PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
PROPERTY ADDRESS: 300 Airport Boulevard
APN: 026-350-130
APPLICANT/ARCHITECT/DESIGNER: Genzon Investment Group (Applicant), Gensler (Architect)
PROPERTY OWNER: Burlingame Point LLC
7-
GENERAL PLAN/ZONING: Commercial Uses: Office Use; Bayfront
Specific Plan Anza Point Area; Anza Point North (APN) Zoning
LOT AREA: 18.13 AC
PROJECT DESCRIPTION
Burlingame Point is a proposed office/life science campus consisting of four office buildings and an
amenities building with a total of 767,000 square feet of floor area on an 18.13 acre site located at 300
Airport Boulevard. The application was approved by the City Council on June 18, 2012.
The project consists of two 5-story buildings, one 7-story building, one 8-story building and a 2-story
amenities building. Parking will be provided in a five -story parking structure, in a podium level parking
area below the four office buildings, and in smaller parking lots scattered throughout the site. Airport
Boulevard will be realigned through the project site. The project also includes public access
improvements along the San Francisco Bay frontage and along Sanchez Channel. The site is currently
vacant, and formerly contained the Burlingame Drive -In Theater, which was demolished about fifteen
years ago.
On August 22, 2016 the Planning Commission reviewed and approved a Design Review Amendment
application and Environmental Impact Report (EIR) Addendum to allow design refinements to the
previously approved project. The revisions to the design included adjustments to building locations and
footprints, changes to building forms and architectural treatments, and refinements to the configuration of
amenities and open spaces.
On November 27, 2017 the Planning Commission approved a Design Review Amendment to allow
removal of the private rooftop terraces on two of the four office buildings to provide additional space for
rooftop mechanical equipment.
REQUEST FOR AMENDMENTS TO CONDITIONS OF APPROVAL
The applicant is seeking approval of amendments of the Conditions of Approval to accommodate
anticipated specifications of a single tenant for the project. Please refer to the letter from the applicant,
dated August 2, 2018 (attached).
1
SURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
There would be no significant changes to the physical design of the buildings. The amendments are
particular to the use and allocation of the food service and retail uses, and to the Transportation Demand
Management (TDM) provisions, in both instances to better match the operational characteristics of a
single -tenant user. Although the amendments do not involve the design of the project, technically the
amendment would be a Commercial Design Review Amendment because the conditions of approval are
situated within the Commercial Design Review permit.
The amendments to the conditions of approval would not preclude occupation by multiple tenants, either
at completion of the project or in the future. While the amendments are intended to address the
anticipated operational characteristics of a single -tenant user, the existing provisions for a multiple -tenant
scenario would continue to remain in the conditions of approval for that circumstance.
Requested Modification to Condition #6: The applicant requests provisions be added to Condition #6 to
accommodate the anticipated food and services characteristics of a single -tenant scenario. Please refer
to the letter from the applicant, dated August 2, 2018 (attached) for a discussion of the request.
Condition #6 currently reads as follows:
that the project shall include approximately 6,655 square feet of retail use and 19,750
square feet of food service use that may be located in buildings B1, B2 and the
amenities building, and Developer shall use its best commercial efforts to lease this
space for retail or food service, including recreation -related uses such as bike rentals,
and interactive educational space, as the case may be, for two years following issuance
of the final certificate of occupancy for each building. Thereafter, any change to the use
of the space designated for retail, recreation -related or food service use shall be
reviewed and approved by the Planning Commission using the process set out in
Municipal Code Sections 25.16.040 through 25.16.085, using the conditional use permit
findings as the standard of review,
Should the Planning Commission be agreeable to the applicant's request for provisions to accommodate
a single -tenant scenario, the existing text would remain and text to the effect of the following could be
added to the condition:
Notwithstandina the above requirements, which are applicable in the event the proiect is
occupied by multiple tenants if the entire proiect is leased to a single tenant, then that
tenant shall provide a minimum of approximately 26,400 square feet of food service
uses and other convenience goods and services to its employees and invited quests
which may be located in buildings B1 B2 or the amenities building. In addition to this
space the project shall use its best commercial efforts to provide a minimum of 1,600
2
$R
Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6
Meeting Date: August 13, 2018
ACTION ITEM
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION
Item No: 8(b)
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
sauare feet of space in buildings B1 or B2 (facing the shoreline) for public-servin
amenities which may include food/beverage service and other retail services to serve
recreational users of the Bay Trail and members of the public. Such public amenities are
encouraged to be provided and open for business on days and times when substantial
use alonq the shoreline is anticipated including weekends and holidays and are
required to provide restrooms accessible to the public. If after two years of operation the
tenant has evidence that the demand for the public amenities is so limited as to justify
discontinuing such services it may request a change of use. Any significant change of
use of the public amenity space or request to discontinue services shall be reviewed and
approved by the Planning Commission.
As noted in the applicant letter, and in the suggested wording for the condition of approval above, in a
single -tenant scenario the applicant is proposing a minimum of 800 square feet of space in each of
buildings B1 and B2 (facing the shoreline) for public -serving amenities (for a total of 1,600 square feet),
which may include food/beverage service and other retail services to serve recreational users of the Bay
Trail and members of the public. For reference, 800 square feet is comparable to the "ready -to -eat food
shop" category in the Burlingame Zoning Code (Code Section 25.08.550-1). Examples of establishments
classified as ready -to -eat food shops include Jougert Bar at 1115 Burlingame Avenue (951 square feet),
and the recently approved Tuna Kahuna at 1117 Burlingame Avenue (810 square feet).
While the applicant has proposed two 800 square foot spaces in separate buildings, the suggested
wording of the condition is broader in that it would not preclude a single, larger 1,600 square foot space.
For reference, a 1,600 square foot space would be slightly larger that Peet's Coffee & Tea at 1241
Burlingame Avenue (1,205 square feet) or Phliz Coffee at 305 Primrose Road (1,375 square feet).
Requested Modification to Condition #21: The applicant requests modifications to Condition #21 to allow
greater flexibility in the selection of Transportation Demand Management (TDM) components, provided
overall trip -reduction performance meets or exceeds those specified in the original approval. Given the
evolving nature of TDM since the original program for the project was approved in 2011 and into the
future, an amendment could be beneficial for either a single- or multiple -tenant scenario provided the
originally intended trip -reduction targets are met (or exceeded).
Condition #21 currently reads as follows:
that the property owner shall comply with the Transportation Demand Management
Program prepared by Fehr and Peers for 350 Beach Road, LLC dated April 6, 2011
including the following measures:
3
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
a. Secure Bicycle Storage: Secure, indoor bicycle storage for at least 26 bicycles shall
be provided in a lobby or garage level room within each of the four office buildings. In
addition, bicycle racks for up to 50 bicycles will be located outside of Buildings #1 or
#4.
b. Showers and Changing Rooms: Shower facilities with changing rooms shall be
provided throughout the site, with access available to all employees. Shower facilities
(two men's and two women's) and changing rooms (one men's and one women's)
shall be provided in each of the four office buildings, the amenities center shall
include 12 showers and two changing rooms.
c. Shuttle Service: Coordinate with the Peninsula Commuter Alliance to add two stops
within the project site to the existing commuter shuttle from the Millbrae Intermodal
Station. The shuttle provides 10-minute headways during peak periods.
d. Carpool Parking: Provide 15 preferential parking spaces for carpools at each of the
four office buildings.
e. Vanpool Parking: Provide two preferential parking spaces for vanpools at each of the
four office buildings.
f. Commute Assistance Center:
1) Provide an on -site one -stop shopping for transit and commute alternatives
information.
2) Provide a part-time on -site TDM coordinator available to assist building
tenants with trip planning.
g. Employees' Surveys: The TDM coordinator shall develop and administer two surveys
per year to examine TDM program participation and best practices.
h. Video Conferencing Center: One video conferencing center of approximately 8500 sf
shall be installed for use by the tenants of the facility.
i. On -Site Amenities/Accommodations: On -site amenities, including banking, retail,
delivery dry cleaning, exercise facilities, child care center, delivery pharmacy and
food service shall be provided at the project site to encourage people to stay on site
during the work day;
f On -Site Bicycles for Employee Use- Bicycles shall be provided at each office
building. Employees will have access to bicycles during breaks for personal or
business use.
k. Child Care Services: Child care center service shall be provided on site;
L Guaranteed Ride Home Program: Employees will have access to the Guaranteed
Ride Home (GRH) program administered by the Peninsula Congestion Relief
Alliance (Alliance) for emergencies. The program provides vouchers for taxicabs
or rental cars for this purpose.
4
9URLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
m. Transportation Action Plan: The TDM coordinator shall work with the Alliance to
create a Transportation Action Plan for each tenant.
n. Transportation Management Association: If the office park has multiple tenants, each
tenant shall provide a representative to form a Transportation
Management Association and be a liaison to the TDM Coordinator.
o. Coordination of Transportation Demand Management Programs: The TDM
coordinator shall coordinate with other TDM programs with existing
developments/employers in the surrounding area.
p. Subsidy for Transit Tickets: Employers shall offer subsidies to employees to
compensate them for the cost of transit tickets.
q. Electric Vehicle Stations: The applicant shall provide plug-in stations for electric
vehicles.
r. House Car for Employee Use: Each building will provide employees with access to a
"house car" for use during the day.
Should the Planning Commission be agreeable to the applicant's request for provisions to allow flexibility
in the specific elements of the TDM program, the list of the various elements would remain but the first
paragraph of the condition could be replaced with text to the effect of the following:
that the Proaerty Owner in the event the Propertv is leased to multiple tenants, or the
tenant in the event that the entire Property is leased to a sole tenant, shall implement a
comprehensive transportation demand management (TDM) program to the satisfaction
of the Community Development Director in order to achieve the same or greater peak
hour trip reductions as the TDM Program prepared by Fehr and Peers for 350 Beach
Road LLC dated April 5 2011. Such TDM Program may include measures such as:
Commercial Design Review: Although the amendments do not involve the design of the project,
technically the amendment would be a Commercial Design Review Amendment because the conditions
of approval are situated within the Commercial Design Review permit.
Design Review Criteria: For reference, criteria for Commercial Design Review as established in
Ordinance No. 1652 adopted by the Council on April 16, 2001 are outlined as follows:
1. Support of the pattern of diverse architectural styles that characterize the city's commercial areas;
5
BURLtNGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
2. Respect and promotion of pedestrian activity by placement of buildings to maximize commercial
use of the street frontage, off-street public spaces, and by locating parking so that it does not
dominate street frontages;
3. On visually prominent and gateway sites, whether the design fits the site and is compatible with
the surrounding development;
4. Compatibility of the architecture with the mass, bulk, scale, and existing materials of existing
development and compatibility with transitions where changes in land use occur nearby;
5. Architectural design consistency by using a single architectural style on the site that is consistent
among primary elements of the structure, restores or retains existing or significant original
architectural features, and is compatible in mass and bulk with other structure in the immediate
area; and
6. Provision of site features such as fencing, landscaping, and pedestrian circulation that enriches
the existing opportunities of the commercial neighborhood.
Environmental Review Status: The project is Categorically Exempt from review pursuant to the
California Environmental Quality Act (CEQA), per Section 15301 (a) of the CEQA Guidelines, which
states that interior or exterior alterations to existing structures are exempt from environmental review. In
this instance, the approved project is considered an existing structure for purposes of CEQA. An
Environmental Impact Report (EIR) was prepared for the initial approval in 2012, and an EIR Addendum
was prepared for the Design Review Amendment approved in 2016. The proposed amendments to the
Conditions of Approval would be consistent with the analyses contained in the EIR and EIR Addendum.
PLANNING COMMISSION ACTION
The Planning Commission should hold a public hearing. Affirmative action should be by resolution and
include findings for accepting the Amendment to the Conditions of Approval contained in the Commercial
Design Review Permit. The reasons for any action should be clearly stated for the record.
The proposed Conditions of Approval are unchanged from those approved by the Planning Commission
on November 27, 2017 except for an amendment to Condition of Approval #6 to address the allocation of
the food service and convenience uses, and to Condition of Approval #21 to address Transportation
Demand Management (TDM) provisions (edits shown in tracked changes).
At the public hearing the following mitigation measures and conditions should be considered:
I.
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (`BURLINGAME POINT")
that the project shall be built as shown on the plans submitted to the Planning Division and date
stamped July 29, 2016, Sheets: COVER SHEET; 1 GENERAL PROJECT INFORMATION; 2 SITE
PLAN; 3 B1 CONSTRUCTION PLAN; 4 LANDSCAPE SITE SECTIONS - EAST CAMPUS; 5
LANDSCAPE SITE SECTIONS - WEST CAMPUS; 6 L1 CONSTRUCTION PLAN - BUILDING 01; 7
L3 CONSTRUCTION PLAN - BUILDING 01; 8 ROOF CONSTRUCTION PLAN - BUILDING 01; 9 L1
CONSTRUCTION PLAN - BUILDING 02; 10 L3 CONSTRUCTION PLAN - BUILDING 02; 11 ROOF
CONSTRUCTION PLAN - BUILDING 02; 12 L1 CONSTRUCTION PLAN - BUILDING 03; 13 L3
CONSTRUCTION PLAN - BUILDING 03; 14 L5 CONSTRUCTION PLAN - BUILDING 03; 15 ROOF
CONSTRUCTION PLAN - BUILDING 03; 16 L1 CONSTRUCTION PLAN - BUILDING 04; 17 L3
CONSTRUCTION PLAN - BUILDING 04; 18 L5 CONSTRUCTION PLAN - BUILDING 04; 19 ROOF
CONSTRUCTION PLAN - BUILDING 04; 20 EXTERIOR ELEVATIONS - BUILDING 01; 21
EXTERIOR ELEVATIONS - BUILDING 01; 22 EXTERIOR ELEVATIONS - BUILDING 02; 23
EXTERIOR ELEVATIONS - BUILDING 02; 24 EXTERIOR ELEVATIONS - BUILDING 03; 25
EXTERIOR ELEVATIONS - BUILDING 03; 26 EXTERIOR ELEVATIONS - BUILDING 03; 27
EXTERIOR ELEVATIONS - BUILDING 03; 28 EXTERIOR ELEVATIONS - BUILDING 04; 29
EXTERIOR ELEVATIONS - BUILDING 04; 30 EXTERIOR ELEVATIONS - BUILDING 04; 31
EXTERIOR ELEVATIONS - BUILDING 04; 32 BUILDING SECTIONS - BUILDING 01 & 02; 33
BUILDING SECTIONS - BUILDING 03; 34 BUILDING SECTIONS - BUILDING 03; 35 BUILDING
SECTIONS - BUILDING 04; 36 BUILDING SECTIONS - BUILDING 04; 37 L1 CONSTRUCTION
PLAN — GARAGE; 38 EXTERIOR ELEVATIONS - BUILDING 05 GARAGE; 39 EXTERIOR
ELEVATIONS - BUILDING 05 GARAGE; 40 BUILDING SECTION — GARAGE; 41 L1
CONSTRUCTION PLAN - AMENITY BUILDING; 42 L2 CONSTRUCTION PLAN - AMENITY
BUILDING; 43 ROOF CONSTRUCTION PLAN - AMENITY BUILDING; 44 EXTERIOR ELEVATIONS
- AMENITY BUILDING; 45 OVERALL GRADING PLAN; 46 OVERALL UTILITY PLAN; with
amendments to Buildings 3 and 4 as indicated on plans submitted to the Planning Division and date
stamped October 5, 2017.
2. that prior to building permit issuance the applicant shall return to the Planning Commission with the
following FYIs:
a. a complete landscape plan indicating size, species, quantities and locations of all plantings; and
b. analysis of compliance with Complete Streets provisions;
3. that any changes to the size or envelope of building, which would include changing or adding exterior
walls or parapet walls, shall require an amendment to this permit;
4. that any changes to building materials, exterior finishes, windows, architectural features, roof height or
pitch, and amount or type of hardscape materials shall be subject to Planning Division or Planning
Commission review (FYI or amendment to be determined by Planning staff);
5. that the project shall include installation and maintenance of the Bay Trail and Sanchez Channel
improvements as shown in the submitted plans and shall obtain approval from the Bay Conservation
and Development Commission (BCDC) for the work within BCDC jurisdiction;
euRIINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
6. that the project shall include approximately 6,655 square feet of retail use and 19,750 square feet of
food service use that may be located in buildings B1, B2 a-nd or the amenities building, and Developer
shall use its best commercial efforts to lease this space for retail or food service, including recreation -
related uses such as bike rentals, and interactive educational space, as the case may be, for two
years following issuance of the final certificate of occupancy for each building. Thereafter, any change
to the use of the space designated for retail, recreation -related or food service use shall be reviewed
and approved by the Planning Commission using the process set out in Municipal Code Sections
25.16.040 through 25.16.085, using the conditional use permit findings as the standard of review.
Notwithstanding the above requirements which are applicable in the event the project is occupied
by multiple tenants if the entire project is leased to a single tenant then that tenant shall provide a
minimum of approximately 26,400 square feet of food service uses and other convenience goods and
services to its employees and invited quests which may be located in buildings B1, B2, or the
amenities building In addition to this space the project shall use its best commercial efforts to provide
a minimum of 1600 square feet of space in buildings B1 or B2 (facing the shoreline) for public -serving
amenities, which may include food/beveragetservice and other retail services to serve recreational
users of the Bay Trail and members of the public Such public amenities are encouraged to be
provided and open for business on days and times when substantial use along the shoreline is
anticipated, including weekends and holidays and are required to provide restrooms accessible to the
public If after two years of operation the tenant has evidence that the demand for the public amenities
is so limited as to justify discontinuing such services it may request a change of use. Any significant
change of use of the public amenity space or request to discontinue services shall be reviewed and
approved by the Planning Commission.
7. that the following items agreed to by the applicant shall be included as a part of the project:
a. Drinking fountains shall be provided as a part of the Bay Trail improvements, and shall include
ground -level spouts for dogs.
b. The educational nodes provided within the Bay Trail improvements shall include interactive
features such as binocular/telescope stands and pictographic educational elements regarding
local flora, fauna, marine and wind phenomena.
c. The Sanchez Channel open space shall include an area for active use (e.g. frisbee or catch);
that the conditions of the Chief Building Official's February 7, 2012 memo shall be met, which includes
the following comments:
a. an application for a building permit for this project received after December 31, 2013 must
comply with the 2013 California Building Codes and adopted City of Burlingame Ordinances
unless specific land use provisions for the project were approved by the City of Burlingame
prior to 5:00 p.m. on December 31, 2013. If the Planning Commission has approved the
project then the building permit application for that project may use the provisions found in the
2010 California Building Codes including all amendments as adopted in Ordinance 1856 2010.
This project must comply with the City of Burlingame Green Building Ordinance in effect at the
time of building permit applications.
0
auRLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
1) On the plans specify that this project will comply with the 2010 California Building
Codes (CBC) which will be employed by the City of Burlingame beginning January 1,
2011.
2) Comply with the City of Burlingame Green Building Ordinance in effect at the time of
Planning Commission approval for this project.
