Loading...
HomeMy WebLinkAboutReso - PC - 138-2000 I RESOLUTION NO. 138 2 RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF BURLINGAME DETERMINING THAT OVERRIDING CONSIDERATIONS DO NOT OUTWEIGH 3 THE SIGNIFICANT, UNAVOIDABLE, ENVIRONMENTAL IMPACTS OF THE PROPOSED PROJECT OF 488,000 SQUARE FEET OF OFFICE SPACE 4 AT 301 AIRPORT BOULEVARD AND THAT THE PROJECT AS PROPOSED WITH THESE IMPACTS IS NOT CONSISTENT WITH GOALS AND OBJECTIVES OF THE 5 GENERAL PLAN ZONED C-4 — APN: 026-350-070 AND 026-350-090 6 OWNER AND APPLICANT: GLENBOROUGH PARTNERS 7 8 RESOLVED by the PLANNING COMMISSION of the CITY of BURLINGAME that: 9 WHEREAS, the applicant seeks to build a four-building office project of approximately 10 488,000 square feet at 301 Airport Boulevard, which is currently a movie drive-in site; and 11 WHEREAS, pursuant to the California Environmental Quality Act (CEQA), the City of 12 Burlingame as lead agency for the project, prepared an Environmental Impact Report (EIR), and on 13 January 10, 2000, following public hearing, the Planning Commission in Commission Resolution No. 14 16-2000 determined that the Final EIR, consisting of the Draft EIR (dated September 14, 1998), the 15 Recirculated Draft EIR(dated January 21, 1999), the Response to Comments Document (dated April 16 15, 1999), and the Addendum/Supplement to the Response to Comments Document (dated 17 November 12, 1999), was complete pursuant to CEQA Guidelines section 15090 (Title 14, Chapter 18 13 of the California Code of Regulations); and 19 WHEREAS, pursuant to CEQA and the CEQA Guidelines, the Final EIR identified six (6) 20 significant and unavoidable environmental impacts; and 21 WHEREAS, pursuant to CEQA, the CEQA Guidelines, and Resolution No. 16-2000, the 22 Commission could not complete certification of the Final EIR and approve or authorize approval of 23 the proposed project until the Commission made findings pursuant to CEQA Guidelines section 24 15091 and a statement of overriding considerations pursuant to CEQA Guidelines section 15093; and 25 WHEREAS, the applicant revised the project following the January 10, 2000, determination; 26 and 27 WHEREAS, the City reviewed the revision (dated February 11, 2000) pursuant to CEQA; 28 and 1 WHEREAS,on March 27,2000,the Planning Commission held a duly noticed study meeting 2 to ask questions of City staff;and 3 WHEREAS,on May 3,2000,the Planning Commission held a duly noticed public hearing 4 on the nature of the findings and statement of overriding considerations applicable to the project,and 5 WHEREAS,the Commission received and considered all oral and written comments made 6 on the proposed project to the close of the public hearing on May 3,2000;and 7 WHEREAS, it appears that the project as revised following the January 10, 2000, 8 determination does not create any additional adverse environmental impacts nor does it make any 9 identified environmental impacts more significant nor does it interfere or alter the mitigation measures 10 identified in the Final EIR,and therefore,the project as revised following the January 10, 2000, 11 determination is within the scope and analysis of the Final EIR;and 12 WHEREAS, the burden is on the applicant to demonstrate to the Commission that the 13 applicant has no further feasible steps to further reduce the identified, significant, unavoidable 14 environmental impacts of the proposed project and that there are overriding considerations that 15 outweigh those impacts making them"acceptable;"and 16 WHEREAS,the findings contained in Exhibit A hereto show that there are insufficient 17 considerations to outweigh the identified, significant, unavoidable environmental impacts of the 18 proposed project;and 19 WHEREAS,the findings contained in Exhibit A hereto further show that while the project 20 meets the minimum requirements of the Zoning Code and the design guidelines of the Bayfront 21 Guidelines,the overall project and its effects are inconsistent with and would frustrate goals and 22 objectives of the Burlingame General Plan;and 23 WHEREAS,further concerns of the community and the Commission can be found in the 24 actual discussion in the record of these proceedings;and 25 WHEREAS,these determinations make unnecessary any further findings on the infeasibility 26 of further mitigation to further reduce the identified,unavoidable,significant environmental impacts 27 without revisions to the proposed project, 28 2 I NOW, THEREFORE, it is hereby resolved as follows: 2 1. The proposed project with the unavoidable, significant, adverse impacts identified in the 3 Final EIR is not consistent with goals and objectives of the Burlingame General Plan. 4 2. There are insufficient benefits of the project to outweigh the unavoidable, significant, 5 adverse environmental impacts of the project identified in the Final EIR. 6 3. A copy of this resolution shall be provided to the Building Official, the Director of Public 7 Works, and the Bay Conservation and Development Commission., as well as any other responsible 8 agencies. 9 This decision is appealable to the City Council pursuant to the Burlingame Municipal Code 10 and CEQA. Anyone wishing to challenge the decision on this Final EIR in a court of competent 11 jurisdiction must first file such an appeal to the City Council and following the decision of the Council 12 must file any action challenging the decision on the Final EIR in a court of competent jurisdiction 13 within the time limits set forth in the California Environmental Quality Act and the provisions of the 14 CEQA Guidelines as adopted by the State of California (Title 4, Chapter 3 of the California Code of 15 Regulations). 16 This Resolution was adopted by the following vote of the City of Burlingame Planning 17 Commission at a regular meeting of the Planning Commission on May 8 2000: 18 AYES: BOJUES , DEAL , KEIGHRAN , VISTICA 19 NOES: NONE ABSENT: DREILING , LUZURIAGA 20 ABSTAINING: O S T E R L I N G 21 /s 22 Cdnunission cretary 23 24 25 26 27 28 3 I EXHIBIT A 2 FINDINGS REGARDING PROJECT AT 301 AIRPORT 3 4 I. Regarding Overriding Considerations 5 A. The proposed project will not create opportunities to work near where persons live. The size and 6 scale of the project make it probable that large corporate tenants or owners will occupy the 7 buildings making long-distance commuting even more likely. 8 B. The project site is a key Bayfront parcel, and the proposed project fails to sufficiently incorporate 9 the necessary elements to make it a focus of community activities, such as cafes, stores, plazas, 10 and inviting access, and not just a set of office buildings. An example of such a community- I 1 oriented project is Levi Strauss Headquarters in San Francisco. These elements could reduce 12 traffic impacts from the project and the cumulative effect of traffic from the area. 13 C. The proposed project does not possess a sophisticated phasing plan that would allow the owner, 14 the Cities of Burlingame and San Mateo, and the community to evaluate at each appropriate 15 phase how the traffic, parking, and other aspects of the development are actually affecting the 16 community and meeting the predictions and goals established by the Final EIR, the mitigation 17 monitoring plan, transportation system management, and the owners, so that adjustments or 18 corrections could be made at each phase. 19 D. It has not been possible to evaluate the additional conditions proposed by the applicant in the two 20 weeks leading up to the May 3, 2000, hearing as to potential effectiveness, difficulty of 21 implementation and ongoing operation, cost to taxpayers and neighboring property owners, and 22 consistency with other programs. 23 E. The additional revenue that this project will generate as an economic benefit to the City does not 24 counterbalance the effects and expenses of the negative impacts of the project or its associated 25 costs. 26 F. The proposed project does not offer the creativity in design and amenities that would 27 counterbalance the identified, significant environmental impacts nor does it propose sufficient 28 programs or plans that would reduce the traffic impact and housing imbalance. I G. The proposed project is not consistent with the scale of development of the area and 2 neighborhood with regard to floor area ratio. 3 H. There do not appear to be any technological or legal benefits from the proposed project. 4 I. The proposed benefits of the project are focused on the people who would occupy the project 5 site and not on those who live and work in the surrounding community. 6 1 The applicant has not reached agreement with the City of San Mateo on the steps necessary and 7 acceptable to San Mateo to address the Poplar Avenue/Humboldt Street/Amphlett Boulevard 8 traffic impact. 9 K. The proposed project has not been justified by an analysis showing how reductions in size might 10 still make the project profitable while appropriately reducing impacts. No analysis of levels of 11 these thresholds has been provided. 12 L. The impact of the proposed project on air quality may not be reduced by alternative 13 transportation methods and systems,because trip reduction cannot be guaranteed. 14 M. Accepting the applicant's additions to the mitigations/conditions at face value,the net effect of 15 the proposed project would still be detrimental to the community. 