�� PLANNING APPLICATION
BURLINGAME COMMUNITY DEVELOPMENT DEPARTMENT—PLANNING DIVISION
501 PRIMROSE ROAD, 2ND FLOOR, BURLINGAME, CA 94010-3997
t TEL: 650.558.7250 � FAX: 650.696.3790 � E-MAIL: PLANNINGDEPTna,BURLINGAME.ORG
_
859 �..�N . .,s�_..����...�,H � .,..�.s w ,_ �.�_��_ _.,. ,.m .. . ._ � ., . ,. _aa_a.�..,�..�.._ �._.:�._....�.;.�-�
Z� Cowan Road DUP1 024-401-510
�_. PROJECT ADDRESS ASSESSOR'S PARCEL #(APN) ZONING
H
� '� PROJECT DESCRIPTION
p';,`, Modification to existing cell site (see attached project description)
z
w,
�`
O
�"
a •
'i:
" PROPERTY OWNER NAME APPLICANT? ADDRESS
z�
The Church in Buflinqame 859 Cowan Rd, Burlingame, CA 94010
O � PHONE E-MAIL
�i!!�`
� ?� ARCHITECTIDESIGNER APPLICANT? ADDRESS
�'�'� J5 Infrastructure Partners 2030 Main St, Ste 200, Irvine, CA 92614
z
� � PHONE E-MAIL
Z ;'.
Q i'
V ! BURLINGAME BUSINESS LICENSE #
J :
d' ..._ ._. ,,__. . . .,._ _. . ....... ..... ... ,. ....__ . .,__,,, .,.. _ _ __ _ __ _ . _ . _,_ .. ... ._. __..._..,... . . . , ........
a` *FOR PROJECT REFUNDS* - Please provide an address to which to all refund checks will be mailed to:
NAME ADDRESS
a' I HEREBY CERTIFY UNDER PENALTY OF PERJURY THAT THE INFORMATION GIVEN HEREIN IS TRUE AND CORRECT TO THE BEST OF MY
� KNOWLEDGE AND BELIEF.
�;
z L�;anPe�re Su� 9/ 11 / 2 0
O APPLICANT'S SIGNATURE (IF DIFFERENT FROM PROPERTY OWNERI DATE
�:
�<' I AM AWARE OF THE PROPOSED APPLICATION AND HEREBY AUTHORIZE THE ABOVE APPLICANT TO SUBMIT THIS APPLICATION TO THE
H
>' PLANNING COMMISSIONIDIVISION.
a
0
�,
Q'' PROPERTY OWNER'S SIGNATURE
v,a.�� m„�,�.�-�,�.,�.��.a.� -� �.��,n� _ . _ --
�� � . .n��.� a.m, � �._ �. .a_�. W...._.� �._� __,..� �,�, .m r _�. ._ .m�,.� �..._.._..�_. �..� �....�.�.w�,_.._.e —�.�...m..��
� AUTHORIZATION TO REPRODUCE PLANS !
` I HEREBY GRANT THE CITY OF BURLINGAME THE AUTHORITY TO REPRODUCE UPON REQUEST AND/OR POST PLANS SUBMITTED WITH THIS ;
APPLICATION ON THE CITY'S WEBSITE AS PART OF THE PLANNING APPROVAL PROCESS AND WAIVE ANY CLAIMS AGAINST THE CITY ARISING
� OUT OF OR RELATED TO SUCH ACTION C S jINITIALS OF ARCHITECT/DESIGNER)
;
s �
DATE
� ' APPLICATION TYPE �, � � �,"" � � � {
Z❑ ACCESSORY DWELLING UNIT (ADU) ❑ VARIANCE (VAR)
� a ❑ CONDITIONAL USE PERMIT (CUP) �WIRELESS � �► UP� j � � �(�?��
w,�,
_ � � DESIGN REVIEW (DSR) ❑ FENCE EXCEPTION
LL� HILLSIDE AREA CONSTRUCTION PERMIT OTHER: ?�-'�{�-'�� "� ',
� �, ❑ ❑
N❑ MINOR MODIFICATION
; ❑ SPECIAL PERMIT (SP) DATE RECEIVED:
N
D
�
�
C
tn
m
O
z
r
�
�j� INFRASTRUCTURE
O�tobet 22°d, 2020
Planning Division
City of Burlingame
501 Primrose Rd
Burlingame, CA 94010
RE: Zoning Permit Application and Fees
Applicant: New Cingular Wireless PCS, LLC ("AT&T")
Property Owner: The Church in Burlingame
Properly Address: 859 Cowan Rd DUP1, Burlingame, CA 94010
Dear Planner:
Enclosed you will find payment for the fees for a zoning permit to modify an existing wireless
facility at the above-referenced property.
