HomeMy WebLinkAboutReso - CC - 078-2019RESOLUTION NO. 78-2019
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BURLINGAME
AWARDING A CONSTRUCTION CONTRACT TO CRATUS INC., FOR EAST
BURLINGAME AVENUE AND ANZA LAGOON BRIDGE UTILITY IMPROVEMENTS
PROJECT AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE
CONSTRUCTION CONTRACT
CITY PROJECT NO. 83522
WHEREAS, on May 13, 2019, the City issued notice inviting bid proposals for the East
Burlingame Avenue and Anza Lagoon Bridge Utility Improvements Project, City Project No.
83522; and
WHEREAS, on June 6, 2019, all proposals were received and opened before the City
Clerk and representatives of the Public Works Department; and
WHEREAS, Cratus Inc. submitted the lowest responsible bid for the job in the amount of
$3,632,704.
and
NOW, THEREFORE, be it RESOLVED and ORDERED,
1. That the Plans and Specifications, including all addenda, are approved and adopted;
2. That the bid of Cratus Inc. for said project in the amount of $3,632,704, is accepted;
and
3. That a contract be entered into between the successful bidder and the City of
Burlingame for the performance of said work, and that the City Manager is authorized on behalf
of the City of Burlingame to execute the contract and to approve the faithful performance bond
and the labor materials bond required to be furnished by the contractor.
N >file
Mayor
I, Meaghan Hassel Shearer, City Clerk of the City of Burlingame, certify that the foregoing
Resolution was introduced at a regular meeting of the City Council held on the 1st day of Jam,
2019, and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: BEACH, BROWNRIGG, COLSON, KEIGHRAN, ORTIZ
NOES: COUNCILMEMBERS: NONE
ABSENT: COUNCILMEMBERS: NONE