WHEREAS, on August 30, 2017, the City issued a notice inviting bid proposals for the
Lorton Ave Storm Drain Line Cleaning Project, City Project No. 84930; and
WHEREAS, on September 14, 2017, all proposals were received and opened before the
City Clerk and representatives of the Public Works Department; and
WHEREAS, Pipe and Plant Solutions, Inc., submitted the lowest bid in the amount of
$398,477; and
WHEREAS, City staff reviewed the bid proposal of Pipe and Plant Solutions, Inc., and
found it to be responsive and in compliance with the project requirements.
NOW, THEREFORE, be it RESOLVED, and it is hereby ORDERED, that the Plans and
Specifications, are approved and adopted; and
BE IT FURTHER RESOLVED that the bid of Pipe and Plant Solutions, Inc., for said
project in the amount of $398,477 is accepted; and
BE IT FURTHER RESOLVED that a contract be entered into between the successful
bidder and the City of Burlingame for the performance of said work, and that the City Manager is
authorized on behalf of the City of Burlingame to execute said contract and to approve the
faithful performance bond and the labor materials/ nd requi do be fu fished by the
contractor.
I, Meaghan Hassel -Shearer, City Clerk of the Citof Burlingame, do hereby certify that
the foregoing Resolution was introduced at a regular mee ing of the City Council held on the 2ND
day of October, 2017, and was adopted thereafter by the following vote:
AYES: COUNCILMEMBERS: BEACH, BROWNRIGG, COLSON, KEIGHRAN, ORTIZ
NOES: COUNCILMEMBERS: NONE
ABSENT: COUNCILMEMBERS: NONE
rty UI rd'