Also included is a copy of the application.
All required documents....Submittal plans, photosims, application, EFR form, Legal letter in lieu
of Waiver .....are being shipped to the City planning department in a separate package and
should arrive no later than Monday, 10/26/20
AT&T applies for the zoning permit under Section 6409 of the federal Middle Class Tax Relief
and Job Creation Act of 2012 (47 U.S.C.A. § 1455). That law provides:
"a 5tate or local government may not deny, and shall approve, any eligible
facilities request for a modification of an existing wireless tower or base station that
does not substantially change the physical dimensions of such tower or base station."
AT&T respectfully requests that the zoning permit be issued as soon as possible but no later than
60 days from the receipt of the fees and all required documents, so that AT&T can proceed with
this modification immediately. If you have any questions regarding this application, please
contact me.
Sincerely,
C�e�e �'c�i�a�e�
Charlene Schlager, JS Infrastructure Partners
Authorized Representative of AT&T Mobility
Mobile: (773) 732-5497
Email: cschlager@JSIP.com
CCL02062 - PROJECT DESCRIPTION
MODIFICATION TO AN UNMANNED TELECOMMUNICATIONS FACILITY,
CONSISTING OF THE FOLLOWING:
AT&T WIRELESS PROJECT SCOPE WILL CONSIST OF THE FOLLOWING:
• REMOVE (2) PANEL ANTENNAS FROM EXISTING TRIPOD, (1) PER
SECTOR
• INSTALL (2) PANEL ANTENNAS ON EXISTING TRIPOD, (1) PER SECTOR
• INSTALL (2) RRUS 4478 B14 NEAR ANTENNAS, (1) PER SECTOR
• INSTALL (2) 6630 WITHIN EXISTING PURCELL CABINET
• REMOVE (4) RRUW FROM EQUIPMENT AREA, (2) PER SECTOR
• REMOVE (1) RBS 3518 FROM EQUIPMENT AREA
• REMOVE (4) 7/8" AND (4) 1-1/4" COAX
• REMOVE (1) 6601 V2 CHASSIS W/(1) XMU WITHIN EXISTING PURCELL
CABINET
• REMOVE (1) 6601 V2 CHASSIS W/(1) 5216 +(1) XMU WITHIN EXISTING
PURCELL CABINET
�>
� at&t
�•.__��
AT&T Services, Inc.
5001 Executive Parkway
Room 2W901
San Ramon, CA 94583
925.543.1548 Phone
925.867.3869 Fax
jdb@att.com
October 20, 2020
VIA E-MAIL
kkane (�a,burlin�ame. org
plannin�dept(�a,bu_ rlin�ame.o�
Kathleen Kane
City Attorney
501 Primrose Road
Burlingame, CA 94010
JOHN DI BENE
Assistant Vice President -
Senior Legal Counsel
�v,� � ., .._.-� �._..
`i 2 � 20Z0
�Jt= BU�! iC�.:�AME
-.,, ,
Re: Wireless Facility Siting Application
AT&T Site ID CCL02062
Property Address: 859 Cowan Road, Burlingame, California 94010
Dear Ms. Kane:
I write on behalf of New Cingular Wireless PCS, LLC d/b/a AT&T Mobility ("AT&T")
regarding an unlawful submittal requirement that is preventing AT&T from submitting its
application to modify an existing wireless telecommunications facility in the City of Burlingame.
Specifically, the Planning Department is requiring AT&T to sign an Applicant Waiver of Review
Timelines before the City will accept AT&T's application. AT&T requests that the city
immediately accept its application, and promptly process it to approval.
Federal law prohibits the city from refusing to accept applications. Moreover, federal law
requires approval of AT&T's application, which qualifes as an eligible facilities request that the
city cannot deny under 47 U.S.C. § 1455(a). AT&T requests that the city immediately accept its
application, and promptly process it to approval.