3) Anyone who is doing business in the City must have a current City of Burlingame
business license.
4) Provide fully dimensioned plans.
5) Indicate on the plans that ail work shall be conducted within the limits of the City's
Noise Ordinance. See City of Burlingame Ordinance Municipal Code, Section
13.04.100 for details.
6) Specify on the plans that this project will comply with the 2008 California Energy
Efficiency Standards or standards in effect at the time of building permit application.
Note: All projects for which a building permit application is received on or after January
1, 2010 must comply with the 2008 California Energy Efficiency Standards. Go to
http://wvvw.enerov.ca.gov/fitle24/2008standards/ for publications and details.
7) Indicate on the plans that all roofing systems will comply with Cool Roof requirements
of the 2008 California Energy Code. 2008 CEC §151 (f) 12. The 2008 Residential and
Non -Residential Compliance Manuals are available on line at
http://www.enerciy.camovititle24/2008standardst.
8) Show the distances from all exterior walls to property lines or to assumed property
lines.
9) Show the dimensions to adjacent structures.
10) Obtain a survey of the property lines.
11) Indicate on the plans that, at the time of Building Permit application, plans and
engineering will be submitted for shoring as required by 2010 CRC, or applicable
Building Code, regarding the protection of adjacent property and as required by OSHA.
On the plans, indicate that the following will be addressed:
a. The walls of the proposed basement shall be properly shored, prior to
construction activity. This excavation may need temporary shoring. A
competent contractor shall be consulted for recommendations and design of
shoring scheme for the excavation. The recommended design type of shoring
shall be approved by the engineer of record or soils engineer prior to usage.
b. All appropriate guidelines of OSHA shall be incorporated into the shoring
design by the contractor. Where space permits, temporary construction slopes
may be utilized in lieu of shoring. Maximum allowable vertical cut for the subject
project will be five (5) feet. Beyond that horizontal benches of 5 feet wide will be
required. Temporary shores shall not exceed 1 to 1 (horizontal to vertical). In
W
9URLINGPME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
some areas due to high moisture content / water table, flatter slopes will be
required which will be recommended by the soils engineer in the field.
C. If shoring is required, specify on the plans whose sole responsibility it is to
design and provide adequate shoring, bracing, formwork, etc. as required for
the protection of life and property during construction of the building.
d. Shoring and bracing shall remain in place until floors, roof, and wall sheathing
have been entirely constructed.
e. Shoring plans shall be wet -stamped and signed by the engineer -of -record and
submitted to the city for review prior to construction. If applicable, include
surcharge loads from adjacent structures that are within the zone of influence
(45 degree wedge up the slope from the base of the retaining wall) and / or
driveway surcharge loads.
12) Indicate on the plans that an OSHA permit will be obtained for the shoring* at the
excavation in the basement per CAL / OSHA requirements. See the Cal / OSHA
handbook at: http://www.ca-osha.com/pdfpubs/osha userguide.pdf. *Construction
Safety Orders : Chapter 4, Subchapter 4, Article 6 , Section 1541.1.
13) Indicate on the plans that a Grading Permit, if required, will be obtained from the
Department of Public Works.
14) Provide guardrails at all landings. NOTE: All landings more than 30" in height at any
point are considered in calculating the allowable lot coverage. Consult the Planning
Department for details if your project entails landings more than 30" in height.
15) Provide handrails at all stairs where there are four or more risers.
16) Provide lighting at all exterior landings.
17) Prior to applying for a Building Permit the applicant must obtain an address for each
structure on the site, acceptable to the Fire Marshal, from the Engineering Department.
Note: The correct address must be referenced on all pages of the plans.
18) On your plans provide a table that includes the following:
a. Occupancy group for each area of the building
b. Type of construction
C. Allowable area
d.
Proposed area
e.
Allowable height
f.
Proposed height
g.
Proposed fire separation distances
h.
Exterior wall and opening protection
i. Allowable
10
WRLINGAME
Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6
Meeting Date: August 13, 2018
ACTION ITEM
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION
Item No: 8(b)
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
ii. Proposed
i. Indicate sprinklered or non-sprinklered
19) Illustrate compliance with the minimum plumbing fixture requirements described in the
2010 California Plumbing Code, Chapter 4, Table 4-1 Minimum Plumbing Facilities and
Table A - Occupant Load Factor.
20) Show compliance with all accessibility regulations found in the 2010 CBC for
commercial buildings including:
a. Accessible paths of travel
b. A level landing must be provided on each side of the door at all required
entrances and exits.
C. Accessible countertops
d. Accessible bathrooms
e. Accessible parking
21) Per CEO 3003.5, all structures four or more stories in height must have at least one
elevator that can accommodate a stretcher. See the referenced code section for
dimensions (80" x 54") and other details.
22) Provide an exit plan showing the paths of travel
23) In Assembly occupancies specify aisle widths that comply with Section 1025.9.
24) Specify the total number of parking spaces on site
25) All NEW non-residential buildings must comply with the requirements of AB-2176 Sec.
42911 (c) [2003 — 2004 Montanez) as follows:
a. Space for recycling must be a part of the project design in new buildings.
b. A building permit will not be issued unless details are shown on the project
plans incorporating adequate storage for collecting and loading recycled
materials.
26) Include with your Building Division plan check submittal a complete underground fire
sprinkler plan. Contact the Burlingame Water Division at 650-558-7660 for details
regarding the water system or Central County Fire for sprinkler details.
27) Sewer connection fees must be paid prior to issuing the building permit.
9. that the conditions of the NPDES Coordinators February 8, 2012 memo shall be met,
which includes the following comments:
11
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
a. The project will need to comply with additional and new Low Impact Development (LID)
requirements under the Municipal Regional Permit, C.3 Provisions, which became effective on
December 11, 2011. For details and technical guidance on these C.3 requirements visit the
San Mateo Countywide Water Pollution Prevention Program (SMCWPPP) at
http://www/flowstobay.orianas new development. php.
b. The following C.3 forms/worksheets have been updated and project proponents will need to
use and submit these forms as part of the final construction documents and associated
building permits:
1) NPDES Permit Impervious Surface Data Collection Worksheet*
2) C.3 and C.6 Development Review Checklist*.
*both forms are available for download at http:/A w v/ lowstobay.orcebs new development. php.
c. When submitting plans for a building permit include a list of construction stormwater pollution
prevention Best Management Practices (BMPs) as project notes and include them as a
separate full size plan sheet, preferably 2' x 3' or larger. Project proponents may use the
attached Construction Best Management Practices (BMPs) plan sheet to comply with this
requirement. Electronic file is available for download at http://www/flowstobay.ora/bs
construction. php (scroll about half -way down the page and click on Construction BMP Plan
Sheet).
10. that the conditions of the Parks Supervisor's February 6, 2012 memo shall be met, which includes the
following comments:
a. Submit a Landscape Project Application to the Parks Division in compliance with the Water
Conservation in Landscape Ordinance.
b. New trees in the Airport Boulevard islands shall be Platanus acerfolia 'Columbia'.
11. that the conditions of the Fire Marshal's April 26, 2010 memo shall be met, which includes the
following comments:
a. All buildings shall be equipped with fire alarms, fire sprinklers and standpipes where required
by the California Fire Code and the Burlingame Municipal Code.
b. Fire Flow and Fire Hydrants shall conform to Appendix B and C of the International Fire Code
2006 Edition.
c. Fire apparatus access shall be provided for all buildings in accordance with §503 of the
International Fire Code.
d. Fire Control Room as required by the California Building Code shall be placed to the exterior
of the building with exterior access. Rooms shall be positioned facing fir apparatus access.
This requirement may negate exterior remote annunciators and key boxes intended to house
HMIS/HMMP as required for Burlingame Municipal Code.
12
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
e. Please see Burlingame Municipal Code specific to Addressing Requirements and Key Boxes
associated with Hazardous Materials.
f. The fire department shall request HMIS/HMIP in accordance with the California Fire Code. All
inventory lists shall at minimum indicate the hazardous material class and quantities
consistent with Table 2703.1.1(1), Title 24 CFC classes and units (i.e.: pounds, gallons, cubic
feet at NTP, etc.).
g. Space shall be provided within each Highrise for installation of a repeater/receiver antenna
and supporting equipment for City Communications. An electrical supply source shall be
provided at the antenna/equipment location. Reasonable access shall be provided to City
staff contractors for installation of necessary telephone lines and for purposes of
installation, maintenance, adjustment and repair of the antenna/equipment.
12. that the conditions of the Public Works Department, Engineering Division's May 8, 2012 memo shall
be met, which includes the following comments:
a. With City approval, the Developer proposes to construct a new, realigned Airport Boulevard
through the Project and to construct Bay Trail and Bay frontage improvements in the City's
right-of-way easement of the original Airport Boulevard. Developer understands that the
underlying fee of the original Airport Boulevard ROW, from the existing Sanchez Chanel
Bridge East to Fisherman's Park and South from Fisherman's Park to Beach Road, is owned
by the State of California, State Lands Commission and that the City only holds a ROW
easement over same. Developer shall give the State Lands Commission written notice of its
development plans and specifically, notice of the proposed improvements to be constructed
in the ROW of the original Airport Boulevard alignment, within ten (10) days of the Planning
Commission's recommendation of the Project to the City Council. At any time, should State
Lands have any concerns over said improvements, object to any aspect of the proposed
improvements or initiate any type of administrative or judicial action in regard to these
proposed improvements, Developer shall hold harmless, defend and indemnify the City, its
officers, agents and employees from any and all fees (including attorneys' fees), damages,
fines or any other costs of any kind related to such objections, claims or actions.
Additionally, the Developer shall obtain letters of no objection to the proposed
realignment of Airport Boulevard from all utility companies. The Project Developer shall
relocate all existing utilities from within the existing Airport Boulevard roadway to the
proposed realigned Airport Boulevard roadway to the satisfaction of the City Engineer and
affected utility companies.
b. The developer shall prepare necessary engineering drawings and construction documents to
construct the Sanchez Channel Bridge widening as identified in the existing BCDC permit to
provide the necessary width for pedestrian, bicyclist and vehicular access along Airport
Boulevard. The developer shall complete construction of these improvements at his/her
expense These drawings shall be approved by the City Engineer as part of the Building Permit
process.
13
Ht7,RLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
c. The developer shall be responsible to meet all San Francisco Bay Conservation and
Development Commission (BCDC) requirements for the project and provide the City with
documentation of all approvals by BCDC for all work within 100 feet of the shoreline band
along the San Francisco Bay and Sanchez drainage channel.
d. The developer shall enter into a Site Maintenance Agreement with the City for maintenance of
all landscape, sidewalk, medians, and stormwater improvements as well as roadway
improvements that do not conform to city standards, such as the proposed roadway
intersections. The Site Maintenance Agreement shall be executed prior to the issuance of the
Building permit.
e. All traffic improvements, including but not limited to traffic signals, pedestrian countdown
signals, pedestrian audible signals, signal interconnection hardware, street lights, signage,
street markings, etc., shall be approved by the City Engineer and installed at the property
owner's expense. The proposed streetlights must conform to current standards which
require Beta LED's or equivalent. The developer shall submit and obtain approval of the
required engineering drawings and specifications for all public improvements as part of the
building permit process.
f. The project shall reimburse to the City the operation, maintenance and energy costs of the
proposed traffic signals. The City will maintain the newly proposed traffic signal operations. The
operation cost of the traffic signal will be adjusted annually by the City based on prevailing
costs. The electricity costs will be based on direct billing by PG & E.
g. The developer shall provide at his/her expense shoreline access, adequate erosion
protection and site amenities to the standards established by the City and BCDC.
The Bay and drainage channel shorelines located on this property will require stabilization
improvements to provide flood protection for the public access trail and bridge. All shoreline
and drainage channel slope protection measures, need to be reviewed and approved by the
City Engineer.
The public and facility users shall be safely provided for and protected from the flooding of the
site in the event of a disaster. This includes a storm or an earthquake which coincides with a
maximum high tide and possible breaching of Sanchez Channel and/or Airport Boulevard
levees. The property owner shall employ a qualified engineer to analyze the seismic stability of
the Sanchez Channel and Airport Boulevard levees and identify protection against possible
earthquake or storm event. The property owner shall submit the structural and seismic stability
analysis to the City Engineer for review and approval. If the analysis indicates that
improvements are necessary along the project site to provide stability for an event, such
improvements shall be installed as approved by the City Engineer prior to occupancy of the first
building.
The developer shall be required to incorporate the following measures into project design in
order to reduce the potential impacts of flooding:
1) Necessary tide gates shall be installed in the storm drain system on the project site to
prevent high water from back flowing into the site during flood periods;
14
9URLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 1 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
2) Adequate drainage and pump facilities, including a sound -baffled backup power supply,
shall be provided in the parking area to prevent water ponding in excess of ten (10) inches
in the event of a 100-year flood;
3) Storm drainage facilities shall be designed to accommodate any future settlement of the
site, levees and other fill along the site perimeter;
4) A flood contingency plan shall be developed to provide guidelines for management of
vehicles in the event of flooding of the parking area; and
5) On -site improvements shall be designed to provide 100-year flood protection. All
emergency equipment, generators, controls, and motors shall be located above the 100-
year flood elevation.
The developer shall install a six-inch diameter recycled water main with the roadway
improvements. This six-inch line shall extend from the existing Sanchez Channel Bridge east
to the other end of the new roadway alignment near Beach Road. Initially the line shall be
connected to the City water main and serve as the service connection for irrigation. This line
and the irrigation system shall convert to a recycled water line once it becomes available.
These improvements shall be done at the property owner's cost and shall be completed in
concurrence with the roadway improvements.
The project developer shall implement and maintain an appropriate Transportation
Demand Management measures in accordance with the San Mateo County Congestion
Plan to reduce the number of trips generated by this project.
m. Detailed grading and drainage plans shall be submitted by the project developer for review by
the City Engineer at the time of applying for a building permit.
n. The project shall comply with the City's NPDES permit requirement to prevent storm water
pollution during and after the construction. In addition, the project developer shall provide all
documentation relating to compliance with the Regional Municipal Permit from the State of
California Water Resources Board.
o. It is possible that this project may require approvals and permits from the U.S. Army Corp of
Engineers, Department of Fish and Game, and the California Regional Water Quality Control
Board. The applicant must provide written records of contacting the above agencies
demonstrating that a permit has been obtained or is not required.
p. All street improvements plans shall be submitted to the City for review and approval These
improvements include but are not limited to sanitary sewer mains and laterals; water mains
and services; storm drain mains and inlets; street structural sections, soils report, etc.
Hydrologic and hydraulic calculations are required for all designs associated with the new
road alignment. The road structural section shall be designed to a traffic index of minimum
12.0 and shall withstand vertical displacement due to natural subsurface settlement. The
structural section shall be designed for a 20-year life based on recommendations of a
professional geotechnical engineer and accompanying soils report.
15
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
q. The project developer shall perform necessary engineering studies to determine the required
capacity and improvements to the system to be approved by the City Engineer. At the City's
discretion, the sanitary sewer improvements shall be routed along Airport Boulevard to an
existing pump station, thence along Airport Boulevard to the Wastewater Treatment Plant.
The sanitary sewer system improvements shall be designed and constructed to
accommodate the fully built -out conditions of the project and adjacent properties.
r. The project shall abandon the existing potable water main located within existing alignment of
Airport Boulevard from Fisherman's Park to Beach Road. The project shall evaluate the
existing condition of the water main. If necessary and at the City's discretion, the project shall
design and construct a new potable water main system along the newly proposed Airport
Boulevard from Beach Road to the Sanchez Channel as well as the replace the existing
potable water main segment from Sanchez Channel to Fisherman's Park.
s. The project shall install purple piping in buildings for future reclaimed water use in building
applications.
13. that early demolition, mass excavation, grading, shoring and foundation permits, including permits for
installation of indicator/production piles, may be issued in advance of a building permit provided that
prior to issuance of such permits, the applicant has submitted construction plans for the project to the
Building Division, or has provided evidence that it is having such plans prepared for the project for
which the demolition or grading work is intended. Further, building construction permits shall be
submitted and received in accordance with the progress of the work which will occur in phases.
Permits that may be submitted individually for application may include, but are not limited to,
indicator/production piles, mass excavation, shoring, grading, foundations, superstructure, architecture
MEP, fire protection, fire alarm, curtain wall, and so forth, subject to the consent of the City's Building
Official and the Fire Marshal. Building Permit phasing and scheduling shall be arranged with the
Project Applicant and the Community Development Department — Building Division, such that the work
can proceed in an orderly fashion as one continuous phase of construction;
14. that the project shall comply with the Construction and Demolition Debris Recycling Ordinance which
requires affected demolition, new construction and alteration projects to submit a Waste Reduction
plan and meet recycling requirements; any partial or full demolition of a structure, interior or exterior,
shall require a demolition permit;
15. Exterior lighting for the project would be designed to meet the requirements of Burlingame Municipal
Code Section 18.16.030 (pertaining to light spillage off site in commercial or residential areas), the
California Energy Commission, and the Illuminating Engineering Society of North America for
illumination levels. Compliance with these performance standards would minimize the dispersion of
light in a manner that reduces the glow or aurora effect to acceptable and allowable levels. In addition,
the project area already contains numerous sources of exterior lighting, and is not adjacent to uses
that would be sensitive to light spillover.