16 17 II. Regarding Consistency with General Plan 18 A. A goal of the Burlingame General Plan is to assure that Burlingame will be a"well-rounded"city 19 with residences,schools,business,industry,and space and facilities for social,recreational and 20 cultural activities. An implementing objective is to encourage the establishment of businesses, 21 professional offices,and institutions to serve residents. This proposed project would not appear 22 to serve residents. 23 B. A goal of the Burlingame General Plan is to maintain and strengthen local sources ofrevenue,and 24 an implementing objective is to enhance land values and economic opportunity by providing 25 efficient connections between functional parts of the City and good access to land to permit 26 development of uses appropriate in type and intensity without undue congestion. The proposed 27 project does not serve this objective as shown by the significant,adverse impacts identified in the 28 Final EIR. I C. A goal of the Burlingame General Plan is to enhance the local economy and the prospects for 2 economic well being for all residents, and implementing objectives are to: 3 i. Improve the functional efficiency and safety of the circulation system. 4 ii. Minimize disruptive effects of vehicular movement on the community. 5 iii. Improve the functional efficiency, character and quality of the Central and other business 6 districts. 7 As documented in the Final EIR, the proposed project does not serve these objectives. 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 ADDENDUM TO THE FINAL EIR TABLE 1 COMPARISON OF KEY PARAMETERS, IMPACTS, AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT, REVISED PROJECT, AND THE REVISED REVISED PROJECT Key Parameters / Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq. ft.) (488,000 sq. ft.)I (488,000 sq. ft.) Key Parameters Daily Trip Generation2 (Full 5,497 4,484 4,484 Project) AM Peak-Hour Trips (Full 815 660 660 Project) PM Peak-Hour Trips (Full 793 626 626 Project) Daily Trip Generation 1,544 1,924 1,544 (Phase 1) AM Peak-Hour Trips 218 274 218 (Phase 1) PM Peak-Hour Trips (Phase 1) 216 261 216 Parking Demand 1,776 1,362 1,362 Proposed Parking Supply 2,123 1,6266 1,627 Code-Required Parking 2,121 1,626 1,626 Supply Site Access Four driveways (Main (full access) One (full access) driveway on north frontage of One (full access) driveway on north frontage of driveway, plus second (right turn in/out) site; emergency access to Beach Road (south site; emergency access to Beach Road (south driveway, on north frontage of site ; frontage of site). frontage of site). Secondary (full access) driveway, plus second (right turn in/out) driveway, on east frontage of site. Bicycle Access/Circulation Class II Bike Lane on proiect side of Class II Bike Lanes on both sides of Airport Class II Bike Lanes on both sides of Airport Airport Boulevard along frontage of site. Boulevard along frontage of site. Boulevard along frontage of site. SCH No.98041109/301 Airport Boulevard Final FIR 3 GSA 1980241 March 15, 2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT, REVISED PROJECT, AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) SIGNIFICANT AND UNAVOIDABLE B. Traffic,Circulation and Parkin Impaacts/Mitigation Measures 1. The proposed project would Significant and Unavoidable impact(at Same as Original Project.? The level of impact Versus Original Project: Same Impact. The increase traffic volumes at Phase 2)to existing LOS F condition at the under buildout conditions would be less due to level of impact under buildout conditions would intersections in the project intersection of Poplar Avenue—U.S. 101 the reduced trip generation,but the larger be less due to the reduced trip generation. The area. Southbound Ramps/North Amphlett Road. Phase 1 would cause the significant impact to level of impact under Phase 1 conditions would occur earlier than for the original project, be the same,affecting the timing of affecting the timing of implementation of the implementation of the mitigation measure(see mitigation measure(see Mitigation Measure Mitigation Measure B.1). B.1). Versus Revised Project: Same Impact. The level of impact under buildout conditions would be the same. The level of impact under Phase 1 conditions would be less due to the reduced trip generation,and the significant impact would occur later than the revised project,affecting the timing of implementation of the mitigation measure(see Mitigation Measure B.1). SCH No.98041109/301 Airport Boulevard Final EIR 4 PSA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) Mitigation Measure B./ The City of San Mateo shall install The City of San Mateo shall install regulatory The City of San Mateo shall install regulatory regulatory signs,to be funded by the signs,to be funded by the project applicant, signs,to be funded by the project applicant,prior project applicant,prior to occupancy of prior to occupancy of Phase 1 of the project,at to occupancy of Phase 2 of the project,at the Phase 2 of the project,at the intersection of the intersection of Poplar Avenue—U.S. 101 intersection of Poplar Avenue—U.S. 101 Poplar Avenue—U.S. 101 Southbound Southbound Ramps/North Amphlett Road to Southbound Ramps/North Amphlett Road to Ramps/North Amphlett Road to restrict restrict vehicle movements to and from North restrict vehicle movements to and from North vehicle movements to and from North Amphlett Road north of Poplar Avenue to Amphlett Road north of Poplar Avenue to Amphlett Road north of Poplar Avenue to right-turns in and out only during the a.m. peak right-turns in and out only during the a.m. peak right-turns in and out only during the a.m. hour and the p.m.peak hour. If monitoring of hour and the p.m.peak hour. If monitoring of peak hour and the p.m. peak hour. If traffic conditions reveals that installation of the traffic conditions reveals that installation of the monitoring of traffic conditions reveals that regulatory signs does not successfully achieve regulatory signs does not successfully achieve installation of the regulatory signs does not mitigation of the impact to a less than mitigation of the impact to a less than significant successfully achieve mitigation of the significant level,then the City of San Mateo level,then the City of San Mateo shall install a impact to a less than significant level,then shall install a raised channelizing island,to be raised channelizing island,to be funded by the the City of San Mateo shall install a raised funded by the project applicant. Because the project applicant. Because the mitigation channelizing island,to be funded by the mitigation measure is not within the authority measure is not within the authority of the City of project applicant. Because the mitigation of the City of Burlingame to implement,the Burlingame to implement,the impact is measure is not within the authority of the impact is considered to remain significant. considered to remain significant. City of Burlingame to implement,the impact is considered to remain significant. 3. The proposed project would Significant and Unavoidable impact at the The Significant and Unavoidable impact would Versus Original Project: Same Impact,at same increase traffic volumes on southbound U.S. 101 off-ramp to Broadway occur at Phase 2 of the Revised Project,same Phase 2. The level of impact under buildout freeway ramps in the project (in the a.m.peak hour);traffic operations as with the original project. The level of conditions would be about 20 percent less due to area. would degrade to an unacceptable level impact under buildout conditions of the the reduced trip generation,although the impact (LOS F)at Phase 2 of the project. Revised Project would be about 20 percent less still would be significant. than with buildout of the original project due to the reduced trip generation,although the Versus Revised Project: Same Impact,at same impact still would be significant. Phase 2. The level of impact under buildout conditions would be the same due to the equal trip generation. SCH No.98041109/301 Airport Boulevard Final EIR 5 ESA/980241 March 15.2000 ADDENDUM TO TIIE FINAL EIR. TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)l (488,000 sq.ft.) Mitigation Measure B.3 The project applicant(and any future Same as Original Project. Same as Original and Revised Projects. property owner)shall require building tenants,as part of lease agreements,to Note: Caltrans is currently preparing a Project Note: Caltrans is currently preparing a Project participate in a Transportation Demand Study Report to evaluate the benefits of adding Study Report to evaluate the benefits of adding Management(TDM)program operated by auxiliary lanes along U.S. 101,including in the auxiliary lanes along U.S. 101,including in the the property-owner in order to reduce the section between Millbrae Avenue and Third section between Millbrae Avenue and Third number of project-generated vehicle trips. ' Avenue. The primary purpose of auxiliary Avenue. The primary purpose of auxiliary lanes lanes is to ease the transition of cars entering is to ease the transition of cars entering and and exiting the freeway. Construction of a exiting the freeway. Construction of a southbound auxiliary lane between the southbound auxiliary lane between the Millbrae Millbrae Avenue on-ramp and the Broadway Avenue on-ramp and the Broadway off-ramp off-ramp would improve the traffic operations would improve the traffic operations and is and is likely to reduce the above-described likely to reduce the