HomeMy WebLinkAboutReso - CC - 093-2025RESOLUTION NO. 093-2025
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BURLINGAME
ACCEPTING IMPROVEMENTS – FIRE STATION 34 MISCELLANEOUS
IMPROVEMENTS PROJECT BY T&S INTERMODAL MAINTENANCE, INC., DBA
T&S WEST CONSTRUCTION
CITY PROJECT NO. 86910
WHEREAS, as part of the Facilities Capital Improvement Program (CIP), Fire Station
34 was identified as one of several City facilities in need of miscellaneous improvements to
ensure the building remains in good working condition for the fire fighters; and
WHEREAS, on August 19, 2024, the City Council awarded the Fire Station 34
Miscellaneous Improvements Project to T&S West Construction, in the amount not-to-exceed
$250,449.77 (Resolution No. 096-2024); and
WHEREAS, construction was successfully completed to the City’s satisfaction and met
all contract requirements; and
WHEREAS, the final project construction cost was $269,946.77, an increase of $19,497
(approximately 7.8%) over the original contract price, primarily due to additional work requested
by City staff, including power washing and painting the exterior of the training tower; and
WHEREAS, sufficient funds are available in the City’s Capital Improvement Program
budget to cover the project costs.
NOW, THEREFORE, BE IT RESOLVED by the CITY COUNCIL of the City of
Burlingame, California, and this Council does hereby find, order and determine as follows:
1. The Director of Public Works of said City has certified the work done by T&S
Intermodal Maintenance, Inc., DBA T&S West Construction, Inc., under the terms of its contract
with the City dated October 21, 2024, has been completed in accordance with the plans and
specifications approved by the City Council and to the satisfaction of the Director of Public
Works.
2. Said work is particularly described as City Project No. 86910.
3. Said work be and the same hereby is accepted.
__________________________
Peter Stevenson, Mayor
Docusign Envelope ID: BE72AC62-25A9-47AB-B52A-90E7C28E535C
I, Meaghan Hassel Shearer, City Clerk of the City of Burlingame, do hereby certify that
the foregoing Resolution was introduced at a regular meeting of the City Council held on the 2nd
day of September, 2025, and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: Brownrigg, Colson, Pappajohn, Stevenson, Thayer
NOES: COUNCILMEMBERS: NONE
ABSENT: COUNCILMEMBERS: NONE
____________________________
Meaghan Hassel Shearer, City Clerk
Docusign Envelope ID: BE72AC62-25A9-47AB-B52A-90E7C28E535C
DATE :
3 - FINAL PAYMENT FOR THE MONTH OF :
CONTRACT ORDER #323779
*************************************************************************************************************************************************************************************************************************************************************************************************ITEM ::UNIT :BID :UNIT :BID :QUANTITY ::AMOUNT :PREVIOUS :AMOUNT
#:ITEM DESCRIPTION :PRICE :QUANTITY :SIZE :AMOUNT :TO DATE ::TO DATE :PAID :THIS PMT.
*************************************************************************************************************************************************************************************************************************************************************************************************1 :Fence :37,933.96$ :1 :LS :37,933.96$ :1.00 ::37,933.96$ :36,037.26$ :1,896.70$
2 :Section 01 :65,161.49$ :1 :LS :65,161.49$ :1.00 ::65,161.49$ :32,580.75$ :32,580.74$
3 :Section 02 :1,290.82$ :1 :LS :1,290.82$ :1.00 ::1,290.82$ :1,290.82$ :-$
4 :Section 06 :16,316.58$ :1 :LS :16,316.58$ :1.00 ::16,316.58$ :16,316.58$ :-$
5 Section 07 729.78$ 1 LS 729.78$ 1.00 729.78$ 729.78$ -$
6 Section 09 28,394.74$ 1 LS 28,394.74$ 1.00 28,394.74$ 26,975.00$ 1,419.74$
7 Section 26 30,357.25$ 1 LS 30,357.25$ 1.00 30,357.25$ 6,071.45$ 24,285.80$
8 :Tower :70,265.15$ :1 :LS :70,265.15$ :1.00 ::70,265.15$ :14,053.03$ :56,212.12$
SUBTOTAL 250,449.77$ 250,449.77$ :134,054.67$ :116,395.10$
PROJECT TOTAL 250,449.77$ 250,449.77$ 134,054.67$ 116,395.10$
CHANGE ORDERS :CCO UNIT :CCO :UNIT :BID :QUANTITY ::AMOUNT :PREVIOUS :AMOUNT
#:DESCRIPTION :PRICE :QUANTITY :SIZE :AMOUNT :TO DATE ::TO DATE :PAID :THIS PMT.