The Telecommunications Act of 1996 requires a local government to act on wireless
facility permit applications within a"reasonable period of time." � In 2009, the Federal
Communications Commission ("FCC") issued a declaratory ruling, commonly known as the
"Shot Clock Order," which established a legal presumption that "reasonable period of time" by
establishing presumptive maximum periods of time for review of wireless siting applications.2 In
2014, the FCC established a maximum 60-day "shot clock" for eligible facilities requests under
47 U.S.C. § 1455(a).3 The FCC's rule also provides that such an application is deemed approved
if the city does not act within the 60-day shot clock.4
�
Ms. Kane
Burlingame
October 20, 2020
Pa�e 2 of 2
The FCC further clarified that local actions to halt or suspend acceptance, processing, or
approval of wireless siting applications are unlawful under the Telecommunications Act.S Thus,
the city must accept AT&T's application and promptly process it.
In addition, federal law requires the city to promptly approve AT&T's application. Under
Section 6409(a) of the Middle Class Tax Relief and Job Creation Act of 2012 (commonly known
as "Section 6409(a)" and codified at 47 U.S.C. § 1455(a)), the city "may not deny, and shall
approve" AT&T's application because it is an eligible facilities request that "does not
substantially change the physical dimensions" of the existing base station.6 Applicable FCC
regulations provide objective parameters for when modifications "substantially change the
physical dimensions" of the existing facility. � AT&T's application materials demonstrate that its
proposed modification qualifies as an eligible facilities request that will not substantially change
the physical dimensions of the existing facility. Thus, the city must approve it within the
applicable 60-day shot clock.
AT&T is willing the work with the City to review the application within a reasonable
period of time. If the City cannot review the application in a timely manner due to the COVID-
19 pandemic, AT&T would be willing to enter into a tolling agreement. However, AT&T will
not waive all of its rights to a timely review.
Please do not hesitate to contact me if you would like to discuss these issues.
Sincerely,
!��- ,
�;. f ��
, �---
John di Bene
JDB/j vs
Cc: Michelle Markiewicz, Associate Planner (plannin�dept(a�burlin a� me.org)
` See 47 USC § 332(c)(7)(B)(ii).
2 See Petition for Declaratory Ruling to Clar� Provisions of Section 332(c)(7)(B), WT Docket No. 08-165, Petition
for Declaratory Ruling to Clarify Provisions of Section 332(c)(7)(B), WT Docket No. 08-165, Declaratory Ruling,
24 FCC Rcd. 13994 (2009).
3 See 47 C.F.R. § 1.6100(c) (former 47 C.F.R. § 1.40001 has been redesignated 47 C.F.R. § 1.6100).
4 See 47 C.F.R. § 1.6100(c)(4).
5 See Accelerating Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment, Third
Report and Order and Declaratory Ruling, WC Docket No. 17-84 and WT Docket No. 17-79, FCC 18-111, ¶¶ 140-
68 (rel. Aug. 3, 2018).
6 See 47 U.S.C. § 1455(a)(1).
' See 47 C.F.R. § 1.6100(b)(7).
Eligible Facilities Request Application -� � w' � � �'' � �.�
(47 U.S.C. § 1455(a))
' _' ; `� �i 202�
Applicant: AT&T
� �.JI` ���n� !I T..nr�'viC
- . , �t � `. I i '
Applicant/Agent Contact Information: CHARLENE SCHLAGER - AGENT FOR AT&T
442 SYLVIA WAY, SAN RAFAEL, CA 94903 PH: (773) 732-5497 EMAIL: CSCHLAGER@J51P.COM
Property Owner: The Church in Burlingame
Property Location (e.g., address, parcel no., GPS coordinates): 859 Cowan Rd DUP1, Burlingame,
CA 94010
Project Description: SEE ATTACHED PROJECT DESCRIPTION
Date of filing:
30 days after filing:
"To toll the timeframe for incompleteness, the reviewing State or local government must provide written
notice to the applicant within 30 days of receipt of the application, clearly and specifically delineating all
missing documents or information. Such delineated information is limited to documents or information
meeting the standard under paragraph (c)(1) of this section. " 47 C.F.R. 1.40001(c)(3)(i).
60 days after filing:
"Timeframe for Review. Within 60 days of the date on which an applicant submits a request seeking
approva! under this section, the State or local government shall approve the application unless it
determines that the application is not covered by this section. " 47 C.F.R. 1.40001(c)(2).
Page 1 of 4
Applicant Initials
Is the proposed modification an Eligible Support Structure? Please check the
applicable boxes:
An "Eligible Support Structure " means "Any tower or base station as defined in this section, provided that
it is existing at the time the relevant application is filed with the State or local government under this
section. " 47 C.F.R. 1.40001(b)(4).
�"Tower" means "Any structure built for the sole or primary purpose of supporting any Commission-
licensed or authorized antennas and their associated facilities, including structures that are constructed for
wireless communications services including, but not limited to, private, broadcast, and public safety
services, as well as unlicensed wireless services and fixed wireless services such as microwave backhaul,
and the associated site. " 47 C.F.R. 1.40001(b)(9).
