HomeMy WebLinkAboutReso - PC - 2022.05.23 - 8CDocuSign Ervelope rlD: 588442D5-M7 A4220-BAC8-42AD3C777 28F
RECORDING REQUESTED BY:
Planning Department
City of Burlingame
WHEN RECORDED MAIL TO:
COMMUNITY DEVELOPMENT DEPARTMENT
CITY OF BURLINGAME
501 PRIMROSE ROAD
BURLINGAME, CA 94010
2022-A6ffi58
3:37 pm 0910912022 Rl Fee: NO FEE
Count of Pages 4
Recorded in Off icialRecords
CountY of San Mateo
Mark Church
Assesso r-Co u ntY Clerk'Recorder
4
l ll]il l illill lll illll lllil llll lllll illll llililllllllllllllliililil lll llli*-s -i- o o o 3 2 8 7 5 5 8 $ *
Resolution No. 2022-05.23-8C
1273 BALBOA AVENUE
APN 026-152-030
TITLE OF DOCUMENT
I hereby certify this to be a full, true and correct copy of the
document it purports to be, the original of which is on file in my
office.
June 3,2022
k iru hr/*,tr
Date:
Kevin Gardiner, AICP, Community Development Director
rrUAlE
RESOLUTION APPROVING CATEGORICAL EXEMPTION AND DESIGN REVIEW
RESOLVED, by the Planning Commission of the City of Burlingame that:
WHEREAS, a Categorical Exemption has been prepared and application has been made for Desiqn
Review for a new. two-storv sinole-unit dwellinq and detached qaraqe at 1273 Balboa Avenue, Zone
R-1 , Betty Chen and Kevin Lanqe, propertv owners, APN: 026-152-030;
WHEREAS, said matters were heard by the Planning Commission of the City of Burlingame on Mav 23.
2022, at which time it reviewed and considered the staff report and all other written materials jnd
testimony presented at said hearing;
NOW, THEREFORE, it is RESOLVED and DETERMINED by this Planning Commission that:
1. On the basis of the lnitial Study and the documents submitted and reviewed, and comments
received and addressed by this Commission, it is hereby found that there is no substantial
evidence that the project set forth above will have a significant effect on the environment, and
categorical exemption, per Section 15303 (a), which states that construction of a limited number
of new, small facilities or structures including one single family residence or a second dwelling
unit in a residential zone is exempt from environmental review. ln urbanized areas, up to three
single-family residences maybe constructed or converted under this exemption, is hereby
approved.
Said Design Review is approved subject to the conditions set forth in Exhibit "A" attached hereto.
Findings for such Design Review is set forth in the staff report, minutes, and recording of said
meeting.
3. lt is further directed that a certified copy of this resolution be recorded in the official records of the
County of San Mateo
rperson
Secretary of the g Commission of the City of Burlingame, do
certify that the foregoing resolution was introd uced and adopted at a regular meeting of the
Planning Commission held on the 23rd dav of Mav,2022 by the following vote
1273 BALBOAAVENUE - RESO 2022{t5.23{CAYES: HORAN,
LOWENTHAL, PFAFF, SCHUID, TSE
NOES: NONE
ABSET{T COIAROTO, GAUL
REGUSED: I{ONE
2
ry
t,
2
EXHIBIT "A"
Conditions of Approval for Categorical Exemption and Design Review
1273 Balboa Avenue
Effective June 2,2022
Page 1
that the project shall be built as shown on the plans submitted to the Planning Division date
stamped May 2,2022, sheets A0.0 through A5.1, and L1;
that the front yard shall contain one Coast Live Oak tree and the rear yard shall contain one
Coast Live Oak tree, one Western Redbud tree, and one relocated Orange tree;
that the window grids on all windows be simulated true divided lites;
that any changes to building materials, exterior finishes, windows, architectural features, roof
height or pitch, and amount or type of hardscape materials shall be subject to Planning Division
or Planning Commission review (FYl or amendment to be determined by Planning staff);
that any changes to the size or envelope of the basement, first or second floors, or garage,
which would include adding or enlarging a dormer(s), shall require an amendment to this
permit;
that any recycling containers, debris boxes or dumpsters for the construction project shall be
placed upon the private property, if feasible, as determined by the Community Development
Director;
that demolition for removal of the existing structures and any grading or earth moving on the
site shall not occur until a building permit has been issued and such site work shall be required
to comply with all the regulations of the Bay Area Air Quality Management District;
that prior to issuance of a building permit for construction of the project, the project construction
plans shall be modified to include a cover sheet listing all conditions of approval adopted by
the Planning Commission, or City Council on appeal; which shall remain a part of all sets of
approved plans throughout the construction process. Compliance with all conditions of
approval is required; the conditions of approval shall not be modified or changed without the
approval of the Planning Commission, or City Council on appeal;
that all air ducts, plumbing vents, and flues shall be combined, where possible, to a single
termination and installed on the portions of the roof not visible from the street; and that these
venting details shall be included and approved in the construction plans before a Building
permit is issued;
that the project shall meet all the requirements of the California Building and Uniform Fire
Codes, in effect at time of building permit submittal, as amended by the City of Burlingame;
3
4
E
6
7
8
I
11
'10. that the project shall comply with the Construction and Demolition Debris Recycling Ordinance
which requires affected demolition, new construction and alteration projects to submit a Waste
Reduction plan and meet recycling requirements; any partial or full demolition of a structure,
interior or exterior, shall require a demolition permit;
EXHIBIT "A"
Conditions of Approval for Categorical Exemption and Design Review
1273 Balboa Avenue
Effective June 2,2022
Page 2
THE FOLLOWING CONDITIONS SHALL BE MET DURING THE BUILDING INSPECTION
PROCESS PRIOR TO THE INSPECTIONS NOTED IN EACH CONDITION:
12 that prior to scheduling the framing inspection the applicant shall provide a certification by the
project architect or residential designer, or another architect or residential design professional,
that demonstrates that the project falls at or below the maximum approved floor area ratio for
the property;
13 that prior to scheduling the foundation inspection, a licensed surveyor shall locate the property
corners, set the building footprint and certify the first-floor elevation of the new structure(s)
based on the elevation at the top of the form boards per the approved plans; this survey shall
be accepted by the City Engineer;
14.that prior to scheduling the framing inspection the project architect or residential designer, or
another architect or residential design professional, shall provide an architectural certification
that the architectural details shown in the approved design which should be evident at framing,
such as window locations and bays, are built as shown on the approved plans; architectural
certification documenting framing compliance with approved design shall be submitted to the
Building Division before the final framing inspection shall be scheduled;
15 that prior to scheduling the roof deck inspection, a licensed surveyor shall shoot the height of
the roof ridge and provide certification of that height to the Building Division; and
16 that prior to final inspection, Planning Division staff will inspect and note compliance of the
architecturat details (trim materials, window type, etc.) to verify that the project has been built
according to the approved Planning and Building plans.