*************************************************************************************************************************************************************************************************************************************************************************************************
1 Paint Tower $19,497.00 1 LS 19,497.00$ 1.00 19,497.00$ 19,497.00$
CHANGE ORDERS TOTAL $19,497.00 19,497.00$ 19,497.00$ :-$ :19,497.00$
DEDUCTIONS:
DATE
PREPARED BY: MARIE GALVIN 7/21/2025 SUBTOTAL ***********************************************269,946.77$ :134,054.67$ :135,892.10$
LESS FIVE (5%) PERCENT RETENTION (13,497.34)$ :(6,702.73)$ :6,794.60$
CHECKED BY: ****************************************************************-------------------------------:------------------------------:-----------------------------------
APPROVED BY SUBTOTAL WITHOUT DEDUCTIONS 256,449.43$ :127,351.94$ :129,097.50$
AMOUNT DUE FROM CONTRACTOR -$ :-$ :-$
***************************************************************-------------------------------:------------------------------:-----------------------------------
TOTAL THIS PERIOD *******************************256,449.43$ :127,351.94$ :129,097.50$
****************************************************************==================:=================:====================
CITY OF BURLINGAMECONTRACTOR: T&S Intermodal Maintenance, Inc. (T&S West)
ADDRESS: P.O. Box 1592
Linden, CA 95236
March 14, 2025
PAYMENT NO.February
FIRE STATION 34 MISCELLANEOUS IMPROVEMENTS PROJECT
CITY PROJECT NO. 86910
7/21/25
Docusign Envelope ID: BE72AC62-25A9-47AB-B52A-90E7C28E535C
Project
T&S Job No.
Owner
Progress Pay Estimate #
Work Completed Thru
Contract Contract To Date To Date Previous Previous Current Current
#Description Qty UM Unit Price Amount Qty Amount Qty Amount Qty Amount
1.FENCE 1 LS $37,933.96 $37,933.96 1.00 37,933.96 0.95 36,037.26 0.05 1,896.70
2.SECTION - 01 1 LS $65,161.49 $65,161.49 1.00 65,161.49 0.50 32,580.75 0.50 32,580.74
3.SECTION - 02 1 LS $1,290.82 $1,290.82 1.00 1,290.82 1.00 1,290.82 0.00 0.00
4.SECTION - 06 1 LS $16,316.58 $16,316.58 1.00 16,316.58 1.00 16,316.58 0.00 0.00
5.SECTION - 07 1 LS $729.78 $729.78 1.00 729.78 1.00 729.78 0.00 0.00
6.SECTION - 09 1 LS $28,394.74 $28,394.74 1.00 28,394.74 0.95 26,975.00 0.05 1,419.74
7.SECTION - 26 1 LS $30,357.25 $30,357.25 1.00 30,357.25 0.20 6,071.45 0.80 24,285.80
8.TOWER 1 LS $70,265.15 $70,265.15 1.00 70,265.15 0.20 14,053.03 0.80 56,212.12
$250,449.77 $250,449.77 $134,054.67 $116,395.10
CHANGE ORDERS
1.PAINT TOWER 1 LS $19,497.00 $19,497.00 1.00 19,497.00 0.00 0.00 1.00 19,497.00
2.$0.00 0.00 0.00 0.00 0.00 0.00 0.00
3.$0.00 0.00 0.00 0.00 0.00 0.00 0.00
4.$0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.$0.00 0.00 0.00 0.00 0.00 0.00 0.00
$19,497.00 $19,497.00 $0.00 $19,497.00
$269,946.77 $269,946.77 $134,054.67 $135,892.10
Amount Complete to Date 269,946.77
Previous Amount Complete 134,054.67
Project Manager Approval Current Amount Complete 135,892.10
Less Retention (5%)6,794.60
Date Current Amount Due 129,097.50
Totals
3/31/2025
BURLINGAME FIRE DEPARTMENT TI
405041.903
CITY OF BURLINGAME
3
Page 1 of 1
Docusign Envelope ID: BE72AC62-25A9-47AB-B52A-90E7C28E535C
Project Location Map, City Project No. 86910
Project Location
Fire Station 34