��'
a"Base Station " means "A structure or equipment at a fixed location that enables Commission-licensed
or authorized wireless communications between user equipment and a communications network. The term
does not encompass a tower as defined in this subpart or any equipment associated with a tower.
(i) The term includes, but is not limited to, equipment associated with wireless communications
services such as private, broadcast, and public safety services, as well as unlicensed wireless services
and fixed wireless services such as microwave backhaul.
(ii) The term includes, but is not limited to, radio transceivers, antennas, coaxial or fiber-optic cable,
regular and backup power supplies, and comparable equipment, regardless of technological
configuration (including Distributed Antenna Systems and small-cell networks).
(iii) The term includes any structure other than a tower that, at the time the relevant application is
filed with the State or local government under this section, supports or houses equipment described in
paragraphs (b)(1)(i)-(ii) of thi.s section that has been reviewed and approved under the applicable
zoning or siting process, or under another State or local regulatory review process, even if the
structure was not built for the sole or primary purpose of providing such support.
(iv) The term does not include any structure that, at the time the relevant application is filed with the
State or local government under this section, does not support or house equipment described in
paragraphs (b)(1)(i)-(ii) of this section. "
47 C.F.R. 1.40001(b)(1).
<� �ati
❑✓ "Existing"— "A constructed tower or base station is existing for purposes of this section if it has been
reviewed and approved under the applicable zoning or siting process, or under another State or local
regulatory review process, provided that a tower that has not been reviewed and approved because it was
not in a zoned area when it was built, but was lawfully constructed, is existing for purposes of this
definition. " 47 C.F.R. 1.40001(b)(S).
2. What is the baseline height of the Eligible Support Structure? Please complete the
Baseline Height Worksheet and insert baseline height here 31'-9" . For modifications
that will not change the height of the Eligible Support Structure, insert "N/A."
Page 2 of 4
Applicant Initials
3. Is the proposed modification an Eligible Facilities Request?
An "Eligible Facilities Request " means "Any request for modification of an existing tower or base
station that does not substantially change the physical dimensions of such tower or base station,
involving:
(i) collocation of new transmission equipment;
(ii) removal of transmission equipment; or
(iii) replacement of transmission equipment. "
47 C.F.R. 1.40001(b)(3); 47 U.S.C.1445(a).
"Collocation " means "The mounting or installation of transmission equipment on an eligible
support structure for the purpose of transmitting and/or receiving radio frequency signals for
communications purposes. " 47 C.F.R. 1.40001(b)(2).
"Transmission equipment" means "Equipment that facilitates transmission for any Commission-licensed
or authorized wireless communication service, including, but not limited to, radio transceivers, antennas,
coazial or fiber-optic cable, and regular and backup power supply. The term includes equipment
associated with wireless communications services including, but not limited to, private, broadcast, and
public safery services, as well as unlicensed wireless services and fixed wireless services such as
microwave backhaul. " 47 C.F.R. 1.40001(b)(8).
3.1 Please check all applicable boxes that describe the proposed modification:
✓�Collocation of new transmission equipment
�Removal of transmission equipment
�Replacement of transmission equipment
3.2 Please complete the Substantial Change Worksheet to determine if the proposed
modification substantially changes the physical dimensions of the Eligible Support
Structure. Based on the Substantial Change Worksheet, will the proposed modification
substantially changes the physical dimensions of the Eligible Support Structure? No
If you answered "Yes," stop because the application is not an eligible facilities request.
4. Compliance with State and Federal regulations and codes. The proposed modification—
Cl�etk �r�1 ca�plicr��de bt�xn�
�Will comply with FCC regulations regarding human exposure to radio frequency
electromagnetic fields
aWill comply with Federal Aviation Administration (FAA) and FCC tower lighting
requirements
✓�Will comply with applicable state environmental regulations
�✓ Will comply with applicable building codes
Page 3 of 4
Applicant Initials
�Will comply with applicable fire codes
✓❑ Will comply with other non-discretionary and generally applicable structural and
safety codes
❑✓ Will comply with Section 106 historic preservation review, if applicable
�Will comply with the National Environmental Policy Act (NEPA), if applicable
5. Attachments:
�Completed Baseline Height Worksheet
�Completed Substantial Change Worksheet
�Letter of authorization
�Applicable non-discretionary permit fees
✓❑Building drawings, including site details and plans
�✓ Documentation of property rights to site
�✓ Prior approval for Eligible Support Structure
❑ Other:
Page 4 of 4
Applicant Initials
Baseline Height Worksheet
�
2.