16. that the applicant shall comply with Ordinance 1503, the City of Burlingame Storm Water Management
and Discharge Control Ordinance;
16
auRLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
17. that the overall height of the buildings as measured from the top of curb at Airport Boulevard (+ 14.5'
elevation) to the top of the mechanical screens shall be no taller than the following heights: Buildings
B1 and B2, 97.0', Building 83, 129.0', Building B4, 144.0% Parking Structure, 67.5', and Amenities
Building, 49.0'; building heights shall be surveyed at the framing of each floor and at the installation
of the mechanical screen and shall be reported to the Building Division as each floor is framed and
accepted by the City Engineer before framing of the subsequent floor or roof commences. The
elevator overruns and associated structures shall be permitted to exceed the stated height limits to
the degree that such exceedance is necessitated by the Uniform Building Code in order for elevators
to serve their intended purpose of providing access by persons to the rooftop terraces on the
buildings. The entire building height of each structure shall be surveyed to confirm conformance with
the approved plans and conditions of approval before scheduling the final framing inspection. If the
building does not conform at any point in the construction process, it shall be made to conform before
construction continues and any further city inspections shall be scheduled (Building Division);
18. that the applicant shall pay the required Bayfront Development Fee based on the square footage of
the buildings and the current rate adjusted for inflation, the total fee due is calculated to be
$1,695,070.00. Per the development agreement, one-half of the fee is due at the time of issuance of
the first City Building Permit for construction of a building, and one-half is due before the final framing
inspection is scheduled, for each Development Phase. The fee due shall be offset by the actual costs
incurred by Developer in designing, preparing, installing and constructing (a) the realignment and
widening of Airport Boulevard but limited to the customary and ordinary costs for such improvements
without special pedestrian treatments, and (b) the Sanchez Channel bridge widening as outlined in
the Development Agreement (Planning Division);
19. that the applicant shall pay the required public facilities impact fees based on the square footage of
the buildings, and that the Parks and Recreation fee ($131,924.00) and the Storm Drain Fee
($549,939.00) shall be waived, the total remaining fee due shall be $1,102,179.00. The remaining fees
shall be payable by development phase, and shall be submitted to the Planning Division prior to the
issuance of the first building permit for construction of each building as follows: Building 61:
$209,802.00, Building 62: $209,802.00, Building 133: $293,722.80, Building B4, $335,683.20, and
Amenities Center: $53,169.00 (Planning Division):
20. that the property owner shall be responsible to see that small delivery trucks or vans making periodic
deliveries are on -site only during office hours; no trucks, recreation vehicles or other vehicles shall be
stored or parked on site continuously throughout the day or overnight, and no parking shall be leased
to tenants or any other users for any purpose,
21. that the property owner shall Gernply with the Transportation Demand Management
that the Property ,Owner,, in the _event „the _Prop E!y_is leased to multiple tenants or the tenant in the
event that the entire Property is leased to a sole tenant shall implement a comprehensive
transportation demand management (TDM) program to the satisfaction of the Community
Development Director in order to achieve the same or greater peak hour trip reductions as the TDM
17
suRLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
Program prepared by Fehr and Peers for 350 Beach Road LLC dated April 5, 2011. Such TDM
Program may include measures such as:
a. Secure Bicycle Storage: Secure, indoor bicycle storage for at least 26 bicycles shall be
provided in a lobby or garage level room within each of the four office buildings. In addition,
bicycle racks for up to 50 bicycles will be located outside of Buildings #1 or #4.
h. Showers and Changing Rooms: Shower facilities with changing rooms shall be provided
throughout the site, with access available to all employees. Shower facilities (two men's and
two women's) and changing rooms (one men's and one women's) shall be provided in each of
the four office buildings, the amenities center shall include 12 showers and two changing
rooms.
i. Shuttle Service: Coordinate with the Peninsula Commuter Alliance to add two stops within
the project site to the existing commuter shuttle from the Millbrae Intermodal Station. The
shuttle provides 10-minute headways during peak periods.
j. Carpool Parking: Provide 15 preferential parking spaces for carpools at each of the four
office buildings.
k. Vanpool Parking: Provide two preferential parking spaces for vanpools at each of the four
office buildings.
I. Commute Assistance Center:
3) Provide an on -site one -stop shopping for transit and commute alternatives information.
4) Provide a part-time on -site TDM coordinator available to assist building tenants with
trip planning.
m. Employees' Surveys: The TDM coordinator shall develop and administer two surveys per
year to examine TDM program participation and best practices.
o. Video Conferencing Center: One video conferencing center of approximately 8500 sf shall
be installed for use by the tenants of the facility.
p. On -Site Amenities/Accommodations: On -site amenities, including banking, retail, delivery
dry cleaning, exercise facilities, child care center, delivery pharmacy and food service shall be
provided at the project site to encourage people to stay on site during the work day;
q. On -Site Bicycles for Employee Use- Bicycles shall be provided at each office building.
Employees will have access to bicycles during breaks for personal or business use.
r. Child Care Services: Child care center service shall be provided on site;
s. Guaranteed Ride Home Program: Employees will have access to the Guaranteed Ride
Home (GRH) program administered by the Peninsula Congestion Relief Alliance (Alliance)
for emergencies. The program provides vouchers for taxicabs or rental cars for this
purpose.
t. Transportation Action Plan: The TDM coordinator shall work with the Alliance to create a
Transportation Action Plan for each tenant.
18
suR�INGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
Transportation Management Association: If the office park has multiple tenants, each
tenant shall provide a representative to form a Transportation
Management Association and be a liaison to the TDM Coordinator.
S. Coordination of Transportation Demand Management Programs: The TDM
coordinator shall coordinate with other TDM programs with existing developments/employers
in the surrounding area.
t. Subsidy for Transit Tickets: Employers shall offer subsidies to employees to
compensate them for the cost of transit tickets.
U. Electric Vehicle Stations: The applicant shall provide plug-in stations for electric
vehicles.
V. House Car for Employee Use: Each building will provide employees with access to a
"house car" for use during the day.
THE FOLLOWING CONDITIONS SHALL BE MET DURING THE BUILDING INSPECTION PROCESS
PRIOR TO THE INSPECTIONS NOTED IN EACH CONDITION:
22. that prior to scheduling the framing inspection, the project architect, engineer or other licensed
professional shall provide architectural certification that the architectural details such as window
locations and bays are built as shown on the approved plans; if there is no licensed professional
involved in the project, the property owner or contractor shall provide the certification under penalty of
perjury. Certifications shall be submitted to the Building Department;
23. that prior to scheduling the roof deck inspection, a licensed surveyor shall shoot the height of the
roof ridge and provide certification of that height to the Building Division; and
24. that prior to final inspection, Planning Division staff will inspect and note compliance of the
architectural details (trim materials, window type, etc.) to verify that the project has been built
according to the approved Planning and Building plans.
Mitigation Measures from Environmental Impact Report:
Measures Applicable to 300 Airport Boulevard Project as well as future development of the 350
Airport Boulevard site:
25. Amphlett Poplar Intersection: The City of San Mateo is considering a range of potential improvements
at the Amphlett Boulevard/Poplar Avenue intersection to provide sufficient capacity for existing and
future traffic volume. However, a specific improvement project has not been identified at this time. The
Project Sponsor, and any future project sponsor for development of the 350 Airport Boulevard site,
shall negotiate an agreement with the City of San Mateo to make a fair share contribution toward the
cost of improvements at this intersection for each projects respective impacts (Transportation,
Planning, Public Works, City of San Mateo);
19
6tlRlINGPME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
26. Implement Recommended Dust Control Measures. To reduce particulate matter emissions during
Project excavation and construction phases, the Project contractor(s) shall comply with the dust
control strategies developed by BAAQMD. The Project Sponsor shall include in all construction
contracts the following requirements or measures:
• All exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and unpaved
access roads) shall be watered two times per day.
• All haul trucks transporting soil, sand, or other loose material off -site shall be covered.
• All visible mud or dirt track -out onto adjacent public roads shall be removed using wet power
vacuum street sweepers at least once per day. The use of dry power sweeping is prohibited.
• All vehicle speeds on unpaved roads shall be limited to 15 mph.
• All roadways, driveways, and sidewalks to be paved shall be completed as soon as possible.
Building pads shall be laid as soon as possible after grading unless seeding or soil binders are
used.
• Idling times shall be minimized either by shutting equipment off when not in use or reducing the
maximum idling time to 5 minutes (as required by the California airborne toxics control measure
Title 13, Section 2485 of California Code of Regulations [CCR]). Clear signage shall be
provided for construction workers at all access points.
• All construction equipment shall be maintained and properly tuned in accordance with
manufacturer's specifications. All equipment shall be checked by a certified mechanic and
determined to be running in proper condition prior to operation.
• Post a publicly visible sign with the telephone number and person to contact at the Lead Agency
regarding dust complaints. This person shall respond and take corrective action within 48 hours.
The Air District's phone number shall also be visible to ensure compliance with applicable
regulations. (Air Quality; (Planning and Building Divisions);
27. Construction Equipment Emissions Minimization. To reduce the potential impacts resulting from
Project construction activities, the Project Sponsor shall include in contract specifications a
requirement for the following measures:
Idling times shall be minimized either by shutting equipment off when not in use or reducing the
maximum idling time to two minutes;
The Project shall develop a construction plan demonstrating that the off -road equipment (more
than 50 horsepower) to be used in the construction Project (i.e., owned, leased, and
subcontractor vehicles) would achieve a Project wide fleet -average 20 percent NOx reduction
and 45 percent PM reduction compared to the most recent CARB fleet average (as specified in
California Code of Regulations Article 4.8, Section 2449 General Requirements for In -Use Off -
Road Diesel -Fueled Fleets). Acceptable options for reducing emissions include the use of late
model engines, low -emission diesel products, alternative fuels, engine retrofit technology, after -
treatment products, add -on devices such as particulate filters, and/or other options as such
become available;
20
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (`BURLINGAME POINT")
All construction equipment, diesel trucks, and generators shall be equipped with Best
Available Control Technology for emission reductions of NOx and PM;
• Use of Interim Tier 4, if applicable, or equivalent equipment for all uses where such equipment
is available;
• Use of Tier 3 equipment with Best Available Control Technology (BACT) or alternative fuel
vehicles for applications where Tier 4 Interim engines are not available;
• Prohibition of diesel generators for construction purposes where feasible alternative sources of
power are available;
• All construction equipment shall be maintained in proper working condition in accordance with
manufacturer's specifications;
• Diesel -powered construction equipment shall comply with BAAQMD requirements or meet Tier
3 or Tier 4 EPA/CARB standards; and
• To the extent feasible, the existing electricity infrastructure surrounding the construction sites
shall be used rather than electrical generators powered by internal combustion engines. (Air
Quality; Planning and Building Divisions)
28. Application of Low-VOC Coatings. The Project Sponsor shall use low VOC (i.e., ROG) coatings
beyond the local requirements as per the BAAQMD Guideline (i.e., Regulation a Rule 3: Architectural
Coatings) (Air Quality; Planning and Building Divisions);
29. Implement Best Management Practices to Reduce Construction Noise. The following BMPs shall be
incorporated into the construction documents to be implemented by the Project contractor.
a. Maximize the physical separation between noise generators and noise receptors. Such
separation includes, but is not limited to, the following measures:
i. Use heavy-duty mufflers for stationary equipment and barriers around particularly noisy
areas of the site or around the entire site;
ii. Use shields, impervious fences, or other physical sound bafflers to inhibit transmission
of noise to sensitive receptors;
iii. Locate stationary equipment to minimize noise impacts on the community; and
iv. Minimize backing movements of equipment.
b. Use quiet construction equipment whenever possible.
c. Impact equipment (e.g., jack hammers and pavement breakers) shall be hydraulically or
electrically powered wherever possible to avoid noise associated with compressed air
exhaust from pneumatically -powered tools. Compressed air exhaust silencers shall be
used on other equipment. Other quieter procedures, such as drilling rather than using
impact equipment, shall be used whenever feasible.
21
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (`BURLINGAME POINT")
d. Prohibit unnecessary idling of internal combustion engines.
e. Select routes for movement of construction -related vehicles and equipment in conjunction
with the Burtingame Planning Division so that noise -sensitive areas, including residences
and schools, are avoided as much as possible.
f. The project sponsor shall designate a "disturbance coordinator for construction
activities. The coordinator would be responsible for responding to any local complaints
regarding construction noise and vibration. The coordinator would determine the cause
of the noise or vibration complaint and would implement reasonable measures to
correct the problem. (Noise, Planning and Building Divisions);
30. Notifv Nearbv Businesses of Construction Activities that Could Affect Vibration -Sensitive Equipment
The Project Sponsor shall provide notification to adjacent property owners and occupants, prior to
the start of construction, informing them of the estimated start date and duration of vibration -
generating construction activities during site preparation, grading, and pile driving, if required. This
notification shall include information warning about the potential for impacts related to vibration -
sensitive equipment. The Project Sponsor shall identify a phone number for the property owners
and occupants to call if they have vibration -sensitive equipment on their site. (Noise, Planning and
Building Divisions);
31. Implement Construction BMPs to Reduce Construction Vibration. The Project Sponsor shall
implement the following measures during construction of all Project components:
• To the extent feasible, construction activities that could generate high vibration levels at any
identified vibration -sensitive locations shall be scheduled during times that would have the least
impact on nearby land uses. This could include restricting construction activities in the areas of
potential impact to the early and late hours of the work day, such as from 8:00 a.m. to 10:00 am.
or 4:00 p.m. to 6:00 p.m. Monday to Friday.
• Stationary sources, such as construction staging areas and temporary generators, shall be
located as far from nearby vibration -sensitive receptors as possible. `
• Trucks shall be prohibited from idling along streets serving the construction site where vibration -
sensitive equipment is located.
• Avoid pile driving when possible within 100 feet of an existing structure. (Noise, Planning and
Building Divisions);
32. Implement Alternative Pile Driving Methods. The Project Sponsor shall use alternative pile driving
methods (e.g., drilled or steel piles) for piles driven in proximity to existing vibration receptors such
that vibration levels at vibration -sensitive equipment shall not exceed 65 VdB. (Noise, Planning and
Building Divisions);
33. Bird Nest Pre -Construction Survey. The Project Sponsor(s) shall retain a qualified biologist to
conduct preconstruction breeding -season surveys (approximately March 15 through August 30) of
22
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
the Project Site and immediate vicinity during the same calendar year that construction is planned to
begin, in consultation with the CDFG as discussed below.
If phased construction procedures are planned for the Project, the results of the above survey shall be
valid only for the season when it is conducted. A report shall be submitted to CDFG, following the
completion of the bird nesting survey that includes, at a minimum, the following information:
• A description of methodology including dates of field visits, the names of survey personnel with
resumes, and a list of references cited and persons contacted.
• A map showing the location(s) of any bird nests observed on the Project Site.
If the above survey does not identify any nesting bird species on the Project Site, no further mitigation
would be required. However, should any active bird nests be located on the Project Site, the following
mitigation measure shall be implemented. (Biological Resources, Planning Division);
34. Bird Nest Buffer Zone. The Project Sponsor(s), in consultation with CDFG, shall delay construction in
the vicinity of active bird nest sites located on or adjacent to the Project Site during the breeding
season (approximately March 15 through August 30) while the nest is occupied with adults and/or
young. If active nests are identified, construction activities should not occur within 500 ft of the nest. A
qualified biologist shall monitor the active nest until the young have fledged, until the biologist
determines that the nest is no longer active, or if it is reasonable that construction activities are not
disturbing nesting behaviors. The buffer zone shall be delineated by highly visible temporary
construction fencing. (Biological Resources, Planning and Building Divisions);
35. In order to reduce significant impacts to the City's wastewater conveyance and treatment system
associated with the Project the Project Sponsor shall adhere to either of the two following mitigation
measures..
a. Upgrade Pump Capacity at the Existing 399 Rollins Road Pump Station and Reduce Inflow and
Infiltration within the Wastewater System. The Project Sponsor(s) shall contribute fair -share
funds toward the upgrade of the 399 RRPS capacity, or equivalent project to increase capacity
in the system, to accommodate the increased PWWF that would result from implementation of
the Project. Additionally, the Project Sponsor(s) shall rehabilitate the existing wastewater
system, where necessary, to reduce inflow and infiltration that contributes to PWWFs at the
WWTP in an amount concomitant with increases in flows contributed by the 300 Airport
Boulevard Project.
b. Upgrade to the Existing Airport Boulevard Conveyance System Variant to Rollins Road Pump
Station Upgrade. The Project Sponsor(s) shall coordinate with the City of Burlingame Public
Works Department to upgrade the capacity of the City's wastewater conveyance and
treatment system to accommodate the increased PWWF that would result from
implementation of development of the 300 and 350 Airport Boulevard Sites. Such measures
could include, as necessary, installation of a new pump station within public right of way or
other area near the Sanchez Channel Bridge on the Project Site, upgrade the capacity of the
existing Airport Boulevard Pump Station, extension of wastewater lines across Sanchez
Channel, via attachment to the Sanchez Channel Bridge, to tie into existing wastewater lines
23
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
under Airport Boulevard west of the Project Site, and increasing, as required, the capacity of
existing gravity lines between the Project.
Site and the Airport Boulevard Pump Station and existing force main between the Airport
Boulevard Pump Station and the WWrp. The Project Sponsor shall construct the necessary
improvements to serve the Project Site and additional properties along Airport Boulevard that
would connect to this sewer line. (Utilities, Public Works Department);
36. Undiscovered Cultural Resources. If evidence of an archaeological site or other suspected cultural
resource as defined by CEQA Guideline Section 15064.5, including darkened soil representing past
human activity ("midden'), that could conceal material remains (e.g., worked stone, worked bone, fired
clay vessels, faunal bone, hearths, storage pits, or burials) is discovered during construction -related
earth -moving activities, all ground -disturbing activity within 100 feet of the resources shall be halted
and the City of Burlingame shall be notified. The Project Sponsor shall hire a qualified archaeologist to
conduct a field investigation. The City of Burlingame shall consult with the archeologist to assess the
significance of the find. Impacts to any significant resources shall be mitigated to a less -than -
significant level through data recovery or other methods determined adequate by a qualified
archaeologist and that are consistent with the Secretary of the Interior's Standards for Archaeological
Documentation.
37. Unique Paleontological/Geological Features. Should a unique paleontological resource or site or
unique geological feature be identified at the project construction site during any phase of
construction, the Project manager shall cease all construction activities at the site of the discovery and
immediately notify the City of Burlingame. The Project Sponsor shall retain a qualified paleontologist
to provide an evaluation of the find and to prescribe mitigation measures to reduce impacts to a less -
than -significant level. Work may proceed on other parts of the project site while mitigation for
paleontological resources or geologic features is carried out. The Project Sponsor shall be responsible
for implementing any additional mitigation measures prescribed by the paleontologist and approved by
the City.
38. Human Remains. If human remains are discovered at any Project construction site during any phase of
construction, all ground -disturbing activity 100 feet of the resources shall be halted and the City of
Burlingame and the San Mateo County coroner shall be notified immediately, according to Section
5097.98 of the State Public Resources Code and Section 7050.5 of California's Health and Safety
Code. If the remains are determined by the County coroner to be Native American, the Native
American Heritage Commission (NAHC) shall be notified within 24 hours, and the guidelines of the
NAHC shall be adhered to in the treatment and disposition of the remains. The Project Sponsor shall
also retain a professional archaeologist with Native American burial experience to conduct a field
investigation of the specific site and consult with the Most Likely Descendant, if any, identified by the
NAHC. As necessary, the archaeologist may provide professional assistance to the Most Likely
Descendant, including the excavation and removal of the human remains. The City of Burlingame
shall be responsible for approval of recommended mitigation as it deems appropriate, taking account
of the provisions of State law, as set forth in CEQA Guidelines section 15064.5(e) and Public
Resources Code section 5097.98. The project applicant shall implement approved mitigation, to be
24
euRLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
verified by the City of Burlingame, before the resumption of ground -disturbing activities within 100 feet
of where the remains were discovered.
MITIGATION MEASURES APPLICABLE ONLY TO THE 300 AIRPORT BLVD. PROJECT
39. Reduce Risk of Exposure During Construction. If the childcare center is operational during the
construction of Phase 2 of the Project, one of the following shall be implemented:
a. A Health Risk Assessment is conducted prior to commencement of construction of Phase 11 that
demonstrates, to the satisfaction of the BAAQMD, that impacts to the children at the childcare
center are less than significant during Phase 11 construction or specific sub phases of Phase ll
construction; or
b. Implement the following building design and operational restrictions.
1. The childcare center building shall be designed such that the air intake would be
located at the far eastern edge of the building with the air intake facing east.
