HomeMy WebLinkAboutReso - CC - 155-2018RESOLUTTON NO. 155-2018
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BURLINGAME
AWARDiNG A CONSTRUCTION CONTRACT FOR THE GAROLAN.ROLLINS
EASEMENT SANITARY SEWER MAIN RELOCATION PROJECT TO CRATUS, INC.
AND AUTHORIZING THE CIry MANAGER TO EXEGUTE THE CONTRACT
CITY PROJECT NO.84850
WHEREAS, on October 18, 2018, the City issued notice inviting bid proposals for the
Carolan-Rollins Easement Sanitary Sewer Main Relocation Project, CITY PROJECT NO.
84850; and
WHEREAS, on November 27, 2018, ten proposals were received and opened before the
City Clerk and representatives of the Public Works Department; and
WHEREAS, Cratus, lnc. submitted the lowest responsible bid for the job in the amount
ot V12,975.
NOW, THEREFORE, be it RESOLVED, and it is ORDERED, that the Plans and
Specifications, including all addenda, are approved and adopted; and
BE lT FURTHER RESOLVED that the bid of Cratus lnc., for said project in the amount
of $412,975 is accepted; and
BE 1T FURTHER RESOLVED that a contract be entered into between the successful
bidder and the City of Burlingame for the performance of said work, and that the City Manager is
authorized on behalf of the City of Burlingame to execute said contract and to approve the faithful
performance bond and the labor materials bond required to be furnished by the contractor.
Mayor
l, Meaghan Hassel Shearer, City Clerk of the City of Burlingame, certify that the foregoing
Resolution was introduced at a regular meeting of the City Council held on the 17h day of
December, 2018, and was adopted thereafter by the following vote:
AYES:
NOES:
ABSENT:
COUNCILMEMBERS: BEACH, BROWNRIGG, COLSON, KEIGHRAN, ORTIZ
COUNCILMEMBERS: NONE
COUNCILMEMBERS: NONE