RESOLUTION NO. 070-2025
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BURLINGAME ACCEPTING THE
LAGUNA PLAYGROUND RENOVATION PROJECT BY G&G BUILDERS, INC., CITY PROJECT
NO. 86490, IN THE AMOUNT OF $534,659.46
WHEREAS, on September 16, 2024, the City Council approved the construction contract with
G&G Builders, Inc. in the amount of $283,917.00 (Resolution No. 115-2024); and
WHEREAS, the project construction has been satisfactorily completed in compliance with the
plans and specifications; and
WHEREAS, the final construction cost of $281,093.19 did not exceed the approved contract
amount.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF BURLINGAME RESOLVES AND
ORDERS AS FOLLOWS:
1. The Director of Parks and Recreation of the City of Burlingame has certified the work done by
G&G Builders, Inc. under the terms of their contract with the City dated September 16, 2024, has
been completed in accordance with the plans and specifications approved by the City Council and
to the satisfaction of the Director of Parks and Recreation.
2. Said work is particularly described as City Project No. 86490.
3. Said work is accepted.
____________________________
Peter Stevenson, Mayor
I, Meaghan Hassel-Shearer, City Clerk of the City of Burlingame, do hereby certify that the
foregoing Resolution was introduced at a regular meeting of the City Council held on the 7th day of July
2025 and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: Brownrigg, Colson, Pappajohn, Stevenson, Thayer
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: None
____________________________
Meaghan Hassel-Shearer, City Clerk