above-described impact to a impact to a less than significant level.4 less than significant level.4 However,because However,because the mitigation measure is the mitigation measure is not within the authority not within the authority of the City of of the City of Burlingame to implement,the Burlingame to implement,the impact is impact is considered significant. considered significant. SCH No.98041109/301 Airport Boulevard Final EIR 6 ESA/980241 March 15.2000 ADDENDUM TO THE FINAL EIR TABLE I (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) 10. The proposed project would Significant and Unavoidable cumulative Same as Original Project for Poplar Avenue— Versus Original Project: Same Impact for Poplar contribute to cumulative impact at the intersection of Poplar U.S. 101 Southbound Ramps/North Amphlett Avenue—U.S. 101 Southbound Ramps/North traffic increases at Avenue—U.S. 101 Southbound Ramps/ Road. The Revised Project's contribution to Amphlett Road. The contribution to the intersections in the project North Amphlett Road. the cumulative impact would be about three to cumulative impact would be about three to four area. four seconds of delay per vehicle less than the seconds of delay per vehicle less due to the original project due to the reduced trip reduced trip generation. generation. Versus Revised Project: Same Impact for Poplar Avenue—U.S. 101 Southbound Ramps/North Amphlett Road. The contribution to the cumulative impact would be the same due to the equal trip generation. Significant and Unavoidable cumulative Less Than Significant cumulative impact at Versus Original Project: Less Than Significant impact at the intersection of North North Bayshore Boulevard/U.S. 101 cumulative impact at North Bayshore Bayshore Boulevard/U.S. 101 Northbound Northbound Off-Ramp The cumulative p.m. Boulevard/U.S. 101 Northbound Off-Ramp Off-Ramp during the p.m.peak hour(based peak-hour v/c ratio=0.82 with the Revised The cumulative p.m.peak-hour v/c ratio=0.82 on City of San Mateo's level of service Project is less than the City of San Mateo's is less than the City of San Mateo's threshold of threshold of significance [i.e.,LOS D, threshold of significance(v/c=0.85). The significance(v/c=0.85). The cumulative v/c ratio=0.85]). cumulative v/c ratio would be 0.87 with the v/c ratio would be 0.87 with the original project. original project. Versus Revised Project: Less Than Significant cumulative impact at North Bayshore Boulevard/U.S. 101 Northbound Off-Ramp The cumulative p.m.peak-hour v/c ratio=0.82 is less than the City of San Mateo's threshold of significance(v/c=0.85),and is the same as with the Revised Project. SCH No.98041109/301 Airport Boulevard Final EIR 7 ESA/980241 March 15.2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)l (488,000 sq.ft.) Mitigation Measure B.10a Implement Mitigation Measure B.1 Same as Original Project;cumulatively Same as Original and Revised Projects; (installation of regulatory signs;monitoring significant at the intersection of Poplar cumulatively significant at the intersection of of traffic conditions,etc.)at the intersection Avenue—U.S. 101 Southbound Ramps/North Poplar Avenue—U.S. 101 Southbound Ramps/ of Poplar Avenue—U.S. 101 Southbound Amphlett Road. Because the mitigation North Amphlett Road. Because the mitigation Ramps/North Amphlett Road. Because measure is not within the authority of the City measure is not within the authority of the City of the mitigation measure is not within the of Burlingame to implement,the impact is Burlingame to implement,the impact is authority of the City of Burlingame to considered to remain significant. considered to remain significant. implement,the impact is considered to remain significant. Mitigation Measure B.10b Prior to occupancy of Phase 6[buildout]of None Required at the intersection of North Versus Original Project: None Required at the the project,the project applicant shall Bayshore Boulevard/U.S. 101 Northbound intersection of North Bayshore Boulevard/ contribute a fair share toward realignment Off-Ramp;less than significant cumulative U.S. 101 Northbound Off-Ramp;less than of the three separate intersections that impact with the Revised Project. significant cumulative impact with the Revised comprise the intersection of North Revised Project. Bayshore Boulevard and U.S. 101 Northbound Off-Ramp into one signalized Versus Revised Project: Same conclusion(None "T"intersection,with the off-ramp and Required at the intersection of North Bayshore North Bayshore forming the top of the"T", Boulevard/U.S. 101 Northbound Off-Ramp; and an added left-turn lane for traffic less than significant cumulative impact with the traveling from Airport Boulevard or Coyote Revised Revised Project). Point Drive to southbound North Bayshore Boulevard. SCH No.98041109/301 Airport Boulevard Final ETR 8 ESA/980241 March IS,2000 ADDENDUM TO THE FINAL EIR . TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT, REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) 11. The proposed project would Significant cumulative impact on three Significant cumulative impact on two freeway Versus Original Project: Significant cumulative contribute to cumulative freeway segments(from Millbrae Avenue segments(from Millbrae Avenue to Broadway; impact on two freeway segments(from Millbrae traffic increases on the U.S. to Broadway;from Broadway to Anza and from Broadway to Anza Boulevard); Avenue to Broadway;and from Broadway to 101 freeway. Boulevard;and from Peninsula Avenue to traffic operations would degrade to an Anza Boulevard);traffic operations would Poplar Avenue);traffic operations would unacceptable level (LOS F). degrade to an unacceptable level (LOS F). degrade to an unacceptable level (LOS F). Versus Revised Project: Same Impact. Mitigation Measure B.II Caltrans is currently preparing a Project Same as Original Project;cumulatively Versus Original Project: Same Mitigation Study Report to evaluate the benefits of significant,but on two,not three,freeway Measure;cumulatively significant,but on two, adding auxiliary lanes along U.S. 101 segments. Traffic flow on these freeway not three,freeway segments. Traffic flow on between Marsh Road in Menlo Park and segments would be helped by the addition of these freeway segments would be helped by the Grand Avenue in South San Francisco auxiliary lanes by Caltrans. See Footnote 4 for addition of auxiliary lanes by Caltrans. See (auxiliary lanes from Marsh Road to discussion of the auxiliary lanes project. Footnote 4 for discussion of the auxiliary lanes Hillsdale Boulevard are currently under However,because the mitigation measure is project. However,because the mitigation construction). The primary purpose of not within the authority of the City of measure is not within the authority of the City of auxiliary lanes is to ease the transition of Burlingame to implement,the impact is Burlingame to implement,the impact is cars entering and exiting the freeway,thus considered to remain significant. considered to remain significant. improving traffic flow on the freeway.4 However,because the mitigation measure Versus Revised Project: Same Mitigation is not within the authority of the City of Measure;cumulatively significant on same Burlingame to implement,the impact is number of freeway segments. Because the considered significant. mitigation measure is not within the authority of the City of Burlingame to implement,the impact is considered to remain significant. SCH No.98041109/301 Airport Boulevard Final EIR 9 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR. TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT, REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)l (488,000 sq.ft.) 12. The proposed project would Significant and Unavoidable cumulative Same as Original Project Versus Original Pr iect: Same Impact. contribute to cumulative impact at the northbound Anza Boulevard traffic increases on U.S. 101 off-ramp(in the p.m.peak hour),and the rVersus Revised Project: Same Impact. amps. southbound Broadway off-ramp, southbound Poplar Avenue on-ramp and northbound Peninsula Avenue off-ramp(in both peak hours). Mitigation Measure B.12 Implement Mitigation Measures B.3 Same as Original Project. See Footnote 4 for Same as Original and Revised Projects. See (participation in a Transportation Demand discussion of auxiliary lanes to reduce this Footnote 4 for discussion of auxiliary lanes to Management program) impact. Because the mitigation measure is not reduce this impact. Because the mitigation within the authority of the City of Burlingame measure is not within the authority of the City of to implement,the impact is considered Burlingame to implement,the impact is significant. considered significant. C. Air Quality Impacts/Mitigation Measures 4. The proposed project would Significant and Unavoidable cumulative Significant and Unavoidable cumulative Versus Original Project: Significant and contribute to cumulative impact on air quality,because vehicle trip impact on air quality. However,the project's Unavoidable cumulative impact on air quality. mobile-source emissions. emissions of cumulative projects together contribution to cumulative mobile-source However,the project's contribution to with those of the proposed project would emissions would be approximately 18 percent cumulative mobile-source emissions would be exceed 80 pounds per day for ROG,NOx, less than the original project. approximately 18 