2. A MERV 15 or higher rated filter shall be installed and operated for at least the duration
of construction activities. The MERV 15 or higher rated filters have the potential to
remove up to 85 percent of particles of 2.5 microns or greater thereby reducing interior
levels of pollutants.
3. All outdoor activities at the childcare center shall be suspended while construction
activities are occurring.
If implementation of this Mitigation Measure is infeasible, then the childcare center would be prohibited
from operating during Phase 11 construction. (Air Quality, Building and Planning Divisions);
40. Maintenance and Testing of Generators. As part of the conditions of operation for the onsite back-up
generators, all diesel emissions associated with the maintenance and testing of the generators
should be conducted at such times as the daycare center is not in operation, particularly nights and
weekends. (Air Quality, Building and Planning Divisions);
41. Implementation of MERV 15 Filters. The Project Sponsor shall consider implementing MERV 15 or
higher rated filters for the amenities building. This would further reduce exposure of daycare students
to emissions from US 101. The MERV 15 or higher rated filters have the potential to remove up to 85
percent of PM2.5 and would reduce risk while students were inside the building. (Air Quality, Building
and Planning Divisions);
42, Incorporate GHG Reduction Measures for Maintenance Activities. The Project Sponsor shall provide
infrastructure for the use of electric landscape equipment during landscaping activities, where
feasible. (Climate Change, Planning Division and Parks Department);
43. Incorporate Trees and Vegetation into Project Design. Trees and other shade structures shall be
incorporated into the Site Plan to maximize summer shade and to minimize winter shade. (Climate
Change, Planning Division and Parks Department),
25
sURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
44. Renewable Energy System. The 300 Airport Boulevard Project shall offset 10 percent of project
electricity demand through implementation of onsite renewable energy systems or through investment
in offsite alternative energy systems. (Climate Change, Planning and Building Divisions);
45. Drought Tolerant Landscaping. The 300 Airport Boulevard Project shall reduce irrigation -related
water demand by a minimum of 10 percent through the implementation of drought tolerant
landscaping. (Climate Change, Planning Division and Parks Department);
46. Cool Roof Material. The 300 Airport Boulevard Project shall incorporate cool -roof materials into project
design to reduce electricity demand associated with building heating, ventilation, and air conditioning
(HVAC) by a minimum of 7 percent. (Climate Change, Planning and Building Divisions);
47. Water Conservation Measures. The 300 Airport Boulevard Project shall implement immediate water
conservation measures to reduce building water demand by 33 percent. Building water demand
shall ultimately be reduced by 50 percent when the City's recycled water system is implemented.
(Climate Change, Planning and Building Divisions);
48. Energy Efficiency beyond Title 24 Standards. The 300 Airport Boulevard Project shall reduce building
energy demand beyond the 2005 Title 24 Standards by 26 percent (Climate Change, Planning and
Building Divisions);
49. aeration Solid Waste Reduction. The 300 Airport Boulevard Project shall implement a solid waste
reduction program to reduce operational solid waste by a minimum of 10 percent (Climate Change,
Planning Division);
50. Utilize Alternative Fueled Vehicles and Local Building Materials. In accordance with BAAQMD BMPs,
the Project Sponsor shall incorporate into the construction fleet a minimum of 15 percent of
construction vehicles and equipment operated by alternative fuels. Further, the Project Sponsor shall
ensure that a minimum of 10 percent of building materials are locally sourced, where feasible.
(Climate Change, Planning and Building Divisions);
51. Conduct a Wetland Delineation. The Project Sponsor shall retain a qualified biologist to conduct a
wetland delineation of the Project Site. This delineation shall be submitted to the Corps for
verification prior to the issuance of any grading permits for the Project. If the Corps determines that
the features in the Project Site are not jurisdictional, then no further mitigation would be required.
(Biological Resources, Planning and Building Divisions);
52. Obtain Applicable Permits and Certifications. If the Corps determines that these features are
jurisdictional, then the Project Sponsor must obtain a CWA Section 404 permit from the Corps, and
a CWA Section 401 Water Quality Certification from the RWQCB prior to issuance of any grading
permits for the Project. A requirement of the permits will be compensation such that there is no net
loss of wetlands. This compensation requirement can be satisfied through avoidance, onsite and/or
offsite construction and preservation of wetlands or by purchase of mitigation credits at an
26
eiIRLINGAME
Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6
Meeting Date: August 13, 2018
ACTION ITEM
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION
Item No: 8(b)
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
approved mitigation bank. At certified mitigation banks, the Corps typically requires a minimum 1:1
ratio, but may require higher ratios for certain wetland types. (Biological Resources, Planning and
Building Divisions);
53. Provide Flood Protection up to the 100-Year Flood Event plus Sea Level Rise for Underground
Structures. To protect underground structures from sea level rise flood risks, prior to approving
grading and/or building permits the City shall ensure that the project design incorporates its
floodplain development requirements into all applicable project features using a flood elevation of at
least 7.1 feet. All below -ground structures, including storm drains, sewers, equipment facilities, and
others, shall be flood proofed and designed to withstand hydrostatic forces and buoyancy from
water surface elevations up to 7.1 feet in elevation. Certain portions of the shoreline open space
may not be protected at the ultimate level of flooding, given proposed heights. However, developed
areas of the Project would be protected. For the shoreline areas, an adaptive strategy would be
developed to address end -of -century conditions. (Hydrology, Building Division and Public Works
Department);
54. Provide Adeauate Storm Flow Conveyance Capacity for Sea Level Rise Conditions. To ensure that
the storm drain system conveyance capacity is not constricted by sea level rise at the outlets, the
Project Sponsor shall design the storm drain system to adequately convey stormwater runoff at
outlet water surface elevations equivalent to the 100-year flood event base elevation plus sea level
rise of 55 inches (water surface elevation of 11.6 feet at the outlet). Prior to receiving a grading
permit, the City shall review project designs and studies for adequacy of storm flow conveyance with
an outlet surface water elevation of 11.6 feet and in accordance with City design standards. The
City shall prepare Conditions of Approval, where necessary, to ensure that the design criteria are
met. The Project Sponsor shall incorporate applicable City Conditions of Approval into project
designs, prior to receiving a grading permit. (Hydrology, Public Works Department);
55. Provide Protection of Shoreline and Flood Protection Features from Hydrodynamic Forces from Sea
Level Rise Conditions. Prior to receiving a grading permit, in order to ensure that the shoreline and
flood protection features associated with the proposed project provide protection under sea level
rise hydrodynamic and/or hydrostatic conditions, the Project Sponsor shall prepare engineering
studies to identify expected hydrodynamic forces for under storm surge conditions (at least 2
percent wave run-up) and a base flood elevation of at least 11.6 feet and hydrostatic forces from a
water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea level rise). For the
shoreline areas, an adaptive strategy would be implemented to address end -of -century conditions.
The Project Sponsor shall design shoreline and flood protection features that could accommodate
hydrodynamic forces from sea level rise conditions along wherever flood protection features are
identified under Mitigation Measure HY-7.1 and at shoreline protection features for stability and
integrity under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of at
least 11.6 feet. The Project Sponsor shall also design flood protection features for protection against
hydrostatic forces from a water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea
level rise). The City shall review designs and associated studies for conformance with City
27
eiiRLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
requirements and adequacy of design measures to withstand hydrodynamic and hydrostatic forces
associated with the design criteria.
The Project Sponsor shall also design erosion protection along the shoreline set -back area for
protection under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of
at least 11.6 feet. The City shall review designs and associated studies for adequacy in protecting the
shoreline set -back area under these conditions.
The City Public Works Department shall prepare Conditions of Approval, where necessary, to ensure
that the design criteria are met. Prior to receiving a grading permit, the Project Sponsor shall
incorporate applicable City and BCDC Conditions of Approval into project designs.
MITIGATION MEASURES APPLICABLE TO THE FUTURE DEVELOPMENT OF THE 350
AIRPORT BOULEVARD SITE
56. Implement TDM Program as part of 350 Airport Boulevard Proiect. These measures could include:
secure bicycle storage, showers and changing rooms, shuttle service, preferential parking for
canpoolers, preferential parking for vanpoolers, commute assistance center, employees' surveys,
video conferencing centers, on -site amenities accommodations, on -site bicycles for employees, child
care services, guaranteed ride home program, transportation action plan, transportation management
association, and coordination of TDM programs (Air Quality, Planning Division);
57. Implement enemy efficiency measures with 350 Airport Boulevard Protect. These measures could
include: LEED certification or to exceed energy efficiency beyond Title 24 requirements which would
further aid in reducing stationary source emissions (Air Quality; Planning and Building Divisions);
58. Incorporate GHG Reduction Measures for Maintenance Activities. The Project Sponsor shall provide
infrastructure for the use of electric landscape equipment during landscaping activities, where
feasible. (Climate Change, Planning Division and Parks Department);
59. Incorporate Trees and Vegetation into Project Design. Trees and other shade structures shall be
incorporated into the Site Plan to maximize summer shade and to minimize winter shade. (Climate
Change, Planning Division and Parks Department);
60. Renewable Enerpy System. The 350 Airport Boulevard Project shall offset 10 percent of project
electricity demand through implementation of onsite renewable energy systems or through investment
in offsite alternative energy systems. (Climate Change, Planning and Building Divisions);
61. Drought Tolerant Landscaping. The 350 Airport Boulevard Project shall reduce irrigation -related
water demand by a minimum of 10 percent through the implementation of drought tolerant
landscaping. (Climate Change, Planning Division and Parks Department);
62. Cool Roof Material. The 350 Airport Boulevard Project shall incorporate cool -roof materials into project
design to reduce electricity demand associated with building heating, ventilation, and air conditioning
(HVAC) by a minimum of 7 percent (Climate Change, Planning and Building Divisions);
28
BURLINGAME Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (`BURLINGAME POINT")
63. Water Conservation Measures. The 350 Airport Boulevard Project shall implement immediate water
conservation measures to reduce building water demand by 33 percent. Building water demand
shall ultimately be reduced by 50 percent when the City's recycled water system is implemented.
(Climate Change, Planning and Building Divisions);
64. Enemy Efficiency beyond Title 24 Standards. The 350 Airport Boulevard Project shall reduce building
energy demand beyond the 2005 Title 24 Standards by 26 percent (Climate Change, Planning and
Building Divisions);
65. aeration Solid Waste Reduction. The 350 Airport Boulevard Project shall implement a solid waste
reduction program to reduce operational solid waste by a minimum of 10 percent. (Climate Change,
Planning Division);
66. Implement a TOM program. The Project Sponsor shall ensure that future development of the 350
Airport Boulevard Site implement a TOM program similar to that described for the 300 Airport
Boulevard Project, to reduce transportation -related GHG emissions. (Climate Change, Planning
Division and Traffic Engineer);
67. Pursue LEED Certification. Future development of the 350 Airport Boulevard Site shall seek LEED
Gold certification or equivalent for development per the recommendations of the City's Green Building
Ordinance. The Project Sponsor shall submit draft LEED (or equivalent) checklists to the City
Sustainability Coordinator for review and consultation. (Climate Change, Planning and Building
Divisions);
68. Placement or Screeninq of HVAC Mechanical Equipment. All HVAC mechanical equipment shall be
located more than 60 feet from the nearest property line. Alternatively, HVAC mechanical equipment
may be installed in a noise enclosure sufficient to reduce ground -level noise levels at the nearest
property boundary to 70 dBA CNEL or less. (Noise, Planning and Building Divisions);
69. Provide Flood Protection up to the 100-Year Flood Event plus Sea Level Rise for Underground
Structures. To protect underground structures from sea level rise flood risks, prior to approving
grading and/or building permits the City shall ensure that the project design incorporates its floodplain
development requirements into all applicable_nroject features using a flood elevation of at least
7.1 feet. All below -ground structures, including storm drains, sewers, equipment facilities, and
others, shall be flood proofed and designed to withstand hydrostatic forces and buoyancy from
water surface elevations up to 7.1 feet in elevation. Certain portions of the shoreline open space
may not be protected at the ultimate level of flooding, given proposed heights. However, developed
areas of the Project would be protected. For the shoreline areas, an adaptive strategy would be
developed to address end -of -century conditions. (Hydrology, Building Division and Public Works
Department);
70. Provide Adequate Storm Flow Conveyance Capacity for Sea Level Rise Conditions. To ensure that
the storm drain system conveyance capacity is not constricted by sea level rise at the outlets, the
Project Sponsor shall design the storm drain system to adequately convey stormwater runoff at
outlet water surface elevations equivalent to the 100-year flood event base elevation plus sea level
29
BURLINGAME
Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6
Meeting Date: August 13, 2018
ACTION ITEM
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION
Item No: 8(b)
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED
OFFICE/LIFE SCIENCE DEVELOPMENT ("BURLINGAME POINT")
rise of 55 inches (water surface elevation of 11.6 feet at the outlet). Prior to receiving a grading
permit, the City shall review project designs and studies for adequacy of storm flow conveyance with
an outlet surface water elevation of 11.6 feet and in accordance with City design standards. The
City shall prepare Conditions of Approval, where necessary, to ensure that the design criteria are
met. The Project Sponsor shall incorporate applicable City Conditions of Approval into project
designs, prior to receiving a grading permit (Hydrology, Public Works Department);
71. Provide Protection of Shoreline and Flood Protection Features from Hydrodynamic Forces from Sea
Level Rise Conditions. Prior to receiving a grading permit, in order to ensure that the shoreline and
flood protection features associated with the proposed project provide protection under sea level
rise hydrodynamic andlor hydrostatic conditions, the Project Sponsor shall prepare engineering
studies to identify expected hydrodynamic forces for under storm surge conditions (at least 2
percent wave run-up) and a base flood elevation of at least 11.6 feet and hydrostatic forces from a
water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea level rise). For the
shoreline areas, an adaptive strategy would be implemented to address end -of -century conditions.
The Project Sponsor shall design shoreline and flood protection features that could accommodate
hydrodynamic forces from sea level rise conditions along wherever flood protection features are
identified under Mitigation Measure HY-7.1 and at shoreline protection features for stability and
integrity under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of at
least 11.6 feet. The Project Sponsor shall also design flood protection features for protection against
hydrostatic forces from a water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea
level rise). The City shall review designs and associated studies for conformance with City
requirements and adequacy of design measures to withstand hydrodynamic and hydrostatic forces
associated with the design criteria.
The Project Sponsor shall also design erosion protection along the shoreline set -back area for
protection under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of
at least 11.6 feet. The City shall review designs and associated studies for adequacy in protecting the
shoreline set -back area under these conditions.
The City Public Works Department shall prepare Conditions of Approval, where necessary, to ensure
that the design criteria are met. Prior to receiving a grading permit, the Project Sponsor shall
incorporate applicable City and BCDC Conditions of Approval into project designs. (Hydrology, Public
Works Department);
72. Provide Flood Protection un to the 100-Year Flood Event plus Sea Level Rise for Above -Ground
Structures. To protect structures and people from sea level rise risks at the 350 Airport Boulevard Site,
prior to approving grading permits, the City shall ensure project design incorporates its floodplain
development requirements for a flood depth of the identified 100-year flood hazard water surface
elevation plus a 4.6-foot (55-inch) rise in sea level. At a minimum, the Project Site shall be graded to
over 10 feet above msl and the finished floor elevation of all building finished floors shall be
constructed to 14.5 feet (i.e., 2.9 feet above the 11.6-foot potential flood elevation), or as otherwise
determined as grading plans are developed. (Hydrology, Public Works Department); and
30
euRIINGAMe Community Development Department
PLANNING COMMISSION STAFF REPORT
APPLICATION FOR AMENDMENT TO CONDITIONS OF APPROVAL #6 Meeting Date: August 13, 2018
(RETAIL AND FOOD SERVICE PROVISIONS) AND #21 (TRANSPORTATION ACTION ITEM
DEMAND MANAGEMENT PROVISIONS) OF A PREVIOUSLY APPROVED Item No: 8(b)
OFFICE/LIFE SCIENCE DEVELOPMENT (-BURLINGAME POINT")
73, Future Wind Tunnel Analysis. To reduce potential impacts associated with future development of the
350 Airport Boulevard Site, a wind tunnel analysis shall be conducted in order to ensure that future
development of the Site is designed in a way to minimize wind shadow effects at surrounding
windsurfing areas. (Wind and Recreation, Planning Division).
Prepared by: Kevin Gardiner, Community Development Director
c. Genzon Investment Group, applicant
Burlingame Point LLC, property owner
Attachments:
• Applicant Letter of Explanation, dated August 2, 2018
• Application to the Planning Commission
• Proposed Resolution
• Notice of Public Hearing - Mailed August 3, 2018
31
Arent Fox � Arent Fox LLP /Attorneys at Law
Los Angeles, CA / New York, NY / San Francisco, CA / Washington, DC
www.arentfox.com
August 2, 2018 Timothy Tosta
Partner
415.805.7969 DIRECT
Kevin Gardiner 415.757.5501 FAx
tim.tostaCa,arentfox.com
Community Development Director
City of Burlingame
501 Primrose Road
Burlingame, CA 94010
Re: 300 Airport Boulevard Minor: Modification of Approval Conditions
Dear Mr. Gardiner:
On behalf of Burlingame Point LLC, sponsor of the 300 Airport Boulevard Project, we are
very pleased to announce that a major enterprise is proposing to lease the entire Burlingame Point
campus as the sole tenant (the "Prospective Tenant"). Because the original entitlements for the Project
contemplated a multi -tenant program for the four office buildings comprising the Project, our client
is now requesting relatively minor amendments of two conditions of approval in order to
accommodate a single tenant campus and better match the operation and opportunities of the
Prospective Tenant.'
The purpose of this letter is to explain the basis for the proposed amendments and why we
believe they are consistent with the purposes of the previously -adopted conditions. No modification
to the Development Agreement is proposed or required in order to accommodate the requested
modifications.
By way of background, over the past several years, Burlingame Point LLC and its team have
been working diligently to identify possible tenants whose prestige and reputation would match the
superior quality of the Burlingame Point campus, and who would enhance the image of Burlingame
as an attractive home for office and R&D businesses.
Burlingame Point is now pursuing final negotiations with a very well recognized company
headquartered in the Bay Area which has expressed an intent to lease the entire campus as a single
The Prospective Tenant has been engaged in serious negotiation with our client for several months. The parties have
signed a Letter of Intent and are very close to finalization of lease terms. For business reasons, the Prospective Tenant
is not yet prepared to reveal its identity; however, we anticipate that the Prospective Tenant will be prepared to identify
itself in the near future and before the Planning Commission takes action on the requested minor changes. While
certain business issues are still being discussed between the parties, it is highly likely that if the proposed condition
changes requested pursuant to this letter are approved, the Prospective Tenant will finalize the lease for the entire
campus.
