MAY 11 1981 DATE May 7, 1981
To: Planning Commission CITY OFBURUWiM
PLAWNG WT.
Fnom: Kerry L. Burke, Planning Staff
SumiECT: Status of the Semmler Land Division Application (File Rio. SMN 80-26)
On February 25, 1981, the Commission heard an appeal of a conditional approval
of a tentative map to create two parcels in the Burlingame Hills area. The
main concerns of the appellant (Mr. Ryan) are the possible geotechnical
problems which may arise from the ultimate development of the property. The
appellant (Mr. Ryan) requested that a geotechnical report be prepared for
the project prior to granting conditional approval of the tentative map.
The applicant (Mr. Semmler) agreed to this request.
The Planning Commission continued this item to allow the applicant (Mr.
Semmler) time to retain a consultant to prepare a geotechnical report.
The applicant (Mr. Semmler) has supplied the County Geologist with a geotech-
nical report prepared by Don Hillebrandt Associates for the subject property
and the area affected by the project. The report evaluated whether any
potential geologic hazards exist at the site which would preclude the construction
of an additional residence on the property. The report also made detailed
earthwork, drainage and foundation engineering recommendations for construction
of the proposed residence. The report concluded that, with proper construction
techniques, development could safely proceed. The County Geologist has
reviewed this report and has accepted it.
The applicant (Mr. Semmler) has satisfied the requirements for a geotechnical
report which meets the County's "Minimum Standards for Geotechnical Reports."
This report made specific recommendations for site development. In light of
the new information, Staff recommendation for SMN 80-26 is that the Planning
Commission make the necessary findings, and conditionally approve the tentative
subdivision with a revision of the original condition 4 to read:
4. Meet all requirements and recommendations set forth in the geotechnical
report prepared for this project.
KLB:as
Encl.: Staff report of February 25, 1981
Don Hillebrandt letter of April 7, 1981