percent less than the original and PM-10. project. Versus Revised Project: Same Impact. SCH No.98041109/301 Airport Boulevard Final EIR 10 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR . TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) Mitigation Measure G4 a: Implement transit measures to Same as Original Project;Significant Same as Original and Revised Projects; encourage use of public transit to the Unavoidable Significant Unavoidable project site. b: Provide bicycle parking for employees. c: Applicant shall explore the feasibility of extending local"Free Bee"or other shuttle service to the project site,and shall participate financially in any such shuttle service determined to be feasible. d: Implement all traffic circulation improvements identified in Section IIID. SCH No.98041109/301 Airport Boulevard Final EIR I I ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) SIGNIFICANT BUT MITIGABLE B. Traffic,Circulation and Parking Impacts/Mitigation Measures 4. The proposed project would Significant impact due to poor(LOS F) Significant impact due to poor(LOS F)level of Versus Original Project: Significant impact due generate turning movements level of service at the intersection of service at the intersection of Airport Boulevard to poor(LOS F)level of service at the between Airport Boulevard Airport Boulevard and the full-access and the(only)full-access driveway on the intersection of Airport Boulevard and the(only) and the site. driveway on the north side during the p.m. north side during the p.m. peak hour. Average full-access driveway on the north side during the peak hour. The full-access driveway on the intersection delay would be about 33 seconds p.m.peak hour. Average intersection delay east side is projected to operate at LOS A. per vehicle for the Revised Project,versus would be about 33 seconds per vehicle for the about 73 seconds per vehicle for the original Revised Revised Project, versus about project. 73 seconds per vehicle for the original project. Versus Revised Project: Same Impact. Mitigation Measure B.4 The project applicant shall design and The project applicant shall design and install a Same as Revised Project. The project applicant install a traffic signal at the intersection of traffic signal at the intersection of Airport shall design and install a traffic signal at the Airport Boulevard and the full-access Boulevard and the full-access driveway on the intersection of Airport Boulevard and the driveway on the north side of the project north side of the project site prior to occupancy full-access driveway on the north side of the site prior to occupancy of Phase 6 of the of Phase 1 of the project. The traffic signal project site prior to occupancy of Phase 1 of the project. The traffic signal plan is subject to plan is subject to review and approval by the project. The traffic signal plan is subject to review and approval by the City Engineer City Engineer of Burlingame. Upon review and approval by the City Engineer of of Burlingame. Upon acceptance of the acceptance of the traffic signal installation by Burlingame. Upon acceptance of the traffic. traffic signal installation by the Burlingame the Burlingame City Council,the City shall be signal installation by the Burlingame City City Council,the City shall be responsible responsible for the maintenance of the traffic Council,the City shall be responsible for the for the maintenance of the traffic signal. signal. Less than significant after mitigation. maintenance of the traffic signal. Less than Less than significant after mitigation. significant after mitigation. SCH No.98041109/301 Airport Boulevard Final EIR 12 ESA/980241 March IS,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters 1 Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) 13. Cumulative traffic increases in Cumulatively significant increase in delays Cumulatively significant increase in delays for Versus Original Project: Cumulatively the project area would for left turns out of the project site at the left turns out of project site at the intersection significant increase in delays for left turns out of exacerbate delays at the north driveway during the p.m.peak hour. of Airport Boulevard and the(only)full-access project site at the intersection of Airport intersection of Airport The east driveway would continue to driveway on the north side during the p.m. Boulevard and the(only)full-access driveway on Boulevard and the project operate at LOS A. peak hour. the north side during the p.m. peak hour. site's north full-access driveway. Versus Revised Project: Same Impact. Mitigation Measure B.13 Implement Mitigation Measure B.4(install Same as Original Project;less than significant Same as Original and Revised Projects; less than traffic signal) after mitigation. significant after mitigation. 14. The proposed project would Cumulative significant(doubling) increase Cumulative significant(more than doubling) Versus Original Project: Cumulative significant contribute to cumulative in the projected number of accidents on the increase in the projected number of accidents (more than doubling) increase in the projected increases on Airport curve. on the curve. number of accidents on the curve. Boulevard,which would affect traffic safety at the 90-degree Versus Revised Project: Same Impact. curve at Fisherman's Park. Mitigation Measure B.14 The City shall reconstruct Airport Same as Original Project. Due to the higher Versus Original Project: Same Mitigation Boulevard,at Fisherman's Park,to increase level of project traffic on the curve under the Measure. Due to the higher level of project the radius of the 90-degree curve to up to Revised Project(about 1,680 vehicles per hour traffic on the curve under the Revised Revised 300 feet, The project applicant shall [vph]) versus the original project(about Project(about 1,680 vehicles per hour[vph]) contribute its fair share of the cost of this 1,100 vph),the project applicant shall versus the original project(about 1,100 vph),the improvement. Less than significant after contribute a greater share of the cost of this project applicant shall contribute a greater share mitigation. improvement. Less than significant after of the cost of this improvement. Less than mitigation. significant after mitigation. Versus Revised Project: Same Mitigation Measure. Same share of the cost of this improvement. Less than significant after mitigation. SCH No.98041109/301 Airport Boulevard Final EIR 13 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) C. Air Quality Impacts/Mitigation Measures 1. Fugitive dust generated by Significant construction emissions without Although less overall construction would occur Versus Original Project: Although less overall construction activities would implementation of construction emission- under the Revised Project compared to the construction would occur under the Revised be substantial and would control measures. original project,construction emissions would Revised Project compared to the original project, contribute to intermittent similarly be considered significant. construction emissions would similarly be ambient respirable particulate matter concentrations that considered significant. would violate state PM-10 standards. Versus Revised Project: Same Impact. Mitigation Measure C.1 Implement a construction dust-abatement Same as Original Project;Less Than Same as Original and Revised Projects;Less program. Significant after mitigation. Than Significant after mitigation. D. Noise Impacts/Mitigation Measures 1. Construction activities would Significant. Construction noise would be Although less overall construction would occur Versus Original Project: Although less overall intermittently and temporarily generated during all of the proposed under the Revised Project compared to the construction would occur under the Revised generate noise levels above construction phases,but the initial phase of original project;construction noise impacts Revised Project compared to the original project, existing ambient levels in the construction would be more extensive due would be similarly significant. construction noise impacts would be similarly project vicinity. to site grading and preparation, including significant. pile driving. Versus Revised Pr eect: Same Impact. SCH No.98041109/301 Airport Boulevard Final EIR 14 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) Mitigation Measure D.1 a: To reduce construction noise effects, Same as Original Project;except for Mitigation Same as Original Project;except for Mitigation the applicant shall require construction Measure D.le,revised as follows: Measure D.le,below,and same as Revised contractors to limit noisy construction Project: activities to less noise-sensitive times e: To the degree feasible,piles for all phases of the day and week(e.g.,7:00 a.m.to of construction shall be pre-drilled to e: To the degree feasible,piles for all phases of 6:00 p.m.,Monday through Friday; reduce the duration of pile driving activity construction shall be pre-drilled to reduce the 9:00 a.m.to 6:00 p.m.,Saturday;none and vibration caused by pile driving. duration of pile driving activity and vibration on Sunday and holidays). caused by pile driving. b: The applicant shall require contractors Less Than Significant after Mitigation Less Than Significant after Mitigation to muffle all equipment used on the project and to maintain it in good operating condition. All internal combustion engine-driven equipment shall be fitted with intake and exhaust mufflers that are in good condition. This measure should result in all non- impact tools generating a maximum noise level of no more than 85 dBA when measured at a distance of 50 feet. c: Applicant shall require contractors to turn off powered construction equipment when not in use. SCH No.98041109/301 Airport Boulevard Final ETR 15 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)I (488,000 sq.ft.) d: To reduce the noise effects of pile driving,applicant shall require construction contractors to limit pile driving activities to the least noise- sensitive times of the day and week (e.g.,9:00 a.m.to 5:00 p.m.,Monday through Friday,and 10:00 a.m. to 4:00 p.m.,Saturday;none on Sundays and holidays). e: To the degree feasible,piles for all phases of construction shall be pre- drilled to reduce the duration of pile driving activity. 