555 West Fifth Street, 4811 Floor 1301 Avenue of the Americas, 42nd Floor 55 Second Street, 21 s' Floor 1717 K Street, NW
Los Angeles, CA 90013-1065 New York, NY 10019-6040 San Francisco, CA 94105-3470 Washington, DC 20006-5344
T 213.629.7400 F 213.629.7401 T 212.484.3900 F 212.484.3990 T 415.757.5500 F 415.757.5501 T 202.857.6000 F 202.857.6395
Kevin Gardiner
August 2, 2018
Page 2
user. Leasing the entire Burlingame Point campus to a single internationally -recognized tenant will
provide several advantages to the community. First, this commitment will accelerate the complete
build -out of the Project. Second, the decision of the Prospective Tenant to locate in Burlingame will
provide a stimulus to other economic development activities in the Bayfront area. In addition, the
Prospective Tenant will implement a comprehensive, leading edge transportation demand
management ("TDM") program that will provide an even greater trip reduction than the TDM plan
specified in the original conditions of approval.
As part of its due diligence, the Prospective Tenant has carefully reviewed the approved
Project and the conditions of approval, and found the campus, as designed, to be suitable for its
purposes. No changes to the architectural program are sought. The Airport Boulevard realignment
will be completed as planned, all the contemplated shoreline open space improvements will be built
(including the renovation of Fisherman's Park, which is not a condition of the City's approvals), and
the public will have full access and use of the shoreline and other on -site open space. Also, the
Prospective Tenant is comfortable with all the mitigation measures and conditions of approval, with
only two minor exceptions discussed below. Burlingame Point LLC is confident that the Prospective
Tenant's occupancy of the entire campus will fulfill the community's vision for this Project.
As noted, the Prospective Tenant intends to occupy the entire campus. While nothing in the
entitlement requires or limits whether the campus is occupied by either a single tenant or multiple
tenants, the original program contemplated a multi -tenant scenario. Accordingly, the Prospective
Tenant has requested that two conditions of approval be adjusted to be more consistent with a single
occupant and the Prospective Tenant's operations.
Requested Modification to Condition 6:
The first modification relates to certain uses that were included in the approved Project in
anticipation of a multi -tenant campus. Specifically, Condition 6, as revised in August 2016, provides
in relevant part:
"That the project shall include approximately 6,655 square feet of retail
use and 19,750 square feet of food service use that may be located in
buildings B1, B2 and the amenities building, and Developer shall use
its best commercial efforts to lease this space for retail or food
service... for two years following issuance of the final certificate of
occupancy for each building. Thereafter, any change to the use of the
space designed for retail, recreation -related or food service use shall be
reviewed and approved by the Planning Commission..."
This provision contemplates that the campus would be occupied by multiple tenants and is
intended to ensure that the employees would have reasonable access to food and other services on -
site. Of course, those facilities would also be made available to the limited market of others working
Kevin Gardiner
August 2, 2018
Page 3
in the vicinity who wish to utilize their services during the work week, as well as other members of
the public. As the condition recognizes, it was also contemplated that these food/retail services would
be provided by leasing space to individual operators (e.g., lunchtime food service companies), and that
it also might not prove economically viable for individual operators to provide these services to office
workers at this somewhat isolated site. For this reason, the condition recognized the possibility that
the intended retail and food service space might not be leased, and that the Planning Commission
could re -visit the use of this approximately 26,000 square feet of space if efforts to lease the space to
individual operators proved unsuccessful.
This contemplated program for providing food and services to employees presents a number
of challenges for a single tenant campus. First, the practice of cutting edge firms within the Bay Area
(including the Prospective Tenant) is to provide a higher level of amenity services for their own
employees in order to recruit and retain a highly qualified workforce and to help reduce vehicle trips.
It is also more efficient for a single user to provide those services directly, without needing to account
for the profit margins required to sustain an outside service provider. Finally, there is a security
component, since providing food and other services in areas restricted to employees ensures that those
employees are free to discuss work and exchange intellectual property and prospective product
strategies in a secure environment.
The Prospective Tenant intends to provide its employees a broad range of food and other on -
site services consistent with its other campus operations. While tenant improvement plans are still
being finalized, the Prospective Tenant anticipates that at full occupancy it would provide
approximately 56,000 square feet of tenant food service, as well as a small tenant store and tenant -
serving laundry facilities as shown on the diagram attached to this letter. The great majority of these
services would be provided in Buildings 1, 2 and the amenities building, consistent with what was
originally contemplated by Condition 6. The Prospective Tenant is therefore requesting a modification
to Condition 6 that would require that the tenant provide a minimum of 26,000 square feet of food
services and other retail -like services to its employees. However, for the reasons noted above, it is
critical that the Prospective Tenant be able to provide these services to its employees/guests only.
Although not considered a "public benefit" for purposes of the Development Agreement, the
current language in Condition 6 does contemplate that any food and retail services within the campus
would also have been made available to the general public visiting the shoreline for recreational
purposes. However, the number of recreational users seeking these services during weekday work
hours is likely to be very small, and there is little likelihood that any of the services contemplated by
Condition 6 would generate enough business to operate on weekends or holidays when recreational
shoreline use would be highest. Indeed, as contemplated in current Condition 6, it remains unclear
whether those services in a multi -tenant scenario would be economically viable even during the
weekdays.
Kevin Gardiner
August 2, 2018
Page 4
However, the Prospective Tenant values the vibrancy of the Bay Trail and its relationship to
the Project, and fully understands the desirability of providing some form of public food and retail
services that would be specifically designed with recreational users in mind. To that end, the
Prospective Tenant is willing to commit to providing a minimum of 800 square feet of space in
Buildings 1, facing the shoreline, for a mix of food/beverage and other services that would expressly
cater to public recreational users of the Bay Trail and Fisherman's Park, in addition to 800 square feet
of space in Building 2 that could include similar uses, or potentially a small retail store providing
convenience goods and apparel, for a total of 1,600 square feet of community -serving uses. The precise
services to be provided would be developed in the future in consultation with City staff.
Requested Modification to Condition 21:
The second requested modification concerns the TDM program requirements set forth in
Condition 21. Condition 21 is somewhat unusual in that it prescribes a set of specific components of
the TDM plan prepared in 2011 as part of the original Project approvals, and does not allow for the
particular features of that TDM plan to evolve or change over time. In other words, it effectively
"freezes" the TDM conditions prepared in 2011 by specifying a strict list of measures that must be
implemented, rather than giving the owner/tenant the right to select from a menu of options to
achieve trip reduction and allow those measures to evolve over time (which is what we see in most
project entitlements). Apart from the rigidity of Condition 21, a further challenge arises because the
TDM plan from 2011 contemplated a multi -tenant program rather than a single tenant campus, and
what works for a multi -tenant program is not necessarily the same as what works for a single tenant.
As noted above, the Prospective Tenant plans to implement a comprehensive, state-of-the-art
TDM Program which will accomplish an even greater level of trip reduction than the TDM measures
required by Condition 21. However, the Prospective Tenant's preferred TDM program will not exactly
correspond to all of the specific TDM elements cited in Condition 21. For example, the Prospective
Tenant operates its own private transit program and therefore there is no need to provide shuttle stops
within the campus for public shuttles to and from the Millbrae Intermodal Station (see e.g., Condition
21.c). Thus, while the Prospective Tenant's TDM program will achieve the purposes of the Condition
21 TDM measures and provide even better performance in terms of reducing single occupancy vehicle
trips, it may not be consistent with every detail of Condition 21.
The Prospective Tenant is fully committed to maintain a leading edge TDM program to reduce
employee vehicle trips, consistent with the intent of Condition 21 to achieve a substantial reduction
in "peak hours" trips that have the greatest impact on traffic congestion. The Prospective Tenant
seeks only flexibility to achieve these goals in a manner more consistent with its current, best TDM
practices. One way to achieve this flexibility would be to request that City Staff review an occupant's
proposed TDM program, and approve that program as long as it demonstrates an equal or greater
degree of trip reduction than the measure listed in Condition 21. This approach would also be more
efficient by allowing TDM plans to evolve over time without the need for future public hearings every
Kevin Gardiner
August 2, 2018
Page 5
time a specific component is changed. To that end, we would request that Condition 21 be amended
to allow for alternative TDM measures to be employed so long as they will achieve the same or greater
trip reductions as compared to the TDM plan from 2011.
Conclusion
On behalf of Burlingame Point LLC, we could not be more excited about partnering with the
Prospective Tenant and the benefits that this Tenant will bring both to the Project and the broader
community. The Prospective Tenant's occupancy of the Burlingame Point campus is fully consistent
with the community's goals for the Project, and the requested changes are only required to
accommodate a marquee single tenant user who operates its own employee amenity program and
state-of-the-art TDM program. All of the Project's key public improvements, including the
reconfiguration of Airport Boulevard and the open space and shoreline improvements, will be fully
implemented. In addition, the general public would continue to have access not only to the shoreline,
but also to the pedestrian promenade, plazas, and interconnected open spaces within the campus.
The Prospective Tenant seeks only minor changes to two approved conditions which will still
achieve the goals of (1) providing a broad range of food and other services for employees, while
ensuring a limited menu of services will be provided for the general public, including people using the
shoreline for recreation, and (2) implementing a TDM program that will achieve the same or greater
trip reductions relative to the TDM measures specified in Condition 21.
As part of the application to amend these two conditions, we have attached a conceptual plan
showing the amenities planned by the Prospective Tenant. We sincerely look forward to working with
you and City staff to bring this request to the Planning Commission. As always, please do not hesitate
to contact me if you have any questions or if there is any additional material we can provide.
Sincerely,
Timothy Tosta
CC: Lisa Goldman, City Manager
Kathleen Kane, City Attorney
Robin Cao, Genzon Investment
Attachment
PROJECT AMENITY PROGRAM
Proposed amenity program
Tenant food service
Tenant conference center
Tenant laundry
Tenant store with public access
Public amenity
■ Tenant food service
❑ Tenant conference center
■ Tenant store w/ public access
Public amenity
j NITY DEVELOPMENT DEPARTMENT • 501 PRIMROSE ROAD • BURLINGAME, CA 94010
9uRUNGAMEEE -
n: 650.558.7250 • f: 650.696.3790 • www.burlingame.org
APi 'RATION TO THE PLANNING COMMISSION
Type of application:
Q Design Review ❑ Variance ❑ Parcel #:APN 026-350-180, 190, 080,100
❑ Conditional Use Permit ❑ Special Permit R1 Zoning / Other: APN
PROJECT ADDRESS: 300 Airport Boulevard
APPLICANT PROPERTY OWNER
Name: Burlingame Point LLC Name: Same
Address: 433 Airport Blvd., Suite 426 Address:
City/State/Zip: Burlingame, CA 94010 City/State/Zip:
Phone: (650) 686-9166: (650) 483-8153 Phone:
E-mail: silas(a-kylli.com: caohao(a-)genzon.com.cn E-mail:
ARCHITECT/DESIGNER
Name: N/A
Address:
City/State/Zip:
Phone:
E-mail:
Burlingame Business License #:
AUG 0 2 2018
CITY OF BIURLINGAME
CDD-PLANNiNG DIV.
Authorization to Reproduce Project Plans:
I hereby grant the City of Burlingame the authority to reproduce upon request and/or post plans submitted with this
application on the City's website as part of the Planning approval process and waive any claims against the City
arising out of or related to such action. NA (Initials of Architect/Designer)
PROJECT DESCRIPTION: Minor amendment of conditions of approval for approved office campus.
AFFIDAVIT/SIGNATURE: I hereby certify under penalty of perjury that the information given herein is true and correct to the
best of my knowledge and belief.
�1 r
Applicant's signature: Uwe Date:
I am aware of the proposed application and hereby authorize the above applicant to submit this application to the
Planning Commission.
Property owner's signature: Da ,, VN Date:
Date submitted:
S: I HA NDO UTS I PC Application. doc
RESOLUTION NO.
RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF BURLINGAME,
APPROVING A REQUEST FOR COMMERCIAL DESIGN REVIEW AMENDMENT OF A
PREVIOUSLY APPROVED OFFICE/LIFE SCIENCE CAMPUS AT 300 AIRPORT BOULEVARD,
ON PROPERTY SITUATED WITHIN THE ANZA POINT NORTH (APN) ZONE
RESOLVED, BY THE PLANNING COMMISSION OF THE CITY OF BURLINGAME THAT:
WHEREAS, an application for Commercial Design Review for Amendments to the
Bayfront Specific Plan amendments to the zoning code related to the Anza Point North and
Parking Regulations amendment to the sign code rezoning of a portion of the site from the
APS zone district to the APN zone district tentative parcel map, development agreement,
Conditional Use Permit for Day Care Use and Commercial Design Review for construction of
767,000 square feet of new uses including office space or life science uses retail uses food
services a childcare facility and an exercise facility at 300 Airport Boulevard, zoned APN and
APS, was approved by the Burlingame City Council on June 18, 2012; and
WHEREAS, the Final Environmental Impact Report (EIR) for the application was
certified by the Burlingame City Council on June 18, 2012; and
WHEREAS, an application for Commercial Design Review Amendment and
Environmental Impact Report (EIR) Addendum of the previously approved Office/Life Science
Campus was approved by the Burlingame Planning Commission on August 22, 2016; and
WHEREAS, an application for Commercial Design Review Amendment and
Environmental Impact Report (EIR) Addendum of the previously approved Office/Life Science
Campus was approved by the Burlingame Planning Commission on November 27, 2017; and
WHEREAS, an application has been made for Commercial Design Review Amendment
of the previously approved Office/Life Science Campus at 300 Airport Boulevard, zoned APN,
Burlingame Point LLC property owner, APN: 026-350-130; and
WHEREAS, said matters were heard by the Planning Commission of the City of
Burlingame on August 13, 2018, at which time it reviewed and considered the staff report and all
other written materials and testimony presented at said hearing;
NOW, THEREFORE, IT IS RESOLVED AND DETERMINED BY THIS PLANNING
COMMISSION THAT:
Section 1. On the basis of the Environmental Impact Report, Environmental Impact
Report Addendum, the documents submitted and reviewed, and comments received and
addressed by this Commission, it is hereby found that there is no substantial evidence that the
project set forth above will have a significant effect on the environment, and categorical
exemption, per CEQA Section 15301 (a) of the CEQA Guidelines, which states that interior or
exterior alterations to existing structures are exempt from environmental review, is hereby
approved..
RESOLUTION NO.
Section 2. Said Commercial Design Review Amendment is approved subject to the
conditions set forth in Exhibit "A" attached hereto. Findings for such Commercial Design
Review are set forth in the staff report, minutes, and recording of said meeting.
Section 3. It is further directed that a certified copy of this resolution be recorded in
the official records of the County of San Mateo.
Chairman
I, , Secretary of the Planning Commission of
the City of Burlingame, do hereby certify that the foregoing resolution was introduced and
adopted at a regular meeting of the Planning Commission held on the 13th day of August, 2018
by the following vote:
Secretary
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
that the project shall be built as shown on the plans submitted to the Planning Division and date
stamped July 29, 2016, Sheets: COVER SHEET; 1 GENERAL PROJECT INFORMATION; 2 SITE
PLAN; 3 B1 CONSTRUCTION PLAN; 4 LANDSCAPE SITE SECTIONS - EAST CAMPUS; 5
LANDSCAPE SITE SECTIONS - WEST CAMPUS; 6 L1 CONSTRUCTION PLAN - BUILDING 01; 7
L3 CONSTRUCTION PLAN - BUILDING 01; 8 ROOF CONSTRUCTION PLAN - BUILDING 01; 9 L1
CONSTRUCTION PLAN - BUILDING 02; 10 L3 CONSTRUCTION PLAN - BUILDING 02; 11 ROOF
CONSTRUCTION PLAN - BUILDING 02; 12 L1 CONSTRUCTION PLAN - BUILDING 03; 13 L3
CONSTRUCTION PLAN - BUILDING 03; 14 L5 CONSTRUCTION PLAN - BUILDING 03; 15 ROOF
CONSTRUCTION PLAN - BUILDING 03; 16 L1 CONSTRUCTION PLAN - BUILDING 04; 17 L3
CONSTRUCTION PLAN - BUILDING 04; 18 L5 CONSTRUCTION PLAN - BUILDING 04; 19 ROOF
CONSTRUCTION PLAN - BUILDING 04; 20 EXTERIOR ELEVATIONS - BUILDING 01; 21
EXTERIOR ELEVATIONS - BUILDING 01; 22 EXTERIOR ELEVATIONS - BUILDING 02; 23
EXTERIOR ELEVATIONS - BUILDING 02; 24 EXTERIOR ELEVATIONS - BUILDING 03; 25
EXTERIOR ELEVATIONS - BUILDING 03; 26 EXTERIOR ELEVATIONS - BUILDING 03; 27
EXTERIOR ELEVATIONS - BUILDING 03; 28 EXTERIOR ELEVATIONS - BUILDING 04; 29
EXTERIOR ELEVATIONS - BUILDING 04; 30 EXTERIOR ELEVATIONS - BUILDING 04; 31
EXTERIOR ELEVATIONS - BUILDING 04; 32 BUILDING SECTIONS - BUILDING 01 & 02; 33
BUILDING SECTIONS - BUILDING 03; 34 BUILDING SECTIONS - BUILDING 03; 35 BUILDING
SECTIONS - BUILDING 04; 36 BUILDING SECTIONS - BUILDING 04; 37 L1 CONSTRUCTION
PLAN — GARAGE; 38 EXTERIOR ELEVATIONS - BUILDING 05 GARAGE; 39 EXTERIOR
ELEVATIONS - BUILDING 05 GARAGE; 40 BUILDING SECTION — GARAGE; 41 L1
CONSTRUCTION PLAN - AMENITY BUILDING; 42 L2 CONSTRUCTION PLAN - AMENITY
BUILDING; 43 ROOF CONSTRUCTION PLAN - AMENITY BUILDING; 44 EXTERIOR ELEVATIONS
- AMENITY BUILDING; 45 OVERALL GRADING PLAN; 46 OVERALL UTILITY PLAN; with
amendments to Buildings 3 and 4 as indicated on plans submitted to the Planning Division and date
stamped October 5, 2017.
2. that prior to building permit issuance the applicant shall return to the Planning Commission with the
following FYIs:
a. a complete landscape plan indicating size, species, quantities and locations of all plantings; and
b. analysis of compliance with Complete Streets provisions;
3. that any changes to the size or envelope of building, which would include changing or adding exterior
walls or parapet walls, shall require an amendment to this permit;
4. that any changes to building materials, exterior finishes, windows, architectural features, roof height or
pitch, and amount or type of hardscape materials shall be subject to Planning Division or Planning
Commission review (FYI or amendment to be determined by Planning staff);
5. that the project shall include installation and maintenance of the Bay Trail and Sanchez Channel
improvements as shown in the submitted plans and shall obtain approval from the Bay Conservation
and Development Commission (BCDC) for the work within BCDC jurisdiction;
6. that the project shall include approximately 6,655 square feet of retail use and 19,750 square feet of
food service use that may be located in buildings B1, B2 or the amenities building, and Developer
shall use its best commercial efforts to lease this space for retail or food service, including recreation -
related uses such as bike rentals, and interactive educational space, as the case may be, for two
years following issuance of the final certificate of occupancy for each building. Thereafter, any change
to the use of the space designated for retail, recreation -related or food service use shall be reviewed
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
and approved by the Planning Commission using the process set out in Municipal Code Sections
25.16.040 through 25.16.085, using the conditional use permit findings as the standard of review.
