Review, Special Permit for garage length and
Conditional Use Permits for an accessory structure for a new two-
story single family dwelling and detached garage at 1517 Howard
Avenue, zoned R-'I, APN: 028-292-240
Staff Review: Tuesday, October 14, 2008
/ «s7E-G? __.._.!` t?E -.. EAiova C.,Pee2--W! 0c 2 E ZD .. .
_. .fd2.k�-.../2�•��C �F .7�-�.-. .7- sitE
Reviewed by: Date: 7 0ld. �/
Project Comments
Date: October 9, 2008
To: ❑ City Engineer
(650) 558-7230
❑ Chief Building Official
(650) 558-7260
❑ City Arborist
(650) 558-7254
From: Planning Staff
❑ Recycling Specialist
(650) 558-7271
Fire Marshal
(650) 558-7600
❑ NPDES Coordinator
(650) 342-3727
❑ City Attorney
Subject: Request for Design Review, Special Permit for garage length and
Conditional Use Permits for an accessory structure for a new two-
story single family dwelling and detached garage at 1517 Howard
Avenue, zoned R-1, APN: 028-292-240
Staff Review: Tuesday, October 14, 2008
Designer should utilized current IBC/IFC code language — Group U-1 and Type VN
no longer exist in the code.
Provide a residential fire sprinkler throughout the residence.
1. Provide a minimum 1 inch water meter.
2. Provide backflow prevention device/double check valve assembly —
Schematic of water lateral line after meter shall be shown on Building
Plans prior to approval indicating location of the device after the split
between domestic and fire protection lines.
3. Drawings submitted to Building Department for review and approval shall
clearly indicate Fire Sprinklers shall be installed and shop drawings
shall be approved by the Fire Department prior to installation.
Reviewed by:
Date:�y 7-
Project Comments
Date: October 9, 2008
To: 001 City Engineer
(650) 558-7230
01 Chief Building Official
(650) 558-7260
000, City Arborist
(650) 558-7254
From: Planning Staff
Recycling Specialist
(650) 558-7271
Fire Marshal
(650) 558-7600
✓
NPDES Coordinator
(650) 342-3727
City Attorney
Subject: Request for Design Review, Special Permit for garage length and
Conditional Use Permits for an accessory structure for a new two-
story single family dwelling and detached garage at 1517 Howard
Avenue, zoned R-1, APN: 028-292-240
Staff Review: Tuesday, October 14, 2008
Any construction project in the City, regardless of size, shall comply with the City's
NPDES permit requirement to prevent stormwater pollution from construction
activities. Project proponent shall ensure all contractors implement Best
Management Practices (BMPs) during construction.
Include a list of BMPs and erosion and sediment control measure plan as project
notes when submitting plans for a building permit. Please see attached brochures
for guidance.
Reviewed by: �f Date: 10/17/2008