3: The project would constitute a Potentially Significant without Same as Original Project;continues to be Versus Original Project: Same as Original commercial land use in an area incorporation of appropriate materials into Potentially Significant. Project;continues to be Potentially Significant. where noise levels would building design. exceed the normally Versus Revised Project: Same Impact. acceptable planning criteria for such uses. Mitigation Measure D.3 Project design shall meet an interior noise Same as Original Project;Less Than Same as Original and Revised Projects;Less standard of 45 CNEL,as required by the Significant after Mitigation Than Significant after Mitigation general plan. SCH NoA8041109/301 Airport Boulevard Final EIR 16 ESA/980241 March 15,2000 ADDENDUM TO TIIE FINAL EIR- TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.) (488,000 sq.ft.) E. Visual Ouality,Light,and Glare Impacts/Mitigation Measures 2. The project would result in Significant. The overall height and bulk of View blockage of San Bruno Mountain and the Versus Original Project: View blockage of San obstruction of views of San the buildings would result in additional San Bruno Hills,would be similar to the Bruno Mountain and the San Bruno Hills, would Bruno Mountain and the San view blockage of San Bruno Mountain and original project;and would continue to be be similar to the original project; and would Bruno hills as seen from the San Bruno hills Significant. The impacts of the Revised continue to be Significant. The impacts of the northbound U.S. 101 and the Project on other views to and through the site Revised Revised Project on other views to and Coyote Point Recreation Area would be similar to,or less than,those of the through the site would be similar to,or less than, beach. original project because the smaller Revised those of the original project because the smaller Project would generally permit greater visual Revised Project would generally permit greater access through the site. visual access through the site. Versus Revised Project: The gross square footage of the Revised Revised Project is identical to the Revised Project,however, it is shorter than the Revised Project(65 feet to top of parapet for Revised Revised Project,compared to 83.28 feet to top of parapet for Revised Project),but would consist of an additional building(total of four)than the Revised Project (total of three). Resultant impacts of the Revised Revised Project would be similar to the Revised Project. SCH No.98041109/301 Airport Boulevard Final EIR 17 ESA 1980241 March 15,2000 ADDENDUM TO THE FINAL EIR' TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) Mitigation Measure E.2 a: In order to compensate for the loss of Same as Original Project;Less Than Same as Original and Revised Projects;Less views of San Bruno Mountain and the Significant after Mitigation Than Significant after Mitigation San Bruno hills,the project shall include the following: (Proposed as Part of the Project) • a designed landscape perimeter along the public frontages of the project site(i.e.,along Airport Boulevard and the Sanchez Channel); • public pedestrian and bicycle access through the landscaped perimeter of the site; • removal of existing movie screens and other dilapidated on-site structures;and • implementation of an active maintenance program for project landscaping,buildings,and parking areas, including unused areas designated for future phases of the project. b: Applicant shall provide and maintain suitable perimeter screening and ground surface treatments,acceptable to the City Planner,for all areas retained for future phases of development. SCH No.98041109/301 Airport Boulevard Final EIR 18 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL OR- TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)I (488,000 sq.ft.) F. Hydrology and Water ualit Impacts/Mitigation Measures 2. Flooding could occur at the Significant. Seepage of water through the Same as Original Project Versus Original Project: Same as Original project site due to seepage permeable fill bordering the channel along Project;continues to be Significant. through the levees from the the western edge of the site could occur Sanchez Channel and bay,or during periods of high tide and could result Versus Revised Project: Same Impact. from overtopping of levees. in flooding at the site. The first floors of project buildings would be constructed above the surface parking level;and therefore,the occupied portions of the buildings would not be subject to flooding. Mitigation Measure F.2 a: As required by the City,the elevation Same as Original Project;Less Than Same as Original and Revised Projects;Less of the first finished floor of all new Significant after Mitigation Than Significant after Mitigation structures shall be a minimum of+10 feet above MSL. No storage or other occupied area shall be constructed below+10 feet above MSL. b: The fill bordering Sanchez Channel shall be reinforced and a low permeability barrier installed to prevent seepage from the channel onto the project site. c: A qualified engineer shall inspect the area along eastern border of the site, on the Airport Boulevard frontage,to determine the advisability of installing a low-permeability barrier,similar to SCH No.98041109/301 Airport Boulevard Final EIR 19 ESA/980241 March 15.2000 ADDENDUM TO THE FINAL EIR . TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.) (488,000 sq.ft.) that along the west side of the site. If determined advisable by the engineer, the applicant shall submit to the City Engineer for review design plans and specifications for such a barrier on the eastern edge of the site,and shall implement such plans as directed by the City Engineer. d: In addition to Mitigation Measures F.2.a and F.2.b,the following measures shall be incorporated into project design to reduce the potential impacts of flooding: • Tide gates shall be installed in the storm drain system to prevent high water from back-flowing into the site during flood periods. • Adequate drainage,and pump facilities,including a sound-baffled backup power supply,shall be provided in the parking area to prevent ponding. • Storm drainage facilities shall be designed to accommodate any future settlement of the site,and levees and other fill along the site perimeter. SCH No.98041109/301 Airport Boulevard Final EIR 20 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR' TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) • A flood contingency plan shall be developed to provide guidelines for management of vehicles in the event of flooding of the lower parking level. 3. Increased intensity of urban Significant. Increased vehicular use and Same as Original Project. However,since the Versus Original Project: Same as Original uses at the site could result in increased use of landscape chemicals could Revised Project would result in less parking Project. However,since the Revised Project degradation of surface water degrade the quality of runoff leaving the area than the original project,the potential would result in less parking area than the original runoff water quality. site compared to existing conditions. adverse water quality impacts associated with project,the potential adverse water quality parking lot runoff would be reduced compared impacts associated with parking lot runoff would to the original project. be reduced compared to the original project. Versus Revised Project: Same Impact. Mitigation Measure F.3 Parking lot runoff shall be filtered to Same as Original Project;Less Than Same as Original and Revised Projects;Less remove oil and grease prior to Significant after Mitigation Than Significant after Mitigation discharge. b: Runoff from landscaped areas shall be directed into the on-site project storm drain system. 