Notwithstanding the above requirements, which are applicable in the event the project is occupied
by multiple tenants, if the entire project is leased to a single tenant, then that tenant shall provide a
minimum of approximately 26,400 square feet of food service uses, and other convenience goods and
services, to its employees and invited guests which may be located in buildings B1, B2, or the
amenities building. In addition to this space, the project shall use its best commercial efforts to provide
a minimum of 1600 square feet of space in buildings B1 or B2 (facing the shoreline) for public -serving
amenities, which may include food/beverage service and other retail services to serve recreational
users of the Bay Trail and members of the public. Such public amenities are encouraged to be
provided and open for business on days and times when substantial use along the shoreline is
anticipated, including weekends and holidays, and are required to provide restrooms accessible to the
public. If after two years of operation the tenant has evidence that the demand for the public amenities
is so limited as to justify discontinuing such services, it may request a change of use. Any significant
change of use of the public amenity space or request to discontinue services shall be reviewed and
approved by the Planning Commission;
7. that the following items agreed to by the applicant shall be included as a part of the project:
a. Drinking fountains shall be provided as a part of the Bay Trail improvements, and shall include
ground -level spouts for dogs.
b. The educational nodes provided within the Bay Trail improvements shall include interactive
features such as binocular/telescope stands and pictographic educational elements regarding
local flora, fauna, marine and wind phenomena.
c. The Sanchez Channel open space shall include an area for active use (e.g. frisbee or catch);
8. that the conditions of the Chief Building Official's February 7, 2012 memo shall be met, which includes
the following comments:
a. an application for a building permit for this project received after December 31, 2013 must
comply with the 2013 California Building Codes and adopted City of Burlingame Ordinances
unless specific land use provisions for the project were approved by the City of Burlingame
prior to 5:00 p.m. on December 31, 2013. If the Planning Commission has approved the
project then the building permit application for that project may use the provisions found in the
2010 California Building Codes including all amendments as adopted in Ordinance 1856 2010.
This project must comply with the City of Burlingame Green Building Ordinance in effect at the
time of building permit applications.
1) On the plans specify that this project will comply with the 2010 California Building
Codes (CBC) which will be employed by the City of Burlingame beginning January 1,
2011.
2) Comply with the City of Burlingame Green Building Ordinance in effect at the time of
Planning Commission approval for this project.
3) Anyone who is doing business in the City must have a current City of Burlingame
business license.
4) Provide fully dimensioned plans.
5) Indicate on the plans that ail work shall be conducted within the limits of the City's
Noise Ordinance. See City of Burlingame Ordinance Municipal Code, Section
13.04.100 for details.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
6) Specify on the plans that this project will comply with the 2008 California Energy
Efficiency Standards or standards in effect at the time of building permit application.
Note: All projects for which a building permit application is received on or after January
1, 2010 must comply with the 2008 California Energy Efficiency Standards. Go to
http://wvvw.enerov.ca.clov/fitle24/2008standards/ for publications and details.
7) Indicate on the plans that all roofing systems will comply with Cool Roof requirements
of the 2008 California Energy Code. 2008 CEC §151 (f) 12. The 2008 Residential and
Non -Residential Compliance Manuals are available on line at
http://www.enerciy.camovititle24/2008standardst.
8) Show the distances from all exterior walls to property lines or to assumed property
lines.
9) Show the dimensions to adjacent structures.
10) Obtain a survey of the property lines.
11) Indicate on the plans that, at the time of Building Permit application, plans and
engineering will be submitted for shoring as required by 2010 CRC, or applicable
Building Code, regarding the protection of adjacent property and as required by OSHA.
On the plans, indicate that the following will be addressed:
a. The walls of the proposed basement shall be properly shored, prior to
construction activity. This excavation may need temporary shoring. A
competent contractor shall be consulted for recommendations and design of
shoring scheme for the excavation. The recommended design type of shoring
shall be approved by the engineer of record or soils engineer prior to usage.
b. All appropriate guidelines of OSHA shall be incorporated into the shoring
design by the contractor. Where space permits, temporary construction slopes
may be utilized in lieu of shoring. Maximum allowable vertical cut for the subject
project will be five (5) feet. Beyond that horizontal benches of 5 feet wide will be
required. Temporary shores shall not exceed 1 to 1 (horizontal to vertical). In
some areas due to high moisture content / water table, flatter slopes will be
required which will be recommended by the soils engineer in the field.
C. If shoring is required, specify on the plans whose sole responsibility it is to
design and provide adequate shoring, bracing, formwork, etc. as required for
the protection of life and property during construction of the building.
d. Shoring and bracing shall remain in place until floors, roof, and wall sheathing
have been entirely constructed.
e. Shoring plans shall be wet -stamped and signed by the engineer -of -record and
submitted to the city for review prior to construction. If applicable, include
surcharge loads from adjacent structures that are within the zone of influence
(45 degree wedge up the slope from the base of the retaining wall) and / or
driveway surcharge loads.
12) Indicate on the plans that an OSHA permit will be obtained for the shoring* at the
excavation in the basement per CAL / OSHA requirements. See the Cal / OSHA
handbook at: http://www.ca-osha.com/pdfpubs/osha userquide.pdf. *Construction
Safety Orders : Chapter 4, Subchapter 4, Article 6 , Section 1541.1.
13) Indicate on the plans that a Grading Permit, if required, will be obtained from the
Department of Public Works.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
14) Provide guardrails at all landings. NOTE: All landings more than 30" in height at any
point are considered in calculating the allowable lot coverage. Consult the Planning
Department for details if your project entails landings more than 30" in height.
15) Provide handrails at all stairs where there are four or more risers.
16) Provide lighting at all exterior landings.
17) Prior to applying for a Building Permit the applicant must obtain an address for each
structure on the site, acceptable to the Fire Marshal, from the Engineering Department.
Note: The correct address must be referenced on all pages of the plans.
18) On your plans provide a table that includes the following:
a. Occupancy group for each area of the building
b. Type of construction
C. Allowable area
d. Proposed area
e. Allowable height
f. Proposed height
g. Proposed fire separation distances
h. Exterior wall and opening protection
i. Allowable
ii. Proposed
i. Indicate sprinklered or non-sprinklered
19) Illustrate compliance with the minimum plumbing fixture requirements described in the
2010 California Plumbing Code, Chapter 4, Table 4-1 Minimum Plumbing Facilities and
Table A - Occupant Load Factor.
20) Show compliance with all accessibility regulations found in the 2010 CBC for
commercial buildings including:
a. Accessible paths of travel
b. A level landing must be provided on each side of the door at all required
entrances and exits.
C. Accessible countertops
d. Accessible bathrooms
e. Accessible parking
21) Per CEO 3003.5, all structures four or more stories in height must have at least one
elevator that can accommodate a stretcher. See the referenced code section for
dimensions (80" x 54") and other details.
22) Provide an exit plan showing the paths of travel
23) In Assembly occupancies specify aisle widths that comply with Section 1025.9.
24) Specify the total number of parking spaces on site
25) All NEW non-residential buildings must comply with the requirements of AB-2176 Sec.
42911 (c) [2003 — 2004 Montanez) as follows:
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
a. Space for recycling must be a part of the project design in new buildings.
b. A building permit will not be issued unless details are shown on the project
plans incorporating adequate storage for collecting and loading recycled
materials.
26) Include with your Building Division plan check submittal a complete underground fire
sprinkler plan. Contact the Burlingame Water Division at 650-558-7660 for details
regarding the water system or Central County Fire for sprinkler details.
27) Sewer connection fees must be paid prior to issuing the building permit.
9. that the conditions of the NPDES Coordinators February 8, 2012 memo shall be met,
which includes the following comments:
a. The project will need to comply with additional and new Low Impact Development (LID)
requirements under the Municipal Regional Permit, C.3 Provisions, which became effective on
December 11, 2011. For details and technical guidance on these C.3 requirements visit the
San Mateo Countywide Water Pollution Prevention Program (SMCWPPP) at
http://www/flowstobay.orianas new development.php.
b. The following C.3 forms/worksheets have been updated and project proponents will need to
use and submit these forms as part of the final construction documents and associated
building permits:
1) NPDES Permit Impervious Surface Data Collection Worksheet*
2) C.3 and C.6 Development Review Checklist*.
*both forms are available for download at http://www/flowstobay.orcebs new development.php.
c. When submitting plans for a building permit include a list of construction stormwater pollution
prevention Best Management Practices (BMPs) as project notes and include them as a
separate full size plan sheet, preferably 2' x 3' or larger. Project proponents may use the
attached Construction Best Management Practices (BMPs) plan sheet to comply with this
requirement. Electronic file is available for download at http://www/flowstobay.orci/bs
construction. php (scroll about half -way down the page and click on Construction BMP Plan
Sheet).
10. that the conditions of the Parks Supervisor's February 6, 2012 memo shall be met, which includes the
following comments:
a. Submit a Landscape Project Application to the Parks Division in compliance with the Water
Conservation in Landscape Ordinance.
b. New trees in the Airport Boulevard islands shall be Platanus acerfolia 'Columbia'.
11. that the conditions of the Fire Marshal's April 26, 2010 memo shall be met, which includes the
following comments:
a. All buildings shall be equipped with fire alarms, fire sprinklers and standpipes where required
by the California Fire Code and the Burlingame Municipal Code.
b. Fire Flow and Fire Hydrants shall conform to Appendix B and C of the International Fire Code
2006 Edition.
c. Fire apparatus access shall be provided for all buildings in accordance with §503 of the
International Fire Code.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
d. Fire Control Room as required by the California Building Code shall be placed to the exterior
of the building with exterior access. Rooms shall be positioned facing fir apparatus access.
This requirement may negate exterior remote annunciators and key boxes intended to house
HMIS/HMMP as required for Burlingame Municipal Code.
e. Please see Burlingame Municipal Code specific to Addressing Requirements and Key Boxes
associated with Hazardous Materials.
f. The fire department shall request HMIS/HMIP in accordance with the California Fire Code. All
inventory lists shall at minimum indicate the hazardous material class and quantities
consistent with Table 2703.1.1(1), Title 24 CFC classes and units (i.e.: pounds, gallons, cubic
feet at NTP, etc.).
g. Space shall be provided within each Highrise for installation of a repeater/receiver antenna
and supporting equipment for City Communications. An electrical supply source shall be
provided at the antenna/equipment location. Reasonable access shall be provided to City
staff contractors for installation of necessary telephone lines and for purposes of
installation, maintenance, adjustment and repair of the antenna/equipment.
12. that the conditions of the Public Works Department, Engineering Division's May 8, 2012 memo shall
be met, which includes the following comments:
a. With City approval, the Developer proposes to construct a new, realigned Airport Boulevard
through the Project and to construct Bay Trail and Bay frontage improvements in the City's
right-of-way easement of the original Airport Boulevard. Developer understands that the
underlying fee of the original Airport Boulevard ROW, from the existing Sanchez Chanel
Bridge East to Fisherman's Park and South from Fisherman's Park to Beach Road, is owned
by the State of California, State Lands Commission and that the City only holds a ROW
easement over same. Developer shall give the State Lands Commission written notice of its
development plans and specifically, notice of the proposed improvements to be constructed
in the ROW of the original Airport Boulevard alignment, within ten (10) days of the Planning
Commission's recommendation of the Project to the City Council. At any time, should State
Lands have any concerns over said improvements, object to any aspect of the proposed
improvements or initiate any type of administrative or judicial action in regard to these
proposed improvements, Developer shall hold harmless, defend and indemnify the City, its
officers, agents and employees from any and all fees (including attorneys' fees), damages,
fines or any other costs of any kind related to such objections, claims or actions.
Additionally, the Developer shall obtain letters of no objection to the proposed
realignment of Airport Boulevard from all utility companies. The Project Developer shall
relocate all existing utilities from within the existing Airport Boulevard roadway to the
proposed realigned Airport Boulevard roadway to the satisfaction of the City Engineer and
affected utility companies.
b. The developer shall prepare necessary engineering drawings and construction documents to
construct the Sanchez Channel Bridge widening as identified in the existing BCDC permit to
provide the necessary width for pedestrian, bicyclist and vehicular access along Airport
Boulevard. The developer shall complete construction of these improvements at his/her
expense These drawings shall be approved by the City Engineer as part of the Building Permit
process.
c. The developer shall be responsible to meet all San Francisco Bay Conservation and
Development Commission (BCDC) requirements for the project and provide the City with
documentation of all approvals by BCDC for all work within 100 feet of the shoreline band
along the San Francisco Bay and Sanchez drainage channel.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
d. The developer shall enter into a Site Maintenance Agreement with the City for maintenance of
all landscape, sidewalk, medians, and stormwater improvements as well as roadway
improvements that do not conform to city standards, such as the proposed roadway
intersections. The Site Maintenance Agreement shall be executed prior to the issuance of the
Building permit.
e. All traffic improvements, including but not limited to traffic signals, pedestrian countdown
signals, pedestrian audible signals, signal interconnection hardware, street lights, signage,
street markings, etc., shall be approved by the City Engineer and installed at the property
owner's expense. The proposed streetlights must conform to current standards which
require Beta LED's or equivalent. The developer shall submit and obtain approval of the
required engineering drawings and specifications for all public improvements as part of the
building permit process.
f. The project shall reimburse to the City the operation, maintenance and energy costs of the
proposed traffic signals. The City will maintain the newly proposed traffic signal operations. The
operation cost of the traffic signal will be adjusted annually by the City based on prevailing
costs. The electricity costs will be based on direct billing by PG & E.
g. The developer shall provide at his/her expense shoreline access, adequate erosion
protection and site amenities to the standards established by the City and BCDC.
h. The Bay and drainage channel shorelines located on this property will require stabilization
improvements to provide flood protection for the public access trail and bridge. All shoreline
and drainage channel slope protection measures, need to be reviewed and approved by the
City Engineer.
i. The public and facility users shall be safely provided for and protected from the flooding of the
site in the event of a disaster. This includes a storm or an earthquake which coincides with a
maximum high tide and possible breaching of Sanchez Channel and/or Airport Boulevard
levees. The property owner shall employ a qualified engineer to analyze the seismic stability of
the Sanchez Channel and Airport Boulevard levees and identify protection against possible
earthquake or storm event. The property owner shall submit the structural and seismic stability
analysis to the City Engineer for review and approval. If the analysis indicates that
improvements are necessary along the project site to provide stability for an event, such
improvements shall be installed as approved by the City Engineer prior to occupancy of the first
building.
The developer shall be required to incorporate the following measures into project design in
order to reduce the potential impacts of flooding:
1) Necessary tide gates shall be installed in the storm drain system on the project site to
prevent high water from back flowing into the site during flood periods;
2) Adequate drainage and pump facilities, including a sound -baffled backup power supply,
shall be provided in the parking area to prevent water ponding in excess of ten (10) inches
in the event of a 100-year flood;
3) Storm drainage facilities shall be designed to accommodate any future settlement of the
site, levees and other fill along the site perimeter;
4) A flood contingency plan shall be developed to provide guidelines for management of
vehicles in the event of flooding of the parking area; and
5) On -site improvements shall be designed to provide 100-year flood protection. All
emergency equipment, generators, controls, and motors shall be located above the 100-
year flood elevation.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
k. The developer shall install a six-inch diameter recycled water main with the roadway
improvements. This six-inch line shall extend from the existing Sanchez Channel Bridge east
to the other end of the new roadway alignment near Beach Road. Initially the line shall be
connected to the City water main and serve as the service connection for irrigation. This line
and the irrigation system shall convert to a recycled water line once it becomes available.
These improvements shall be done at the property owner's cost and shall be completed in
concurrence with the roadway improvements.
I. The project developer shall implement and maintain an appropriate Transportation
Demand Management measures in accordance with the San Mateo County Congestion
Plan to reduce the number of trips generated by this project.
m. Detailed grading and drainage plans shall be submitted by the project developer for review by
the City Engineer at the time of applying for a building permit.
n. The project shall comply with the City's NPDES permit requirement to prevent storm water
pollution during and after the construction. In addition, the project developer shall provide all
documentation relating to compliance with the Regional Municipal Permit from the State of
California Water Resources Board.
o. It is possible that this project may require approvals and permits from the U.S. Army Corp of
Engineers, Department of Fish and Game, and the California Regional Water Quality Control
Board. The applicant must provide written records of contacting the above agencies
demonstrating that a permit has been obtained or is not required.
p. All street improvements plans shall be submitted to the City for review and approval These
improvements include but are not limited to sanitary sewer mains and laterals; water mains
and services; storm drain mains and inlets; street structural sections, soils report, etc.
Hydrologic and hydraulic calculations are required for all designs associated with the new
road alignment. The road structural section shall be designed to a traffic index of minimum
12.0 and shall withstand vertical displacement due to natural subsurface settlement. The
structural section shall be designed for a 20-year life based on recommendations of a
professional geotechnical engineer and accompanying soils report.
q. The project developer shall perform necessary engineering studies to determine the required
capacity and improvements to the system to be approved by the City Engineer. At the City's
discretion, the sanitary sewer improvements shall be routed along Airport Boulevard to an
existing pump station, thence along Airport Boulevard to the Wastewater Treatment Plant.
The sanitary sewer system improvements shall be designed and constructed to
accommodate the fully built -out conditions of the project and adjacent properties.
r. The project shall abandon the existing potable water main located within existing alignment of
Airport Boulevard from Fisherman's Park to Beach Road. The project shall evaluate the
existing condition of the water main. If necessary and at the City's discretion, the project shall
design and construct a new potable water main system along the newly proposed Airport
Boulevard from Beach Road to the Sanchez Channel as well as the replace the existing
potable water main segment from Sanchez Channel to Fisherman's Park.
s. The project shall install purple piping in buildings for future reclaimed water use in building
applications.
13. that early demolition, mass excavation, grading, shoring and foundation permits, including permits for
installation of indicator/production piles, may be issued in advance of a building permit provided that
prior to issuance of such permits, the applicant has submitted construction plans for the project to the
Building Division, or has provided evidence that it is having such plans prepared for the project for
which the demolition or grading work is intended. Further, building construction permits shall be
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
submitted and received in accordance with the progress of the work which will occur in phases.
Permits that may be submitted individually for application may include, but are not limited to,
indicator/production piles, mass excavation, shoring, grading, foundations, superstructure, architecture
MEP, fire protection, fire alarm, curtain wall, and so forth, subject to the consent of the City's Building
Official and the Fire Marshal. Building Permit phasing and scheduling shall be arranged with the
Project Applicant and the Community Development Department — Building Division, such that the work
can proceed in an orderly fashion as one continuous phase of construction;
14. that the project shall comply with the Construction and Demolition Debris Recycling Ordinance which
requires affected demolition, new construction and alteration projects to submit a Waste Reduction
plan and meet recycling requirements; any partial or full demolition of a structure, interior or exterior,
shall require a demolition permit;
15. Exterior lighting for the project would be designed to meet the requirements of Burlingame Municipal
Code Section 18.16.030 (pertaining to light spillage off site in commercial or residential areas), the
California Energy Commission, and the Illuminating Engineering Society of North America for
illumination levels. Compliance with these performance standards would minimize the dispersion of
light in a manner that reduces the glow or aurora effect to acceptable and allowable levels. In addition,
the project area already contains numerous sources of exterior lighting, and is not adjacent to uses
that would be sensitive to light spillover.