Does the application seek approval for collocation or replacement of transmission
equipment?
�No. Stop, the height will not increase for removal of transmission equipment.
Continue to #7 and respond "N/A."
❑✓ Yes. Continue to #2.
Was the tower or base station subject to previous review and approval by the local
jurisdiction (as originally built or as nzodified to its current state)?
❑✓ Yes. Continue to #3.
�No. Does the application seek to modify a tower or base station that was in a
zoned area when built?
A. �No. Was the tower or base station lawfully constructed?
i. �Yes.
ii. �No.
Request.
Continue to #3.
Stop, the application is not an Eligible Facilities
B. �Yes. Stop, the application is not an Eligible Facilities Request
(because the tower or base station is not considered "existing").
3. Does the application seek to collocate transmission equipment that will be separated
horizontally on a base station (such as on a rooftop)?
�
�✓ Yes. Continue to #7. The baseline height is that of the original support
structure (e.g., the height of the rooftop, penthouse).
�No. Continue to #4.
:
4. Has the tower or base station been modified per a previous approval by the local
jurisdiction?
A. �✓ No. Continue to #7. The baseline height is the originally-approved height of
the tower or base station.
B. �Yes. Continue to #5.
Baseline Height Worksheet Page 1 of 2
Applicant Initials
5. Was the tower or base station modified based on approval by the local jurisdiction issued
before February 17, 2012?1
A. �Yes. Continue to #6.
B. �No. Continue to #7. The baseline height is the height of the tower or base
station as of February 17, 2012.
6. Was the tower or base station modified to the maximum height approved by the local
jurisdiction per any approval(s) before February 17, 2012?
A. �Yes. Continue to #7. The baseline height is the existing height of the tower or
base station.
B. �No. Continue to #7. The baseline height is the height as approved by the local
jurisdiction before February 17, 2012.
7. Insert baseline height here 31 �-9�� and at item 2 to the Eligible Facilities Request
Application.
' The Spectrum Act was passed by Congress on February 17, 2012 and signcd into law by the President on February
22, 2012. The FCC's Report and Order and regulations refer to the date of passage rather than date of enactment as
the trigger for the analysis. Approvals issued after February 17, 2012 do not affect the baseline dimensions for
determining whether an application proposes a substantial change.
Baseline Height Worksheet Page 2 of 2
Applicant Initials
Substantial Change Worksheet
Definition of "Substantial Change":
"Substantial Change " means "A modification substantially changes the physical dimensions of an eligible
support structure if it meets any of the following criteria:
(i) for towers other than towers in the public rights-of-way, it increases the height of the tower by more
than 10% or by the height of one additional antenna array with separation from the nearest existing
antenna not to exceed twenty feet, whichever is greater; for other eligible support structures, it increases
the height of the structure by more than 10% or more than ten feet, whichever is greater;
(A) Changes in height should be measured from the original support structure in cases where
deployments are or will be separated horizontally, such as on buildings' rooftops; in other
circumstances, changes in height should be measured from the dimensions of the tower or base station,
inclusive of originally approved appurtenances and any modifications that were approved prior to the
passage of the Spectrum Act.
(ii) for towers other than towers in the public rights-of-way, it involves adding an appurtenance to the body
of the tower that would protrude from the edge of the tower more than twenty feet, or more than the width
of the tower structure at the level of the appurtenance, whichever is greater; for other eligible support
structures, it involves adding an appurtenance to the body of the structure that would protrude from the
edge of the structure by more than six feet;
(iii) for any eligible support stnscture, it involves installation of more than the standard number of new
equipment cabinets for the technology involved, but not to exceed four cabinets; or, for towers in the public
righls-of-way and base statio�zs, it involves installation of�any new equipment cabinets on the ground if
there are no pre-existing ground cabinets associated with the structure, or else involves installation of
ground cabinets that are more than 10% larger in height or overall volume than any other ground cabinets
associated with the structure;
(iv) it entails any excavation or deployment outside the current sitez;
(v) it would defeat the concealment elements of the eligible support structure; or
(vi) it does not comply with conditions associated with the siting approval of the construction or
modification of the eligible support structure or base station equipment, provided however that this
limitation does not apply to any rnodification that is noncomplia�st only in a manner that woz�ld not exceed
the thresholds identified in � 1.40001(b)(7)(i)-(iv). "
47 C.F.R. 1.40001(b)(7).
Check the box that describes the Eligible Support Structure:
❑✓ Base station. Continue to #2.