4. Project construction could Significant. Grading and construction Same as Original Project Versus Original Project: Same as Original result in an increase in the activities could contribute to local soil Project. level of sediment,oil,and erosion and an increase in sediment loads grease in runoff from the site. of runoff leaving the site. Versus Revised Project: Same Impact. SCH No.98041109/301 Airport Boulevard Final EIR 21 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters I Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) Mitigation Measure F.4 To reduce the potential for increased Mitigation Measure F.4 revised as follows: Same as Original Project;except for Mitigation contamination of surface flows from the Measure F.4,below,and same as Revised project,prepare and implement a Storm To reduce the potential for increased Project: Water Pollution Prevention Plan(SWPPP) contamination of surface flows from the for the construction phase of the project. project,prepare and implement a Storm Water To reduce the potential for increased The SWPPP shall be submitted for review Pollution Prevention Plan(SWPPP)for the contamination of surface flows from the project, to the City of Burlingame and San Mateo construction phase of the project. The SWPPP prepare and implement a Storm Water Pollution County and shall be approved prior to shall be submitted for review to the City of Prevention Plan(SWPPP)for the construction construction. Burlingame and San Mateo County and shall phase of the project. The SWPPP shall be be approved prior to issuance of a grading submitted for review to the City of Burlingame permit. and San Mateo County and shall be approved prior to issuance of a grading permit. G. Sanitary Sewer Imaacts/MitiQation Measures 2. Under cumulative conditions, Significant. Taking into account Significant. However,required upgrades to the Versus Original Project: Significant. However, the project would contribute to cumulative development,the capacities of study sanitary sewer system would be less than required upgrades to the study sanitary sewer the need for municipal all study sanitary sewer components would the original project. As under the original system would be less than the original project. sanitary sewer improvements. be exceeded,including the 431 Rollins project,the eight-inch main upstream and As under the original project,the eight-inch main Pump Station,the 12-inch main connecting downstream of the 431 Rollins Pump Station upstream and downstream of the 431 Rollins the project site to the sewer main in Rollins would need to be upgraded to 10-inch diameter. Pump Station would need to be upgraded to 10- Road,and the main upstream and The 431 Rollins Pump Station would need to be inch diameter. The 431 Rollins Pump Station downstream of the 431 Rollins Pump upgraded to approximately 610 gallons per would need to be upgraded to approximately Station. minute(less than the 650 gpm upgrade needed 610 gallons per minute(less than the 650 gpm under the original project). No upgrades would upgrade needed under the original project). No be required for the 12-inch main between the upgrades would be required for the 12-inch main project site and Rollins Road. between the project site and Rollins Road. Versus Revised Project: Same Impact. SCH No.98041109/301 Airport Boulevard Final EIR 22 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) Mitigation Measure G.2 As determined necessary by the City As determined necessary by the City through As determined necessary by the City through through monitoring of cumulative monitoring of cumulative wastewater flows at monitoring of cumulative wastewater flows at wastewater flows at the 431 Rollins Pump the 431 Rollins Pump Station,the applicant the 431 Rollins Pump Station,the applicant shall Station,the applicant shall contribute its shall contribute its fair share to 1)upgrade the contribute its fair share to 1)upgrade the 431 fair share to 1)upgrade the 431 Rollins 431 Rollins Pump Station from peak capacity Rollins Pump Station from peak capacity of 600 Pump Station from peak capacity of of 600 gpm to a peak capacity of 610 gpm, gpm to a peak capacity of 610 gpm,2)upgrade 600 gpm to a peak capacity of 650 gpm 2)upgrade 925 linear feet of the sanitary sewer 925 linear feet of the sanitary sewer line located (750 gpm if Alternative 3 is approved),2) line located upstream of the 431 Rollins Pump upstream of the 431 Rollins Pump Station to 10- upgrade the 12-inch main connecting the Station to 10-inch diameter and 3)upgrade 350 inch diameter and 3)upgrade 350 linear feet of project site to the main in Rollins Road to linear feet of the sanitary sewer main located the sanitary sewer main located downstream of 15-inch diameter,3)upgrade 925 linear feet downstream of pump to 10-inch diameter. pump to 10-inch diameter. of the sanitary sewer line located upstream of the 431 Rollins Pump Station to 12-inch Less Than Significant After Mitigation Less Than Significant After Mitigation diameter and 4)upgrade 350 linear feet of the sanitary sewer main located downstream of pump to 12-inch diameter. SCH No.98041109/301 Airport Boulevard Final EIR 23 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR. TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) LESS THAN SIGNIFICANT B. Traffic,Circulation and Parkin IA. The proposed project would Less Than Significant Impact The Revised Project would add less traffic; Versus Original Project: The Revised Revised increase traffic volumes on i.e.,about 650 vehicles per day(vpd)to North Project would add less traffic;i.e.,about residential streets in the Humboldt Avenue and about 336 vpd to North 650 vehicles per day(vpd)to North Humboldt project area. Bayshore Boulevard,versus about 800 vpd and Avenue and about 336 vpd to North Bayshore 410 vpd,respectively,with the original project. Boulevard,versus about 800 vpd and 410 vpd, The impact would continue to be less than respectively,with the original project. The significant. impact would continue to be less than significant. Versus Revised Project: Same Conclusion. 2. The proposed project would Less Than Significant Impact The Revised Project would add less than Versus Original Project: The Revised Revised increase traffic volumes on traffic;i.e.,up to about 225 vehicles per hour Project would add less than traffic; i.e., up to freeway segments in the (vph)to study freeway segments during peak about 225 vehicles per hour(vph) to study project area. traffic hours,versus about 280 vph with the freeway segments during peak traffic hours, original project. The impact would continue to versus about 280 vph with the original project. be less than significant. The impact would continue to be less than significant. Versus Revised Project: Same Conclusion. SCH No.98041109/301 Airport Boulevard Final EIR 24 ESA/980241 March 15.2000 ADDENDUM TO TILE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) 5. The proposed project would Significant impact because parking stalls Less than Significant impact. At the project Versus Original Protect: Less than Significant generate on-site circulation near the northwest and southeast driveways entrance to Airport Boulevard,the parking impact. At the project entrance to Airport within the project parking would create vehicle circulation conflicts circulation aisles would be isolated from the Boulevard,the parking circulation aisles would areas. (with potential traffic safety implications) main project driveway so as not to interfere be isolated from the main project driveway so as between vehicles backing out of these with queued outbound vehicles. not to interfere with queued outbound vehicles. spaces(blocking the driveways) and vehicles exiting the parking area(queuing back from these driveways,and preventing Versus Revised Project: Same Conclusion. vehicles from backing out of their spaces). Mitigation Measure B.5 The project applicant shall design the None Required. Versus Original Project: None Required. layout of parking stalls to reduce conflicts between vehicles exiting via the northwest Versus Revised Project: Same Conclusion. and southeast driveways and vehicles backing out of the stalls near the driveways. 6. The proposed project would Less Than Significant Impact Less Than Significant Impact. On the basis of Versus Original Project: Same Conclusion. generate demand for parking typical ITE parking demand rates,the spaces. estimated peak parking demand for the Revised Versus Revised Project: Same Conclusions Project would be about 1,362 parked vehicles. regarding the sufficiency of the on-site supply to The parking supply should exceed the peak accommodate projected parking demand and to parking demand by approximately 10 percent meet the City's Code required number of parking to account for the difficulty in finding the last spaces. The Revised Revised Project would few available spaces,and the recommended provide the same number of on-site parking supply is about 1,498 spaces. The proposed spaces as the Revised Project,but the dimensions supply of 1,626 on-site parking spaces would of those spaces would meet the City's Code be sufficient to accommodate the projected parking demand. requirements,whereas the Revised Project's proposed use of unistall (smaller)spaces would The City of Burlingame parking code require a variance to Code requirements requirements for an office use is one parking regarding space dimensions. stall per 300 sq. ft.of gross floor area. The SCH No.98041109/301 Airport Boulevard Final EIR 25 ESA/980241 March 15.2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) Code requirement for the Revised Project would be 1,626 stalls,and the on-site parking supply would meet the City's code requirement. 