16. that the applicant shall comply with Ordinance 1503, the City of Burlingame Storm Water Management
and Discharge Control Ordinance;
17. that the overall height of the buildings as measured from the top of curb at Airport Boulevard (+ 14.5'
elevation) to the top of the mechanical screens shall be no taller than the following heights: Buildings
B1 and B2, 97.0', Building 83, 129.0', Building B4, 144.0% Parking Structure, 67.5', and Amenities
Building, 49.0'; building heights shall be surveyed at the framing of each floor and at the installation
of the mechanical screen and shall be reported to the Building Division as each floor is framed and
accepted by the City Engineer before framing of the subsequent floor or roof commences. The
elevator overruns and associated structures shall be permitted to exceed the stated height limits to
the degree that such exceedance is necessitated by the Uniform Building Code in order for elevators
to serve their intended purpose of providing access by persons to the rooftop terraces on the
buildings. The entire building height of each structure shall be surveyed to confirm conformance with
the approved plans and conditions of approval before scheduling the final framing inspection. If the
building does not conform at any point in the construction process, it shall be made to conform before
construction continues and any further city inspections shall be scheduled (Building Division);
18. that the applicant shall pay the required Bayfront Development Fee based on the square footage of
the buildings and the current rate adjusted for inflation, the total fee due is calculated to be
$1,695,070.00. Per the development agreement, one-half of the fee is due at the time of issuance of
the first City Building Permit for construction of a building, and one-half is due before the final framing
inspection is scheduled, for each Development Phase. The fee due shall be offset by the actual costs
incurred by Developer in designing, preparing, installing and constructing (a) the realignment and
widening of Airport Boulevard but limited to the customary and ordinary costs for such improvements
without special pedestrian treatments, and (b) the Sanchez Channel bridge widening as outlined in
the Development Agreement (Planning Division);
19. that the applicant shall pay the required public facilities impact fees based on the square footage of
the buildings, and that the Parks and Recreation fee ($131,924.00) and the Storm Drain Fee
($549,939.00) shall be waived, the total remaining fee due shall be $1,102,179.00. The remaining fees
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
shall be payable by development phase, and shall be submitted to the Planning Division prior to the
issuance of the first building permit for construction of each building as follows: Building 61:
$209,802.00, Building 62: $209,802.00, Building 133: $293,722.80, Building B4, $335,683.20, and
Amenities Center: $53,169.00 (Planning Division):
20. that the property owner shall be responsible to see that small delivery trucks or vans making periodic
deliveries are on -site only during office hours; no trucks, recreation vehicles or other vehicles shall be
stored or parked on site continuously throughout the day or overnight, and no parking shall be leased
to tenants or any other users for any purpose,
21. that the Property Owner, in the event the Property is leased to multiple tenants, or the tenant in the
event that the entire Property is leased to a sole tenant, shall implement a comprehensive
transportation demand management (TDM) program to the satisfaction of the Community
Development Director in order to achieve the same or greater peak hour trip reductions as the TDM
Program prepared by Fehr and Peers for 350 Beach Road, LLC dated April 5, 2011. Such TDM
Program may include measures such as:
a. Secure Bicycle Storage: Secure, indoor bicycle storage for at least 26 bicycles shall be
provided in a lobby or garage level room within each of the four office buildings. In addition,
bicycle racks for up to 50 bicycles will be located outside of Buildings #1 or #4.
b. Showers and Changing Rooms: Shower facilities with changing rooms shall be provided
throughout the site, with access available to all employees. Shower facilities (two men's and
two women's) and changing rooms (one men's and one women's) shall be provided in each of
the four office buildings, the amenities center shall include 12 showers and two changing
rooms.
c. Shuttle Service: Coordinate with the Peninsula Commuter Alliance to add two stops within
the project site to the existing commuter shuttle from the Millbrae Intermodal Station. The
shuttle provides 10-minute headways during peak periods.
d. Carpool Parking: Provide 15 preferential parking spaces for carpools at each of the four
office buildings.
e. Vanpool Parking: Provide two preferential parking spaces for vanpools at each of the four
office buildings.
f. Commute Assistance Center:
1) Provide an on -site one -stop shopping for transit and commute alternatives information.
2) Provide a part-time on -site TDM coordinator available to assist building tenants with
trip planning.
g. Employees' Surveys: The TDM coordinator shall develop and administer two surveys per
year to examine TDM program participation and best practices.
h. Video Conferencing Center: One video conferencing center of approximately 8500 sf shall
be installed for use by the tenants of the facility.
i. On -Site Amenities/Accommodations: On -site amenities, including banking, retail, delivery
dry cleaning, exercise facilities, child care center, delivery pharmacy and food service shall be
provided at the project site to encourage people to stay on site during the work day;
j. On -Site Bicycles for Employee Use- Bicycles shall be provided at each office building.
Employees will have access to bicycles during breaks for personal or business use.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
k. Child Care Services: Child care center service shall be provided on site;
Guaranteed Ride Home Program: Employees will have access to the Guaranteed Ride
Home (GRH) program administered by the Peninsula Congestion Relief Alliance (Alliance)
for emergencies. The program provides vouchers for taxicabs or rental cars for this
purpose.
m. Transportation Action Plan: The TDM coordinator shall work with the Alliance to create a
Transportation Action Plan for each tenant.
n. Transportation Management Association: If the office park has multiple tenants, each
tenant shall provide a representative to form a Transportation
Management Association and be a liaison to the TDM Coordinator.
o. Coordination of Transportation Demand Management Programs: The TDM coordinator
shall coordinate with other TDM programs with existing developments/employers in the
surrounding area.
p. Subsidy for Transit Tickets: Employers shall offer subsidies to employees to compensate
them for the cost of transit tickets.
q. Electric Vehicle Stations: The applicant shall provide plug-in stations for electric vehicles.
r. House Car for Employee Use: Each building will provide employees with access to a "house
car" for use during the day.
THE FOLLOWING CONDITIONS SHALL BE MET DURING THE BUILDING INSPECTION PROCESS
PRIOR TO THE INSPECTIONS NOTED IN EACH CONDITION:
22. that prior to scheduling the framing inspection, the project architect, engineer or other licensed
professional shall provide architectural certification that the architectural details such as window
locations and bays are built as shown on the approved plans; if there is no licensed professional
involved in the project, the property owner or contractor shall provide the certification under penalty of
perjury. Certifications shall be submitted to the Building Department;
23. that prior to scheduling the roof deck inspection, a licensed surveyor shall shoot the height of the
roof ridge and provide certification of that height to the Building Division; and
24. that prior to final inspection, Planning Division staff will inspect and note compliance of the
architectural details (trim materials, window type, etc.) to verify that the project has been built
according to the approved Planning and Building plans.
Mitigation Measures from Environmental Impact Report:
Measures Applicable to 300 Airport Boulevard Project as well as future development of the 350
Airport Boulevard site:
25. Amphlett Poplar Intersection: The City of San Mateo is considering a range of potential improvements
at the Amphlett Boulevard/Poplar Avenue intersection to provide sufficient capacity for existing and
future traffic volume. However, a specific improvement project has not been identified at this time. The
Project Sponsor, and any future project sponsor for development of the 350 Airport Boulevard site,
shall negotiate an agreement with the City of San Mateo to make a fair share contribution toward the
cost of improvements at this intersection for each projects respective impacts (Transportation,
Planning, Public Works, City of San Mateo);
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
26. Implement Recommended Dust Control Measures. To reduce particulate matter emissions during
Project excavation and construction phases, the Project contractor(s) shall comply with the dust
control strategies developed by BAAQMD. The Project Sponsor shall include in all construction
contracts the following requirements or measures:
• All exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and unpaved
access roads) shall be watered two times per day.
• All haul trucks transporting soil, sand, or other loose material off -site shall be covered.
• All visible mud or dirt track -out onto adjacent public roads shall be removed using wet power
vacuum street sweepers at least once per day. The use of dry power sweeping is prohibited.
• All vehicle speeds on unpaved roads shall be limited to 15 mph.
• All roadways, driveways, and sidewalks to be paved shall be completed as soon as possible.
Building pads shall be laid as soon as possible after grading unless seeding or soil binders are
used.
• Idling times shall be minimized either by shutting equipment off when not in use or reducing the
maximum idling time to 5 minutes (as required by the California airborne toxics control measure
Title 13, Section 2485 of California Code of Regulations [CCR]). Clear signage shall be
provided for construction workers at all access points.
• All construction equipment shall be maintained and properly tuned in accordance with
manufacturer's specifications. All equipment shall be checked by a certified mechanic and
determined to be running in proper condition prior to operation.
• Post a publicly visible sign with the telephone number and person to contact at the Lead Agency
regarding dust complaints. This person shall respond and take corrective action within 48 hours.
The Air District's phone number shall also be visible to ensure compliance with applicable
regulations. (Air Quality; (Planning and Building Divisions);
27. Construction Equipment Emissions Minimization. To reduce the potential impacts resulting from
Project construction activities, the Project Sponsor shall include in contract specifications a
requirement for the following measures:
Idling times shall be minimized either by shutting equipment off when not in use or reducing the
maximum idling time to two minutes;
The Project shall develop a construction plan demonstrating that the off -road equipment (more
than 50 horsepower) to be used in the construction Project (i.e., owned, leased, and
subcontractor vehicles) would achieve a Project wide fleet -average 20 percent NOx reduction
and 45 percent PM reduction compared to the most recent CARB fleet average (as specified in
California Code of Regulations Article 4.8, Section 2449 General Requirements for In -Use Off -
Road Diesel -Fueled Fleets). Acceptable options for reducing emissions include the use of late
model engines, low -emission diesel products, alternative fuels, engine retrofit technology, after -
treatment products, add -on devices such as particulate filters, and/or other options as such
become available;
All construction equipment, diesel trucks, and generators shall be equipped with Best
Available Control Technology for emission reductions of NOx and PM;
Use of Interim Tier 4, if applicable, or equivalent equipment for all uses where such equipment
is available;
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
• Use of Tier 3 equipment with Best Available Control Technology (BACT) or alternative fuel
vehicles for applications where Tier 4 Interim engines are not available;
• Prohibition of diesel generators for construction purposes where feasible altemative sources of
power are available;
• All construction equipment shall be maintained in proper working condition in accordance with
manufacturer's specifications;
• Diesel -powered construction equipment shall comply with BAAQMD requirements or meet Tier
3 or Tier 4 EPA/CARB standards; and
• To the extent feasible, the existing electricity infrastructure surrounding the construction sites
shall be used rather than electrical generators powered by internal combustion engines. (Air
Quality; Planning and Building Divisions)
28. Application of Low-VOC Coatings. The Project Sponsor shall use low VOC (i.e., ROG) coatings
beyond the local requirements as per the BAAQMD Guideline (i.e., Regulation a Rule 3: Architectural
Coatings) (Air Quality; Planning and Building Divisions);
29. Implement Best Management Practices to Reduce Construction Noise. The following BMPs shall be
incorporated into the construction documents to be implemented by the Project contractor.
a. Maximize the physical separation between noise generators and noise receptors. Such
separation includes, but is not limited to, the following measures:
i. Use heavy-duty mufflers for stationary equipment and barriers around particularly noisy
areas of the site or around the entire site;
ii. Use shields, impervious fences, or other physical sound bafflers to inhibit transmission
of noise to sensitive receptors;
iii. Locate stationary equipment to minimize noise impacts on the community; and
iv. Minimize backing movements of equipment.
b. Use quiet construction equipment whenever possible.
c. Impact equipment (e.g., jack hammers and pavement breakers) shall be hydraulically or
electrically powered wherever possible to avoid noise associated with compressed air
exhaust from pneumatically -powered tools. Compressed air exhaust silencers shall be
used on other equipment. Other quieter procedures, such as drilling rather than using
impact equipment, shall be used whenever feasible.
d. Prohibit unnecessary idling of internal combustion engines.
e. Select routes for movement of construction -related vehicles and equipment in conjunction
with the Burlingame Planning Division so that noise -sensitive areas, including residences
and schools, are avoided as much as possible.
f. The project sponsor shall designate a "disturbance coordinator for construction
activities. The coordinator would be responsible for responding to any local complaints
regarding construction noise and vibration. The coordinator would determine the cause
of the noise or vibration complaint and would implement reasonable measures to
correct the problem. (Noise, Planning and Building Divisions);
30. Notify Nearby Businesses of Construction Activities that Could Affect Vibration -Sensitive Equipment.
The Project Sponsor shall provide notification to adjacent property owners and occupants, prior to
the start of construction, informing them of the estimated start date and duration of vibration-
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
generating construction activities during site preparation, grading, and pile driving, if required. This
notification shall include information warning about the potential for impacts related to vibration -
sensitive equipment. The Project Sponsor shall identify a phone number for the property owners
and occupants to call if they have vibration -sensitive equipment on their site. (Noise, Planning and
Building Divisions);
31. Implement Construction BMPs to Reduce Construction Vibration. The Project Sponsor shall
implement the following measures during construction of all Project components:
• To the extent feasible, construction activities that could generate high vibration levels at any
identified vibration -sensitive locations shall be scheduled during times that would have the least
impact on nearby land uses. This could include restricting construction activities in the areas of
potential impact to the early and late hours of the work day, such as from 8:00 a.m. to 10:00 am.
or 4: 00 p.m. to 6: 00 p.m. Monday to Friday.
• Stationary sources, such as construction staging areas and temporary generators, shall be
located as far from nearby vibration -sensitive receptors as possible.
• Trucks shall be prohibited from idling along streets serving the construction site where vibration -
sensitive equipment is located.
• Avoid pile driving when possible within 100 feet of an existing structure. (Noise, Planning and
Building Divisions);
32. Implement Alternative Pile Driving Methods. The Project Sponsor shall use alternative pile driving
methods (e.g., drilled or steel piles) for piles driven in proximity to existing vibration receptors such
that vibration levels at vibration -sensitive equipment shall not exceed 65 VdB. (Noise, Planning and
Building Divisions);
33. Bird Nest Pre -Construction Survey. The Project Sponsor(s) shall retain a qualified biologist to
conduct preconstruction breeding -season surveys (approximately March 15 through August 30) of
the Project Site and immediate vicinity during the same calendar year that construction is planned to
begin, in consultation with the CDFG as discussed below.
If phased construction procedures are planned for the Project, the results of the above survey shall be
valid only for the season when it is conducted. A report shall be submitted to CDFG, following the
completion of the bird nesting survey that includes, at a minimum, the following information:
• A description of methodology including dates of field visits, the names of survey personnel with
resumes, and a list of references cited and persons contacted.
• A map showing the location(s) of any bird nests observed on the Project Site.
If the above survey does not identify any nesting bird species on the Project Site, no further mitigation
would be required. However, should any active bird nests be located on the Project Site, the following
mitigation measure shall be implemented. (Biological Resources, Planning Division);
34. Bird Nest Buffer Zone. The Project Sponsor(s), in consultation with CDFG, shall delay construction in
the vicinity of active bird nest sites located on or adjacent to the Project Site during the breeding
season (approximately March 15 through August 30) while the nest is occupied with adults and/or
young. If active nests are identified, construction activities should not occur within 500 ft of the nest. A
qualified biologist shall monitor the active nest until the young have fledged, until the biologist
determines that the nest is no longer active, or if it is reasonable that construction activities are not
disturbing nesting behaviors. The buffer zone shall be delineated by highly visible temporary
construction fencing. (Biological Resources, Planning and Building Divisions);
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
35. In order to reduce significant impacts to the City's wastewater conveyance and treatment system
associated with the Project the Proiect Sponsor shall adhere to either of the two following mitigation
measures..
a. Upgrade Pump Capacity at the Existing 399 Rollins Road Pump Station and Reduce Inflow and
Infiltration within the Wastewater System. The Project Sponsor(s) shall contribute fair -share
funds toward the upgrade of the 399 RRPS capacity, or equivalent project to increase capacity
in the system, to accommodate the increased PWWF that would result from implementation of
the Project. Additionally, the Project Sponsor(s) shall rehabilitate the existing wastewater
system, where necessary, to reduce inflow and infiltration that contributes to PWWFs at the
WWTP in an amount concomitant with increases in flows contributed by the 300 Airport
Boulevard Project.
b. Upgrade to the Existing Airport Boulevard Conveyance System Variant to Rollins Road Pump
Station Upgrade. The Project Sponsor(s) shall coordinate with the City of Burlingame Public
Works Department to upgrade the capacity of the City's wastewater conveyance and
treatment system to accommodate the increased PWWF that would result from
implementation of development of the 300 and 350 Airport Boulevard Sites. Such measures
could include, as necessary, installation of a new pump station within public right of way or
other area near the Sanchez Channel Bridge on the Project Site, upgrade the capacity of the
existing Airport Boulevard Pump Station, extension of wastewater lines across Sanchez
Channel, via attachment to the Sanchez Channel Bridge, to tie into existing wastewater lines
under Airport Boulevard west of the Project Site, and increasing, as required, the capacity of
existing gravity lines between the Project.
Site and the Airport Boulevard Pump Station and existing force main between the Airport
Boulevard Pump Station and the WWCp. The Project Sponsor shall construct the necessary
improvements to serve the Project Site and additional properties along Airport Boulevard that
would connect to this sewer line. (Utilities, Public Works Department);
36. Undiscovered Cultural Resources. If evidence of an archaeological site or other suspected cultural
resource as defined by CEQA Guideline Section 15064.5, including darkened soil representing past
human activity ("midden'), that could conceal material remains (e.g., worked stone, worked bone, fired
clay vessels, faunal bone, hearths, storage pits, or burials) is discovered during construction -related
earth -moving activities, all ground -disturbing activity within 100 feet of the resources shall be halted
and the City of Burlingame shall be notified. The Project Sponsor shall hire a qualified archaeologist to
conduct a field investigation. The City of Burlingame shall consult with the archeologist to assess the
significance of the find. Impacts to any significant resources shall be mitigated to a less -than -
significant level through data recovery or other methods determined adequate by a qualified
archaeologist and that are consistent with the Secretary of the Interior's Standards for Archaeological
Documentation.
