HomeMy WebLinkAboutReso - CC - 147-2019RESOLUTION NO. 147-2019
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BURLINGAME APPROVING
THE PRE -QUALIFIED BIDDER LIST FOR THE COMMUNITY CENTER PROJECT
CONSTRUCTION
CITY PROJECT NO. 83240
WHEREAS, the City of Burlingame Capital Improvement Program includes the
construction of a new Community Center; and
WHEREAS, the City of Burlingame has taken appropriate steps to pre -qualify bidders for
said construction per the Department of Industrial Relations guidelines; and
WHEREAS, a notice was duly published on September 9, 2019 for bids for the pre -
qualification process; and
WHEREAS, on October 16, 2019, the City received seven proposals, which were delivered
to the City Clerk and representatives of the Parks & Recreation Department; and
WHEREAS, City staff and the construction management firm staff reviewed the proposals
for completeness and followed the uniform system of rating provided by the Department of Industrial
Relations guidelines; and
WHEREAS, the following contractors met all the requirements and successfully passed the
pre -qualification process: Alten Construction, BHM Construction Inc., Amoroso Construction, and
Lathrop Construction Associates, Inc.
NOW THEREFORE BE IT RESOLVED by the CITY COUNCIL of the City of Burlingame, California,
which finds, orders and determines that the following contractors are qualified to bid for the construction
of the Community Center project: Alten Construction, BHM Construction Inc., Amoroso Construction,
Lathrop Construction Associates, Inc.
Donna Colson, Mayor
I, Meaghan Hassel -Shearer, City Clerk of the City of Burlingame, certify that the foregoing
Resolution was introduced at a regular meeting of the City Council held on the 18th day of November,
2019, and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: BEACH, BROWNRIGG, COLSON, KEIGHRAN, ORTIZ
NOES: COUNCILMEMBERS: NONE
ABSENT: COUNCILMEMBERS: NONE
Meagher - earer, City Clerk