7. The proposed project would Significant impact because the project Less Than Significant Impact. The Revised Versus Original Project: Less Than Significant have an effect on bicycle and would construct a Class II bike lane along Project would construct a Class II bike lane on Impact. The Revised Revised Project would pedestrian access to facilities the two frontages of the project site,but not the site side of Airport Boulevard along the construct a Class II bike lane on the site side of in the area. on the north side of Airport Boulevard two frontages of the project site,and on the Airport Boulevard along the two frontages of the opposite the project site,and increased north side of Airport Boulevard between project site,and on the north side of Airport traffic generated by the project would affect Fisherman's Park and Sanchez Channel. Boulevard between Fisherman's Park and the safety of bicyclists traveling on the Sanchez Channel. north side of Airport Boulevard without a designated Class II bike lane. Versus Revised Project: Same Conclusion. Mitigation Measure B.7 The project applicant shall construct None required(the project applicant now Versus Original Project: None required(the Class II bike lanes,as needed,so that proposes that the original project's Mitigation project applicant now proposes that the original Class II bike lanes exist on both sides of Measure B.7 as part of the Revised Project.) project's Mitigation Measure B.7 as part of the Airport Boulevard along the project site. Revised Revised Project.) Versus Revised Project: Same Conclusion. SCH No.98041109/301 Airport Boulevard Final EIR 26 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR' TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) 8. The proposed project would Less Than Significant Impact Less Than Significant Impact. The Versus Original Project: Less Than Significant increase traffic volumes on consolidation of access driveways into one Impact. The consolidation of access driveways Airport Boulevard,which driveway under the Revised Project would into one driveway under the Revised Revised could affect traffic safety,at increase project traffic volumes on the curve by Project would increase project traffic volumes on the 90-degree curve at about 580 vehicles per day(vpd)above that the curve by about 580 vehicles per day(vpd) Fisherman's Park. projected for the original project(an increase above that projected for the original project(an from about 1,100 vpd to about 1,680 vpd), increase from about 1,100 vpd to about yielding a potential increase in the number of 1,680 vpd),yielding a potential increase in the accidents on the curve of about 0.51 accidents number of accidents on the curve of about 0.51 per year(versus about 0.34 accidents per year accidents per year(versus about 0.34 accidents with the original project). The impact would per year with the original project). The impact continue to be considered less than significant. would continue to be considered less than significant. Versus Revised Project: Same Impact. 9. Construction activity Less Than Significant Impact Same as Original Project;Less Than Versus Original Project: Same Conclusion. associated with the proposed Significant Impact project would temporarily Versus Revised Proiect: Same Conclusion. increase traffic volumes on roadways in the project area. SCH No.98041109/301 Airport Boulevard Final EIR 27 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) C. Air Ouality Impacts/Mitigation Measures 2. The project would result in Less Than Significant Less Than Significant. The Revised Project Versus Original Project: Less Than Significant. increased emissions of criteria would generate approximately 18 percent less The Revised Project would generate pollutants from vehicular emissions of criteria pollutants from vehicular approximately 18 percent less emissions of traffic to and from the project traffic than the original project. criteria pollutants from vehicular traffic than the site. The increase in original project. emissions would not exceed BAAQMD significance criteria for daily emissions of Versus Revised Project: Same impact. NOx,ROG,or respirable particulate matter. 3. Mobile emissions generated Less Than Significant Less Than Significant. The Revised Project Versus Original Project: Less Than Significant. by project traffic would would generate approximately 18 percent less The Revised Project would generate increase CO concentrations at CO concentrations from mobile emissions than approximately 18 percent less emissions of intersections in the project the original project. criteria pollutants from vehicular traffic than the vicinity. original project. Versus Revised Project: Same impact. D. Noise Impacts/Mitigation Measures 2. Project-generated traffic Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original would generate noise that Than Significant. Project;continues to be Less Than Significant. would affect nearby sensitive noise receptors. Versus Revised Project: Same impact. 28 ESA/980241 SCH No.98041109 1301 Airport Boulevard Final EIR March 15,2000 ADDENDUM TO THE FINAL F,IR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) 4. The project,together with Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original cumulative development in the Than Significant. Project;continues to be Less Than Significant. Bayfront area,would contribute to an increase in Versus Revised Project: Same impact. ambient noise levels as a result of motor vehicle traffic. E. Visual Quality,Light,and Glare Impacts/Mitigation Measures 1. The proposed project would Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original alter the visual character of the Than Significant. Project;continues to be Less Than Significant. site. Versus Revised Project: Same impact. 3. The proposed project would Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original potentially cause sun glare off Than Significant. Project;continues to be Less Than Significant. the east-facing building facades for northbound U.S. Versus Revised Project: Same impact. 101 motorists during early morning hours in summer months. 4. Project-related construction Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original activities would be visible Than Significant. Project;continues to be Less Than Significant. from surrounding areas during the construction period. Versus Revised Project: Same impact. 29 ESA/980241 SCH No.98041109/301 Airport Boulevard Final EIR March I5,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)t (488,000 sq.ft.) 5. The proposed project,together Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original with other reasonably Than Significant. Project;continues to be Less Than Significant. foreseeable development in the project area,may have a Versus Revised Project: Same impact. cumulative impact on visual quality. F. Hydrology and Water Quality Impacts/Mitigation Measures 1. The proposed project could Less Than Significant Same as Original Project;continues to be Less Versus Original Project: Same as Original alter the rate and amount of Than Significant. Project;continues to be Less Than Significant. runoff from the site. Versus Revised Project: Same impact. G. Sanitary Sewer Impacts/Mitigation Measures 1. Under Existing Plus Project Significant. Due to the size and shallow Less Than Significant. Total projected Versus Original Project: Less Than Significant. conditions,the project would slope the eight-inch mains upstream and wastewater flows would be at approximately Total projected wastewater flows would be at result in the need for downstream of the 431 Rollins Pump 23 percent less than the original project. No approximately 23 percent less than the original municipal sanitary sewer Station,these eight-inch mains would need upgrades to the study sanitary sewer project. No upgrades to the study sanitary sewer improvements. to be upgraded prior to construction of components would be required under Existing components would be required under Existing Building E(Phase 6)to accommodate the Plus Project conditions. Plus Project conditions. estimated peak wet weather sewage flows. Versus Revised Project: Same impact. SCH No.98041109/301 Airport Boulevard Final EIR 30 FSA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.) (488,000 sq.ft.) Mitigation Measure G.1 Prior to completion of Building E(Phase 6) None Required. None Required. of the project,the developer shall: 1) upgrade approximately 925 linear feet of the eight-inch sewer line located upstream of the 431 Rollins Road Pump Station to 10-inch diameter;and 2)upgrade approximately 350 linear feet of eight-inch main located downstream of pump station to 10-inch diameter. 3. Under Existing Plus Project Less Than Significant Same as Original Project;continues to be Less Same as Original and Revised Projects; conditions,the project would Than Significant. continues to be Less Than Significant. increase wastewater flows to, and increase the need for treatment of wastewater flows at,the Burlingame Wastewater Treatment Plant. 4. Under cumulative conditions, Less Than Significant Same as Original Project;continues to be Less Same as Original and Revised Projects; the project would contribute to Than Significant. continues to be Less Than Significant. cumulative wastewater flows to,and increase the need for treatment of cumulative wastewater flows at,the Burlingame Wastewater Treatment Plant. SCH No.98041109/301 Airport Boulevard Final ETR 31 ESA/980241 March 15,2000 ADDENDUM TO THF,FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)l (488,000 sq.ft.) H. Population,Jobs,and Housing Impacts/Mitigation Measures 1. The project would not reduce Less Than Significant Same as Original Project;continues to be Less Same as Original and Revised Projects; the supply of land available Than Significant. continues to be Less Than Significant. for residential development, and thus would not conflict with the policies and objectives of the City of Burlingame Housing Element. I. Cultural Resources Impacts/Mitigation Measures 1. The project would result in Less Than Significant Same as Original Project;continues to be Less Same as Original and Revised Projects; demolition of the Burlingame Than Significant. continues to be Less Than Significant. Drive-in Theater,a potential architectural resource. 