37. Unique Paleontological/Geological Features. Should a unique paleontological resource or site or
unique geological feature be identified at the project construction site during any phase of
construction, the Project manager shall cease all construction activities at the site of the discovery and
immediately notify the City of Burlingame. The Project Sponsor shall retain a qualified paleontologist
to provide an evaluation of the find and to prescribe mitigation measures to reduce impacts to a less -
than -significant level. Work may proceed on other parts of the project site while mitigation for
paleontological resources or geologic features is carried out. The Project Sponsor shall be responsible
for implementing any additional mitigation measures prescribed by the paleontologist and approved by
the City.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
38. Human Remains. If human remains are discovered at any Project construction site during any phase
of construction, all ground -disturbing activity 100 feet of the resources shall be halted and the City of
Burlingame and the San Mateo County coroner shall be notified immediately, according to Section
5097.98 of the State Public Resources Code and Section 7050.5 of California's Health and Safety
Code. If the remains are determined by the County coroner to be Native American, the Native
American Heritage Commission (NAHC) shall be notified within 24 hours, and the guidelines of the
NAHC shall be adhered to in the treatment and disposition of the remains. The Project Sponsor shall
also retain a professional archaeologist with Native American burial experience to conduct a field
investigation of the specific site and consult with the Most Likely Descendant, if any, identified by the
NAHC. As necessary, the archaeologist may provide professional assistance to the Most Likely
Descendant, including the excavation and removal of the human remains. The City of Burlingame
shall be responsible for approval of recommended mitigation as it deems appropriate, taking account
of the provisions of State law, as set forth in CEQA Guidelines section 15064.5(e) and Public
Resources Code section 5097.98. The project applicant shall implement approved mitigation, to be
verified by the City of Burlingame, before the resumption of ground -disturbing activities within 100 feet
of where the remains were discovered.
MITIGATION MEASURES APPLICABLE ONLY TO THE 300 AIRPORT BLVD. PROJECT
39. Reduce Risk of Exposure During Construction. If the childcare center is operational during the
construction of Phase 2 of the Project, one of the following shall be implemented:
a. A Health Risk Assessment is conducted prior to commencement of construction of Phase 11 that
demonstrates, to the satisfaction of the BAAQMD, that impacts to the children at the childcare
center are less than significant during Phase 11 construction or specific sub phases of Phase II
construction; or
b. Implement the following building design and operational restrictions.
1. The childcare center building shall be designed such that the air intake would be
located at the far eastern edge of the building with the air intake facing east.
2. A MERV 15 or higher rated filter shall be installed and operated for at least the duration
of construction activities. The MERV 15 or higher rated filters have the potential to
remove up to 85 percent of particles of 2.5 microns or greater thereby reducing interior
levels of pollutants.
3. All outdoor activities at the childcare center shall be suspended while construction
activities are occurring.
If implementation of this Mitigation Measure is infeasible, then the childcare center would be prohibited
from operating during Phase 11 construction. (Air Quality, Building and Planning Divisions);
40. Maintenance and Testing of Generators. As part of the conditions of operation for the onsite back-up
generators, all diesel emissions associated with the maintenance and testing of the generators
should be conducted at such times as the daycare center is not in operation, particularly nights and
weekends. (Air Quality, Building and Planning Divisions);
41. Implementation of MERV 15 Filters. The Project Sponsor shall consider implementing MERV 15 or
higher rated filters for the amenities building. This would further reduce exposure of daycare students
to emissions from US 101. The MERV 15 or higher rated filters have the potential to remove up to 85
percent of PM2.5 and would reduce risk while students were inside the building. (Air Quality, Building
and Planning Divisions);
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
42. Incorporate GHG Reduction Measures for Maintenance Activities. The Project Sponsor shall provide
infrastructure for the use of electric landscape equipment during landscaping activities, where
feasible. (Climate Change, Planning Division and Parks Department);
43. Incorporate Trees and Vegetation into Project Design. Trees and other shade structures shall be
incorporated into the Site Plan to maximize summer shade and to minimize winter shade. (Climate
Change, Planning Division and Parks Department);
44. Renewable Energy System. The 300 Airport Boulevard Project shall offset 10 percent of project
electricity demand through implementation of onsite renewable energy systems or through investment
in offsite alternative energy systems. (Climate Change, Planning and Building Divisions);
45. Drought Tolerant Landscaping. The 300 Airport Boulevard Project shall reduce irrigation -related
water demand by a minimum of 10 percent through the implementation of drought tolerant
landscaping. (Climate Change, Planning Division and Parks Department);
46. Cool Roof Material. The 300 Airport Boulevard Project shall incorporate cool -roof materials into project
design to reduce electricity demand associated with building heating, ventilation, and air conditioning
(HVAC) by a minimum of 7 percent. (Climate Change, Planning and Building Divisions);
47. Water Conservation Measures. The 300 Airport Boulevard Project shall implement immediate water
conservation measures to reduce building water demand by 33 percent. Building water demand
shall ultimately be reduced by 50 percent when the City's recycled water system is implemented.
(Climate Change, Planning and Building Divisions);
48. Energy Efficiency beyond Title 24 Standards. The 300 Airport Boulevard Project shall reduce building
energy demand beyond the 2005 Title 24 Standards by 26 percent (Climate Change, Planning and
Building Divisions);
49. Operation Solid Waste Reduction. The 300 Airport Boulevard Project shall implement a solid waste
reduction program to reduce operational solid waste by a minimum of 10 percent (Climate Change,
Planning Division);
50. Utilize Alternative Fueled Vehicles and Local Building Materials. In accordance with BAAQMD BMPs,
the Project Sponsor shall incorporate into the construction fleet a minimum of 15 percent of
construction vehicles and equipment operated by alternative fuels. Further, the Project Sponsor shall
ensure that a minimum of 10 percent of building materials are locally sourced, where feasible.
(Climate Change, Planning and Building Divisions);
51. Conduct a Wetland Delineation. The Project Sponsor shall retain a qualified biologist to conduct a
wetland delineation of the Project Site. This delineation shall be submitted to the Corps for
verification prior to the issuance of any grading permits for the Project. If the Corps determines that
the features in the Project Site are not jurisdictional, then no further mitigation would be required.
(Biological Resources, Planning and Building Divisions);
52. Obtain Applicable Permits and Certifications. If the Corps determines that these features are
jurisdictional, then the Project Sponsor must obtain a CWA Section 404 permit from the Corps, and
a CWA Section 401 Water Quality Certification from the RWQCB prior to issuance of any grading
permits for the Project. A requirement of the permits will be compensation such that there is no net
loss of wetlands. This compensation requirement can be satisfied through avoidance, onsite and/or
offsite construction and preservation of wetlands or by purchase of mitigation credits at an
W/:11-3kdV_I%
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
approved mitigation bank. At certified mitigation banks, the Corps typically requires a minimum 1:1
ratio, but may require higher ratios for certain wetland types. (Biological Resources, Planning and
Building Divisions);
53. Provide Flood Protection up to the 100-Year Flood Event plus Sea Level Rise for Underground
Structures. To protect underground structures from sea level rise flood risks, prior to approving
grading and/or building permits the City shall ensure that the project design incorporates its
floodplain development requirements into all applicable project features using a flood elevation of at
least 7.1 feet. All below -ground structures, including storm drains, sewers, equipment facilities, and
others, shall be flood proofed and designed to withstand hydrostatic forces and buoyancy from
water surface elevations up to 7.1 feet in elevation. Certain portions of the shoreline open space
may not be protected at the ultimate level of flooding, given proposed heights. However, developed
areas of the Project would be protected. For the shoreline areas, an adaptive strategy would be
developed to address end -of -century conditions. (Hydrology, Building Division and Public Works
Department);
54. Provide Adequate Storm Flow Conveyance Capacity for Sea Level Rise Conditions. To ensure that
the storm drain system conveyance capacity is not constricted by sea level rise at the outlets, the
Project Sponsor shall design the storm drain system to adequately convey stormwater runoff at
outlet water surface elevations equivalent to the 100-year flood event base elevation plus sea level
rise of 55 inches (water surface elevation of 11.6 feet at the outlet). Prior to receiving a grading
permit, the City shall review project designs and studies for adequacy of storm flow conveyance with
an outlet surface water elevation of 11.6 feet and in accordance with City design standards. The
City shall prepare Conditions of Approval, where necessary, to ensure that the design criteria are
met. The Project Sponsor shall incorporate applicable City Conditions of Approval into project
designs, prior to receiving a grading permit. (Hydrology, Public Works Department);
55. Provide Protection of Shoreline and Flood Protection Features from Hydrodynamic Forces from Sea
Level Rise Conditions. Prior to receiving a grading permit, in order to ensure that the shoreline and
flood protection features associated with the proposed project provide protection under sea level
rise hydrodynamic and/or hydrostatic conditions, the Project Sponsor shall prepare engineering
studies to identify expected hydrodynamic forces for under storm surge conditions (at least 2
percent wave run-up) and a base flood elevation of at least 11.6 feet and hydrostatic forces from a
water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea level rise). For the
shoreline areas, an adaptive strategy would be implemented to address end -of -century conditions.
The Project Sponsor shall design shoreline and flood protection features that could accommodate
hydrodynamic forces from sea level rise conditions along wherever flood protection features are
identified under Mitigation Measure HY-7.1 and at shoreline protection features for stability and
integrity under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of at
least 11.6 feet. The Project Sponsor shall also design flood protection features for protection against
hydrostatic forces from a water surface elevation of 8A feet (mean higher high water plus 55-inch sea
level rise). The City shall review designs and associated studies for conformance with City
requirements and adequacy of design measures to withstand hydrodynamic and hydrostatic forces
associated with the design criteria.
The Project Sponsor shall also design erosion protection along the shoreline set -back area for
protection under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of
at least 11.6 feet. The City shall review designs and associated studies for adequacy in protecting the
shoreline set -back area under these conditions.
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
The City Public Works Department shall prepare Conditions of Approval, where necessary, to ensure
that the design criteria are met. Prior to receiving a grading permit, the Project Sponsor shall
incorporate applicable City and BCDC Conditions of Approval into project designs.
MITIGATION MEASURES APPLICABLE TO THE FUTURE DEVELOPMENT OF THE 350
AIRPORT BOULEVARD SITE
56. Implement TDM Program as part of 350 Airport Boulevard Proiect. These measures could include:
secure bicycle storage, showers and changing rooms, shuttle service, preferential parking for
carpoolers, preferential parking for vanpoolers, commute assistance center, employees' surveys,
video conferencing centers, on -site amenities accommodations, on -site bicycles for employees, child
care services, guaranteed ride home program, transportation action plan, transportation management
association, and coordination of TDM programs (Air Quality, Planning Division);
57. Implement enemy efficiency measures with 350 Airport Boulevard Protect. These measures could
include: LEED certification or to exceed energy efficiency beyond Title 24 requirements which would
further aid in reducing stationary source emissions (Air Quality; Planning and Building Divisions);
58. Incorporate GHG Reduction Measures for Maintenance Activities. The Project Sponsor shall provide
infrastructure for the use of electric landscape equipment during landscaping activities, where
feasible. (Climate Change, Planning Division and Parks Department);
59. Incorporate Trees and Vegetation into Project Design. Trees and other shade structures shall be
incorporated into the Site Plan to maximize summer shade and to minimize winter shade. (Climate
Change, Planning Division and Parks Department);
60. Renewable Energy System. The 350 Airport Boulevard Project shall offset 10 percent of project
electricity demand through implementation of onsite renewable energy systems or through investment
in offsite alternative energy systems. (Climate Change, Planning and Building Divisions);
61. Drought Tolerant Landscaping. The 350 Airport Boulevard Project shall reduce irrigation -related
water demand by a minimum of 10 percent through the implementation of drought tolerant
landscaping. (Climate Change, Planning Division and Parks Department);
62. Cool Roof Material. The 350 Airport Boulevard Project shall incorporate cool -roof materials into project
design to reduce electricity demand associated with building heating, ventilation, and air conditioning
(HVAC) by a minimum of 7 percent (Climate Change, Planning and Building Divisions);
63. Water Conservation Measures. The 350 Airport Boulevard Project shall implement immediate water
conservation measures to reduce building water demand by 33 percent. Building water demand
shall ultimately be reduced by 50 percent when the City's recycled water system is implemented.
(Climate Change, Planning and Building Divisions);
64. Enemy Efficiency beyond Title 24 Standards. The 350 Airport Boulevard Project shall reduce building
energy demand beyond the 2005 Title 24 Standards by 26 percent (Climate Change, Planning and
Building Divisions);
65. Operation Solid Waste Reduction. The 350 Airport Boulevard Project shall implement a solid waste
reduction program to reduce operational solid waste by a minimum of 10 percent. (Climate Change,
Planning Division);
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
66. Implement a TDM program. am. The Project Sponsor shall ensure that future development of the 350
Airport Boulevard Site implement a TOM program similar to that described for the 300 Airport
Boulevard Project, to reduce transportation -related GHG emissions. (Climate Change, Planning
Division and Traffic Engineer);
67. Pursue LEED Certification. Future development of the 350 Airport Boulevard Site shall seek LEED
Gold certification or equivalent for development per the recommendations of the City's Green Building
Ordinance. The Project Sponsor shall submit draft LEED (or equivalent) checklists to the City
Sustainability Coordinator for review and consultation. (Climate Change, Planning and Building
Divisions);
68. Placement or Screening of HVAC Mechanical Equipment. All HVAC mechanical equipment shall be
located more than 60 feet from the nearest property line. Altematively, HVAC mechanical equipment
may be installed in a noise enclosure sufficient to reduce ground -level noise levels at the nearest
property boundary to 70 dBA CNEL or less. (Noise, Planning and Building Divisions);
69. Provide Flood Protection up to the 100-Year Flood Event plus Sea Level Rise for Unde rrcroound
Structures. To protect underground structures from sea level rise flood risks, prior to approving
grading and/or building permits the City shall ensure that the project design incorporates its floodplain
development requirements into all applicable_nroject features using a flood elevation of at least
7.1 feet. All below -ground structures, including storm drains, sewers, equipment facilities, and
others, shall be flood proofed and designed to withstand hydrostatic forces and buoyancy from
water surface elevations up to 7.1 feet in elevation. Certain portions of the shoreline open space
may not be protected at the ultimate level of flooding, given proposed heights. However, developed
areas of the Project would be protected. For the shoreline areas, an adaptive strategy would be
developed to address end -of -century conditions. (Hydrology, Building Division and Public Works
Department);
70. Provide Adequate Storm Flow Conveyance Capacity for Sea Level Rise Conditions. To ensure that
the storm drain system conveyance capacity is not constricted by sea level rise at the outlets, the
Project Sponsor shall design the storm drain system to adequately convey stormwater runoff at
outlet water surface elevations equivalent to the 100-year flood event base elevation plus sea level
rise of 55 inches (water surface elevation of 11.6 feet at the outlet). Prior to receiving a grading
permit, the City shall review project designs and studies for adequacy of storm flow conveyance with
an outlet surface water elevation of 11.6 feet and in accordance with City design standards. The
City shall prepare Conditions of Approval, where necessary, to ensure that the design criteria are
met. The Project Sponsor shall incorporate applicable City Conditions of Approval into project
designs, prior to receiving a grading permit (Hydrology, Public Works Department);
71. Provide Protection of Shoreline and Flood Protection Features from Hydrodynamic Forces from Sea
Level Rise Conditions. Prior to receiving a grading permit, in order to ensure that the shoreline and
flood protection features associated with the proposed project provide protection under sea level
rise hydrodynamic andlor hydrostatic conditions, the Project Sponsor shall prepare engineering
studies to identify expected hydrodynamic forces for under storm surge conditions (at least 2
percent wave run-up) and a base flood elevation of at least 11.6 feet and hydrostatic forces from a
water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea level rise). For the
shoreline areas, an adaptive strategy would be implemented to address end -of -century conditions.
The Project Sponsor shall design shoreline and flood protection features that could accommodate
hydrodynamic forces from sea level rise conditions along wherever flood protection features are
identified under Mitigation Measure HY-7.1 and at shoreline protection features for stability and
integrity under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of at
least 11.6 feet. The Project Sponsor shall also design flood protection features for protection against
EXHIBIT "A"
Conditions of approval for Commercial Design Review Amendment
300 Airport Boulevard
Effective August 23, 2018
hydrostatic forces from a water surface elevation of 8.1 feet (mean higher high water plus 55-inch sea
level rise). The City shall review designs and associated studies for conformance with City
requirements and adequacy of design measures to withstand hydrodynamic and hydrostatic forces
associated with the design criteria.
The Project Sponsor shall also design erosion protection along the shoreline set -back area for
protection under storm surge conditions (at least 2 percent wave run-up) and a base flood elevation of
at least 11.6 feet. The City shall review designs and associated studies for adequacy in protecting the
shoreline set -back area under these conditions.
The City Public Works Department shall prepare Conditions of Approval, where necessary, to ensure
that the design criteria are met. Prior to receiving a grading permit, the Project Sponsor shall
incorporate applicable City and BCDC Conditions of Approval into project designs. (Hydrology, Public
Works Department);
72. Provide Flood Protection up to the 100-Year Flood Event plus Sea Level Rise for Above -Ground
Structures. To protect structures and people from sea level rise risks at the 350 Airport Boulevard Site,
prior to approving grading permits, the City shall ensure project design incorporates its floodplain
development requirements for a flood depth of the identified 100-year flood hazard water surface
elevation plus a 4.6-foot (55-inch) rise in sea level. At a minimum, the Project Site shall be graded to
over 10 feet above msl and the finished floor elevation of all building finished floors shall be
constructed to 14.5 feet (i.e., 2.9 feet above the 11.6-foot potential flood elevation), or as otherwise
determined as grading plans are developed. (Hydrology, Public Works Department); and
73. Future Wind Tunnel Analysis. To reduce potential impacts associated with future development of the
350 Airport Boulevard Site, a wind tunnel analysis shall be conducted in order to ensure that future
development of the Site is designed in a way to minimize wind shadow effects at surrounding
windsurfing areas. (Wind and Recreation, Planning Division).
CITY OF BURLINGAME
"
COMMUNITY DEVELOPMENT DEPARTMENT
BURLINGAME
501 PRIMROSE ROAD
BURLINGAME, CA 94010
PH: (650) 558-7250 • FAX: (650) 696-3790
vvwvv.burlingame.org
Site: 300 AIRPORT BOULEVARD
The City of Burlingame Planning Commission announces the
following public hearing on MONDAY, AUGUST 13, 2018 at
7:00 P.M. in the City Hall Council Chambers, 501 Primrose Road,
Burlingame, CA:
Application for Amendment to Conditions of Approval #6 (retail
and food service provisions) and #21 (Transportation Demand
Management provisions) of a previously approved office/life
science development ("Burlingame Point") at
300 AIRPORT BOULEVARD zoned APN 026-350-130.
Mailed: August 3, 2018
(Please refer to other side)
PUBLIC HEARING
NOTICE
City of Burlingame
A copy of the application and plans for this project may be reviewed prior to
the meeting at the Community Development Department at 501 Primrose
Road, Burlingame, California.
If you challenge the subject application(s) in court, you may be limited to
raising only those issues you or someone else raised at the public hearing,
described in the notice or in written correspondence delivered to the city at or
prior to the public hearing.
Property owners who receive this notice are responsible for informing their
tenants about this notice.
For additional information, please call (650) 558-7250. Thank you.
William Meeker
Community Development Director
PUBLIC HEARING NOTICE
(Please refer to other side)