HomeMy WebLinkAboutReso - CC - 099-2024 RESOLUTION NO. 099-2024
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BURLINGAME
AWARDING A CONSTRUCTION CONTRACT FOR THE ROLLINS ROAD SEWER
FORCEMAIN IMPROVEMENTS PROJECT TO CRATUS, INC. IN THE AMOUNT OF
$2,817,6000, AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE
CONTRACT
CITY PROJECT NO. 85870
WHEREAS, on June 6, 2024, the City issued notice inviting bid proposals for the Rollins
Road Sewer Force Main Improvements, City Project No. 85870; and
WHEREAS, on July 16, 2024, six proposals were received and opened via PlanetBids;
and
WHEREAS, Cratus, Inc. submitted the lowest responsible bid for the job (Base Bid) in the
amount of $2,817,600.
NOW, THEREFORE, BE IT RESOLVED, and it is ORDERED, that the Plans and
Specifications, including all addenda, are approved and adopted; and
BE IT FURTHER RESOLVED that the bid of Cratus, Inc. for said project in the amount of
$2,817,600, and the same hereby is accepted; and
BE IT FURTHER RESOLVED that a contract be entered into between the successful
bidder hereinabove referred to and the City of Burlingame for the performance of said work, and
that the City Manager be authorized for and on behalf of the City of Burlingame to execute said
contract and to approve the faithful performance bond and the labor materials bond required to
be furnished by the contractor.
____________________________
Donna Colson, Mayor
I, Meaghan Hassel Shearer, City Clerk of the City of Burlingame, do hereby certify that the
foregoing Resolution was introduced at a regular meeting of the City Council held on the 19th day
of August, 2024, and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: BROWNRIGG, COLSON, LEE, PAPPAJOHN, STEVENSON
NOES: COUNCILMEMBERS: NONE
ABSENT: COUNCILMEMBERS: NONE
_____________________________
Meaghan Hassel Shearer, City Clerk
Docusign Envelope ID: 95A3BE3B-588E-4488-9500-6100DBD081ED