2. Demolition of the Burlingame Less Than Significant Same as Original Project;continues to be Less Same as Original and Revised Projects; Drive-in Theater would Than Significant. continues to be Less Than Significant. constitute the loss of a recreational resource. SCH No.98041109/301 Airport Boulevard Final EIR 32 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS, IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT,REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)I (488,000 sq.ft.) K. Wind and Recreation Impacts/Mitigation Measures 1. The speed of winds passing Less Than Significant Less Than Significant. The shape and the Versus Original Project: over the Project would be orientation of the buildings under the Revised Less Than Significant. The shape and the reduced by the mass of the Project decrease the amount by which wind orientation of the buildings under the Revised proposed group of five speeds would be reduced by the original Revised Project would decrease the amount by buildings with roof heights 52 project. In some areas of the Bay east of the which wind speeds would be reduced by the to 105 feet,and equipment and project site wind speeds would be increased. Original Project. In some areas of the Bay east of mechanical shelters that would the project site wind speeds would be increased. rise approximately 10 feet above the roofs. Versus Revised Project: Less Than Significant. The lower roof heights of the Revised Revised Project would further diminish the amount by which wind speeds would be reduced by the Revised Project. In some areas of the Bay east of the project site wind speeds would be increased. SCH No.98041109/301 Airport Boulevard Final EIR 33 ESA/980241 March 15,2000 ADDENDUM TO THE FINAL EIR TABLE 1 (Continued) COMPARISON OF KEY PARAMETERS,IMPACTS,AND MITIGATION MEASURES FOR THE ORIGINAL PROJECT, REVISED PROJECT,AND THE REVISED REVISED PROJECT Key Parameters/Impacts and Original Project Revised Project Revised Revised Project Mitigations (636,400 sq.ft.) (488,000 sq.ft.)1 (488,000 sq.ft.) 2. The speed of winds passing Less Than Significant Less Than Significant. As was the case with Versus Original and Revised Projects: over the Project combined the original project,introduction of the Less Than Significant. As with the Original and with cumulative development cumulative development would be expected to the Revised Projects,the addition of cumulative of the site at 300 Airport have a noticeable effect on the northernmost development(including 300 Airport Boulevard) Boulevard would be reduced portion of the study area,where the would affect the northernmost portion of the by the combined masses of the accelerations introduced by the project would study area,where the accelerations introduced by two developments. be reduced. The cumulative development the Revised Revised Project would be reduced. should have little effect on the winds in the Cumulative development would have little effect southern portion of the study area,since that for west winds and,to a lesser degree,west- area would be controlled by the project. northwest winds, in the southern portion of the Reducing the mass and/or altering the shape or study area. Reducing the mass and/or altering location of the cumulative development at 300 the shape or location of the cumulative future Airport Boulevard could further diminish development at 300 Airport Boulevard could potentially adverse effects on wind speed. further diminish potentially adverse effects on wind speed. Versus Revised Project: Less Than Significant.The smaller wind effects of the Revised Revised Project would increase the relative magnitude of the potential contribution of future cumulative development (including 300 Airport Boulevard) to overall wind speed reductions in the Bay east of the project site. SOURCE: Environmental Science Associates,2000 34 ESA 1980241 SCH No.98041109/301 Airport Boulevard Final EIR March l5,2000 ENDNOTES t The Burlingame Zoning Code requires that all structures more than 30 inches above grade are included in calculating the gross floor area. By this definition,the escalators and stairways between the ground floor parking level and the elevated lobbies are included,and the gross floor area for the Revised Project is 488,000 sq.ft. If the stairways and escalators had not been included,then the total floor area of the three buildings would be 480,000 sq.ft. With respect to traffic impacts,the difference in trip generation between the two floor areas is negligible,and the effect on judgments about impacts at study locations (intersections,freeway segments and ramps,etc.)is de minimus(i.e.,impacts,and mitigation measures, would be the same using either set of numbers). The project's parking impact would be less than significant under either scenario because the projected parking demand would be fully accommodated by the supply of on-site parking spaces. Documentation of transportation analysis summarized below is provided in Appendix A of this report. Z Although the square footage of the project's floor area would be reduced by about 23%,the percent decrease in trip generation would be somewhat less. Compared to the original project,the revised project would generate approximately 18 to 21%fewer trips. Changes in trip generation rates for office buildings are inversely related to changes in the floor area. Based on extensive survey data on office buildings,it has been established that at higher floor areas,total vehicle trips continue to increase,but trips are generated at a lower rate(per square feet of building floor area)than at a lower level of floor area. This inverse relationship(i.e.,increasing floor area and decreasing trip generation rate)exists for various reasons. For example,service providers(e.g.,FedEx and mail deliveries)can make a reduced number of trips to one site with a large building than to multiple sites with smaller buildings,and with smaller office buildings,tenants generally are unrelated,and each office requires basic support staff (e.g.receptionist,secretary)regardless of the number of employees. As the building size increases,the ratio of support staff to other workers decreases,and more space might be devoted to equipment. 3 The level of impact under buildout conditions would be less due to the reduced trip generation from the lesser square footage,but the larger Phase 1(162,000 gsf vs.122,000 gsf)would cause the significant impact to occur earlier than for the original project,and implementation of the mitigation measure would be required prior to Phase 1 of the Revised Project. 4 Caltrans is currently preparing a Project Study Report to evaluate the benefits of adding auxiliary lanes along U.S.101,including in the section between Millbrae Avenue and Third Avenue. The primary purpose of auxiliary lanes is to ease the transition of cars entering and exiting the freeway. Construction of a southbound auxiliary lane between the Millbrae Avenue on-ramp and the Broadway off-ramp would improve the traffic operations and is likely to reduce the above-described impact to a less than significant level. According to the Draft 1998 Regional Transportation Plan,which is a blueprint to guide transportation investments in the San Francisco Bay Area,the total cost for constructing auxiliary lanes between the Third Avenue interchange in San Mateo and the Grand Avenue interchange in South San Francisco,is$101.2 million. About$55.7 million of the cost has been committed by the San Mateo County Transportation Authority through the Measure A sales tax program(to which the City of Burlingame contributes). The remaining funding is expected to come from other regional discretionary funding sources. The Metropolitan Transportation Commission(MTC)has given high priority to the auxiliary lanes by including this project on the list of"Track 1"projects. About$6.5 billion dollars of Track l funds are available for capital investments in transportation improvements in the San Francisco Bay Area. In deciding which projects would be eligible for Track I funding,MTC gave priority to maintaining the existing transportation system and expanding the regional infrastructure to keep pace with increasing population and employment. In addition,Track 1 funds supplement funding already committed by local sources(e.g.,Measure A funds)to improving the region's transportation system, such as the U.S.101 auxiliary lane project in San Mateo County. Another indication of the high probability that this project will be constructed is that the Third Avenue to Grand Avenue auxiliary lane project is the continuation of providing auxiliary lanes between most interchanges along U.S.101 in San Mateo County;the Marsh Road to Hillsdale Boulevard auxiliary lanes are currently being constructed. With completion of the Third Avenue to Grand Avenue project,auxiliary lanes would be provided between Marsh Road in Menlo Park and Grand Avenue in South San Francisco.