HomeMy WebLinkAbout1813 Castenada Drive - Approval Letter��� CITY O�
BURLINGAME
q,
�1►ATm JYNE b•
The City of Burlingame
CITY HALL 501 PRIMROSE ROAD TEL: (650) 558-7250
PLANNING DEPARTMENT BURLINGAME, CALIFORNIA 94010-3997 FAX: (650) 696-3790
February 4, 2005
Lincoln Lue
1567 33rd Avenue
San Francisco, CA 94122
Dear Mr. Lue,
Since there was no appeal to or suspension by the City Council, the January 24, 2005, Planning Commission
approval of your application for design review and hillside area construction permit became effective February 3,
2005. This application was to allow for a first and second story addition at,,,$#13 Castenada Drive, zoned R-1.
The January 24, 2005 minutes of the Planning Commission state your application was approved with the
following conditions:
that the project shall be built as shown on the plans submitted to the Planning Department date stamped
January 11, 2005, sheets Al through A5, and that any changes to building materials, exterior finishes,
footprint or floor area of the building shall require an amendment to this permit;
2. that any changes to the size or envelope of the first or second floors, or garage, which would include
adding or enlarging a dormer(s), moving or changing windows and architectural features or changing the
roof height or pitch, shall be subject to Planning Commission review;
3. that prior to scheduling the framing inspection, the project architect, engineer or other licensed
professional shall provide architectural certification that the architectural details such as window
locations and bays are built as shown on the approved plans; if there is no licensed professional involved
in the project, the property owner or contractor shall provide the certification under penalty of perjury.
Certifications shall be submitted to the Building Department;
4. that prior to final inspection, Planning Department staff will inspect and note compliance of the
architectural details (trim materials, window type, etc.) to verify that the project has been built according
to the approved Planning and Building plans.
5. that prior to scheduling the roof deck inspection, a licensed surveyor shall shoot the height of the roof
ridge and provide certification of that height to the Building Department;
6. that all air ducts, plumbing vents, and flues shall be combined, where possible, to a single termination
and installed on the portions of the roof not visible from the street; and that these venting details shall be
included and approved in the construction plans before a Building permit is issued;
February 4, 2005
1813 Castenada Drive
Page 2
7. that the conditions of the City Engineer's, Fire Marshal's and Recycling Specialist's June 7, 2004, memos
shall be met;
8. that the project shall meet all the requirements of the California Building and Uniform Fire Codes, 2001
Edition, as amended by the City of Burlingame; and
9. that the applicant shall comply with Ordinance 1503, the City of Burlingame Storm Water Management
and Discharge Control Ordinance.
All site improvements and construction work will require separate application to the Building Department. This
approval is valid for one year during which time a building permit must be issued. One extension of up to one
year may be considered by the Planning Commission if application is made before the end of the first year.
The decision of the Council is a final administrative decision pursuant to Code of Civil Procedure Section
1094.6. If you wish to challenge the decision in a court of competent jurisdiction, you must do so within 90 days
of the date of the decision unless a shorter time is required pursuant to state or federal law.
Sincerely yours,
�&-qmAYI
Margaret Monroe
City Planner
c. Mark and Amy Liew, property owners
1813 Castenada Drive
Burlingame, CA 94010
Chief Building Inspector
'C- Inef Deputy Valuation, Assessor's Office
(LOT 7 BLOCK 35 MILLS ESTATE NO 9 RSM 46/33 34 CITY OF BURLINGAME; APN: 025-051-070)