HomeMy WebLinkAboutReso - CC - 014-19832/17/83
RESOLUTION NO. 14-82
AWARDING CONTRACT
1982/83 SIDEWALK. CURB AND GUTTER REPLACEMENT
PROJECT NO. 105
WHEREAS, the City Council has authorized an invitation for bids
for the 1982/83 Sidewalk, Curb and Gutter Replacement, Project No. #105; and
WHEREAS, on January 27, 1983, all bids received were opened before
the City Clerk and the Director of Public Works; and
WHEREAS, ARTHUR H. SMITH ENGINEERING submitted the lowest bid for
the job in the amount of $86,656.09;
NOW, THEREFORE, be it RESOLVED, and it is hereby ORDERED, that the
bid of ARTHUR H. SMITH ENGINEERING for said Project No. #105 in the amount of
$86,656.09 be, and the same hereby is accepted.
BE IT FURTHER RESOLVED that a contract be entered into between
the successful bidder hereinabove referred to and the City of Burlingame for
the performance of said work, and that the City Manager be, and he hereby is,
authorized for and on behalf of the City of Burlingame to execute said contract
and to approve the faithful performance bond and the labor and materials bond
(required to be furnished by the contractor.
ff;
I, EVELYN H. HILL, City Clerk of the City of Burlingame, do hereby
certify that the foregoing Resolution was introduced at a regular meeting of
the Burlingame City Council held on the 22nd day of February 1983,
and was adopted thereafter by the following vote:
AYES: COUNCILMEN: AMSTRUP, BARTON, MANGINI, MARTIN
NOES: COUNCILMEN: NONE
ABSENT: COUNCILMEN: CROSBY
CiX y Clerk