AUTHORIZING THE CITY MANAGER TO EXECUTE A $620,465 CONSTRUCTION
CONTRACT FOR THE NEIGHBORHOOD STORM DRAIN PROJECT NO. 11
WITH STOLOSKI & GONZALEZ, INC.
CITY PROJECT NO. 85130
WHEREAS, on August 15, 2019, the City issued notice inviting bid proposals for the
Neighborhood Storm Drain Project No. 11, City Project No. 85130; and
WHEREAS, on September 5, 2019, all proposals were received and opened before the
City Clerk and representatives of the Public Works Department; and
WHEREAS, Stoloski & Gonzalez, Inc. submitted the lowest responsible bid for the job in
the amount of $620,465.
NOW, THEREFORE, be it RESOLVED, and ORDERED, that
1. The Plans and Specifications, including all addenda, are approved and adopted; and
2. The bid of Stoloski & Gonzalez, Inc. in the amount of $620,465 is accepted; and
3. That a contract be entered into between the successful bidder and the City of
Burlingame for the performance of said work, and that the City Manager is authorized on behalf
of the City of Burlingame to execute the contract and to approve the faithful performance bond
and the labor materials bond required to be furnished by the contractor.
I, Meaghan Hassel Shearer, City Clerk of the City of Burlingame, certify that the
foregoing Resolution was introduced at a regular meeting of the City Council held on the 161h
day of September, 2019, and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: BEACH, BROWNRIGG, COLSON, KEIGHRAN, ORTIZ
NOES: COUNCILMEMBERS: NONE
ABSENT: COUNCILMEMBERS: NONE