�Tower located in the public right-of-way. Continue to #2.
�Tower located outside of the public right-of-way. Continue to #3.
z"Site "—"For towers other than towers in the public rights-of-way, the current boundaries of the leased or owned
property surrounding the tower and any access or utility easements currently related to the site, and, for other
eligible support structures, further restricted to that area in proximity to the structure and to other transmission
equipment already deployed on the ground. " 47 C.F.R. 1.40001(b)(6).
Substantial Change Worksheet Page 1 of 4
Applicant Initials
2. Answer the following questions about the proposed modification and proceed as
instructed:
A. Is the baseline height for the Eligible Support Structure greater than 100 feet?
�Yes. Continue to item 2B.
�No. Continue to item 2C.
B. Does the proposed modification increase height by more than 10°/a of the baseline
height?
�Yes. Continue to item 11.
�No. Continue to item 2D.
C. Does the proposed modification increase height by mare than 10 feet?
�Yes. Continue to item 11.
�✓ No. Continue to item 2D.
D. Does the proposed modification add any appurtenance that would protrude more
than 6 feet from edge of the Eligible Support Structure?
�Yes. Continue to item 11.
�No. Continue to item 4.
3. Answer the following questions about the proposed modification and proceed as
instructed:
A. Will the proposed modification increase height by more than 10% of the baseline
height of the Eligible Support Structure?
�Yes. Continue to item 3B.
�No. Continue to item 3C.
B. Will the proposed modification increase height by more than the height of one
additional antenna array with separation from the nearest existing antenna not to exceed
20 feet?
�Yes. Continue to item 11.
❑No. Continue to item 3C.
Substantial Change Worksheet Page 2 of 4
Applicant Initials
C. Does the proposed modification add any appurtenance that would protrude more
than 20 feet from the edge of the Eligible Support Structure?
�Yes. Continue to item 3D.
�No. Continue to item 4.
D. Does the proposed modification add any appurtenance that would protrude more
than the width of the tower structure at the level of the appurtenance?
�Yes. Continue to item 11.
�No. Continue to item 4.
4. Does the proposed modification involve installation of more than standard number of
equipment cabinets for the technology involved, not to exceed four?
�Yes. Continue to item 11.
�No. If the Eligible Support Structure is a base station, continue to item 5.
If the Eligible Support Structure is a tower in the public right-of-way,
continue to item 5.
If the Eligible Support Structure is a tower outside of the public right-of-
way, continue to item 8.
5. Does the proposed modification involve installation of any new equipment cabinets on
the ground?
�Yes. Continue to item 6.
�No. Continue to item 8.
6. Are there any pre-existing ground cabinets associated with the Eligible Support
Structure?
�Yes. Continue to item 7.
❑No. Continue to item 11.
7. Are the proposed new ground cabinets more than 10% larger in height or overall volume
than any other ground cabinets associated with the Eligible Support Structure?
�Yes. Continue to item 11.
❑No. Continue to item 8.
Substantial Change Worksheet Page 3 of 4
Applicant Initials
0
.
8. Does the proposed modification involve excavation or deployment outside of the current
site3?
�Yes. Continue to item 11.
�No. Continue to item 9.
9. Will the proposed modification defeat the existing concealment elements of the Eligible
Support Structure?
�Yes. Continue to item 11.
�No. Continue to item 10.
10. Will the proposed modification comply with conditions associated with the siting
approval(s)?
A. �✓ Yes. Continue to item 12.
�No. Describe the non-compliance:
Continue to item l OB.
�Not applicable. Continue to item 12.
B. Is the non-compliance with conditions associated with the siting approval(s) based
on any of the following: (a) height, (b) protrusion of any appurtenance from edge of the
Eligible Support Structure, (c) number of equipment cabinets to be installed, (d) location
of excavation, ar(e) impact to concealment elements that would not exceed the
thresholds outlined above?
❑Yes. Continue to item 12.
�No. Continue to item 11.
11. The proposed modification is a substantial change to the physical dimensions of the
existing tower or base station. Insert "Yes" in item 3.2 of the Eligible Facilities Request
Application.
12. The proposed modification is not a substantial change to the physical dimensions of the
existing tower or base station. Insert "No" in item 3.2 of the Eligible Facilities Request
Application.
3 See footnote 2.
Substantial Change Worksheet Page 4 of 4
Applicant Initials